Summary Introduction
To draw: The pattern test for determining any non-random pattern in observations
Introduction
Pattern test makes an observation of patterns. There are various cases where it can be seen that the patterns show various fluctuations. Noting of patterns in these observations make it quite difficult. Run test is done in this case, where the control chart is divided in three zones. First zone includes the values existed between 2 and 3 standard deviations from the mean. Second zone includes value lying between 1 and 2 standard deviations from the mean. Third zone includes values that exists at less than 1 standard deviation from the mean.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
At Webster Chemical Company, lumps in the caulking compound could cause difficulties in dispensing a smooth bead from the tube. Testing for the presence of lumps destroys the product, so an analyst takes random samples. The following results are obtained:
Tube No.
Lumps
Tube No.
Lumps
Tube No.
Lumps
1
6
5
6
9
0
2
7
6
5
10
5
3
2
7
5
11
2
4
4
8
8
12
3
Determine the c-chart
two-sigma
upper and lower control limits for this process. Is the process in statistical control?
The
UCLc
equals
------
and the
LCLc
equals
------
(Enter
your responses rounded to two decimal
places.)
Auto pistons at Wemming Chung's plant in Shanghai are produced in a forging process, and the diameter is a critical factor
that must be controlled. From sample sizes of 5 pistons produced each day, the mean and the range of this diameter have
been as follows:
Day
Mean (mm)
Range R (mm)
158
4.3
151.2
4.4
155.7
4.2
153.5
4.8
156.6
4.5
What is the UCL using 3-sigma?(round your response to two decimal places).
1.
2.
4.
A production manager at a Contour Manufacturing planthas inspected the number of defective plastic molds in 5 randomsamples of 20 observations each. Following are the number ofdefective molds found in each sample:
Construct a 3-sigma control chart (z = 3) with this information
Chapter 3 Solutions
Operations and Supply Chain Management, 9th Edition WileyPLUS Registration Card + Loose-leaf Print Companion
Ch. 3.S - Prob. 1QCh. 3.S - Prob. 2QCh. 3.S - Prob. 3QCh. 3.S - Prob. 4QCh. 3.S - Prob. 5QCh. 3.S - Prob. 6QCh. 3.S - Prob. 7QCh. 3.S - The Great Lakes Company, a grocery store chain,...Ch. 3.S - Prob. 2PCh. 3.S - Prob. 3P
Ch. 3.S - The Fast Break Computer Company assembles personal...Ch. 3.S - Prob. 5PCh. 3 - Using Sampling and Statistics to Analyze...Ch. 3 - Prob. 2.1ASCCh. 3 - Prob. 3.1ASCCh. 3 - Prob. 4.1ASCCh. 3 - Prob. 5.1ASCCh. 3 - Prob. 1QCh. 3 - Prob. 2QCh. 3 - Prob. 3QCh. 3 - Prob. 4QCh. 3 - Prob. 5QCh. 3 - Prob. 6QCh. 3 - Prob. 7QCh. 3 - Prob. 8QCh. 3 - Prob. 9QCh. 3 - Prob. 10QCh. 3 - Prob. 11QCh. 3 - Prob. 1PCh. 3 - Prob. 2PCh. 3 - Prob. 3PCh. 3 - Prob. 4PCh. 3 - Prob. 5PCh. 3 - Prob. 6PCh. 3 - Prob. 7PCh. 3 - Prob. 8PCh. 3 - Prob. 9PCh. 3 - Prob. 10PCh. 3 - Prob. 11PCh. 3 - Prob. 12PCh. 3 - Prob. 13PCh. 3 - Prob. 14PCh. 3 - Prob. 15PCh. 3 - Prob. 16PCh. 3 - Prob. 17PCh. 3 - Prob. 18PCh. 3 - Prob. 20PCh. 3 - Prob. 21PCh. 3 - Prob. 22PCh. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 26PCh. 3 - Prob. 27PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 34PCh. 3 - Prob. 36PCh. 3 - Prob. 37PCh. 3 - Prob. 38PCh. 3 - Prob. 39PCh. 3 - Prob. 40PCh. 3 - Elon Corporation manufactures parts for an...Ch. 3 - Prob. 42PCh. 3 - Prob. 44PCh. 3 - Prob. 45PCh. 3 - Prob. 46PCh. 3 - Prob. 47PCh. 3 - Metropolitan General Hospital is a city-owned...Ch. 3 - Prob. 50PCh. 3 - Prob. 51PCh. 3 - The Shuler Motor Mile is a high-volume discount...Ch. 3 - Prob. 1.1CPCh. 3 - Prob. 2.1CPCh. 3 - Improving Service Time at Daves Burgers Daves...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Define random sampling error and non samling error, two major type of non sampling error.arrow_forwardThe production manager at Sunny Soda, Inc., is interested in tracking the quality of the company's 12-ounce bottle filling line. The bottles must be filled within the tolerances set for this product because the dietary information on the label shows 12 ounces as the serving size. The design standard for the product calls for a fill level of 12±0.10 ounces. The manager collected the accompanying sample data (in fluid ounces per bottle) on the production process. Click the icon to view the sample data. Click the icon to view the table of factors for calculating three-sigma limits for the xachaR-chart. Design an R- and an x-chart for this process. The UCLR equals 0.371 ounces and the LCLR equals 0.000 ounces. (Enter your responses rounded to three decimal places.) The UCL equals 12.115 ounces and the LCL equals 11.878 ounces. (Enter your responses rounded to three decimal places.) a. Are the process average and range in statistical control? The process average is in statistical control…arrow_forwardmq3arrow_forward
