Question
Chapter 3, Problem 32P
Summary Introduction
To draw: The control chart and to indicate if the process is in control or not.
Introduction: Statistical process control is a statistical technique used to analyze the functioning of production process. It helps to determine the factors that leads to poor quality in the production process. It also determines the measures that has to be taken in order to correct the production process.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A. Choudhury’s bowling ball factory in Illinois makes
bowling balls of adult size and weight only. The standard devia-tion in the weight of a bowling ball produced at the factory is
known to be 0.12 pounds. Each day for 24 days, the averageweight, in pounds, of nine of the bowling balls produced that dayhas been assessed as follows:
a) Establish a control chart for monitoring the average weights
of the bowling balls in which the upper and lower control lim-its are each two standard deviations from the mean. What are
the values of the control limits?b) If three standard deviations are used in the chart, how do thesevalues change? Why?
Valtec Electronics
Valtec Electronics fills orders for its electronic components and parts by truck to customers through
several distribution centers. A measure of its supply chain responsiveness is order fulfillment lead
time, which is the number of days from when a company receives an order to when it is delivered to
the customer. A distribution center manager has taken 20 samples of 5 orders each during the month
and recorded the lead time for each as follows.
Construct an Xbar chart and R-chart using 30 limits for this data and indicate if the process is in
control.
Load Time (Days)
Load Time (Days)
2.4
Samples
Samples
1
1.3
2.4
0.7
3.0
1.8
15
3.7
7.0
1.4
3.3
2
2.1
1.2
1.0
2.5
3.6
16
3.6
2.7
4.8
2.0
1.7
3
4.2
3.3
2.6
1.5
3.0
17
0.4
1.8
6.5