- Need help on calculating control limits for x-bar and r-chart based on the samples below: Sample No X-BAR (Sample Mean) R (Sample Range) X-BAR R 1 28.2151942 9.5450186 2 30.5767201 11.1032318 3 29.0253789 5.52221327 4 29.9431791 6.27087883 5 29.947177 12.7568255 6 29.6848334 11.4927456 7 29.2539019 4.72514932 8 29.6694257 13.9330532 9 30.1590205 6.33461804 10 28.6867307 6.49522527 11 30.5960109 8.13717125 12 29.4390565 5.80286433 13 31.863426 3.40227918 14 32.3716448 8.62217828 15 29.7052597 10.0026916 16 30.0060069 4.25003967 17 32.8491753 4.6515662 18 33.5023103 9.62764088 19 28.1876404 9.6980397 20 30.5043768 6.46724539 21 29.6856417 7.65071069 22 32.5728395 9.2483604 23 28.2363719 7.54975234 24 29.6579999 11.3224787 25 28.1319897 13.213391 26 28.8811004 8.08405181 27 31.6730765 12.9865678 28 28.2078142 5.96315947 29 27.9430689 7.39518992 30 29.6269815 9.48802129 31 34.3599108 7.66563648 32 28.2423234 7.34122645…arrow_forwardA control chart for fraction nonconforming is to be established using a center line of p=0.03. What sample size is required if we wish to detect a shift in the process fraction nonconforming to 0.08 with probability 0.50? 1269 475 73 316 216 2 105 150 265arrow_forward4. Organic Grains LLC uses statistical process control to ensure that its health-conscious, low-fat, multigrain sandwich loaves have the proper weight. Based on a previously stable and in-control process, the control limits of the x- and R-charts are: UCLx = 5.35, LCLx = 4.93; UCLR = 0.894, LCLR = 0. Over the past few days, they have taken five random samples of four loaves each and have found the following: Net Weight Sample Loaf # 1 Loaf # 2 Loaf # 3 Loaf # 4 1 4.9 5.2 5.1 5.0 2 5.3 5.1 5.2 5.3 3 4.9 5.2 4.9 5.2 4 5.5 5.5 5.3 5.5 5 5.3 5.2 5.3 5.0 Part 2 Based on the x-chart, is one or more samples beyond the control limits? ▼ No Yes .arrow_forward
- Boxes of Honey-Nut Oatmeal are produced tocontain 14 ounces, with a standard deviation of .1 ounce. Setup the 3-sigma x-chart for a sample size of 36 boxes.arrow_forwardc) A process manufactures ball bearing whose diameters are normally distributed with mean 2.505cm and standard deviation 0.008cm.Specifications call for the diameter to be in the interval 2.5 ‡ 0.01 cm. estimate the proportion of the ball bearings will meet the specification?arrow_forwardThe Road King Tire Company in Birmingham wants to moni-tor the quality of the tires it manufactures. Each day the com-pany quality-control manager takes a sample of 100 tires, tests them, and determines the number of defective tires. The re-sults of 20 samples have been recorded as follows:Construct a p-chart for this process using 2 limits and for each of the last 30 weekdays are shown as follows:describe the variation in the process. Sample Defectives Sample Defectives1 14 11 182 12 12 103 9 13 194 10 14 205 11 15 176 7 16 187 8 17 188 14 18 229 16 19 2410 17 20 23arrow_forward
- Construct a 3-sigma X-bar chart for the length in centimeters of a part from the following tabble . What is the upper controt limit? sample observation 1 observation 2 observation 3 observation 4 1 0.486 0.499 0.493 0.511 2 0.499 0.506 0.516 0.494 3 0.496 0.5 0.515 0.488 4 0.495 0.506 0.483 0.487 5 0.472 0.502 0.526 0.469 6 0.473 0.495 0.507 0.493 7 0.495 0.512 0.49 0.471 8 0.525 0.501…arrow_forwardBreeze Toothpaste Company has been having a problemwith some of the tubes of toothpaste leaking. The tubes are packedin containers with 100 tubes each. Ten containers of toothpastehave been sampled. Th e following number of toothpaste tubeswere found to have leaks: Develop a p-chart with 3-sigma control limits and evaluatewhether the process is in statistical control.arrow_forward6 of 11 5 3. The manager of a building-supplies company randomly samples incoming lumber to see whether it meets quality specifications. From each shipment, 100 pieces of 2 x 4 lumber are inspected and judged according to whether they are first (acceptable) or second (defective) grade. The proportions of second-grade 2 x 4s recorded for 30 shipments were as follows: a. Construct a control chart for the proportion of second-grade 2 x 4s in samples of 100 pieces of lumber. b. Explain how the control chart can be of use to the manager of the building supplies company. Shipment No. Proportion of second grade 1 0.14 2 0.22 3 0.21 4 0.15 0.19 0.26 7 0.18 8 0.22 9 0.23 10 0.21 11 0.2 12 0.14 13 0.25 14 0.2 15 0.19 16 0.18 17 0.22 18 0.22 19 0.17 20 0.21 21 0.21 22 0.13 23 0.15 24 0.2 25 0.23 26 0.23 27 0.12 28 0.19 29 0.19 30 0.26arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.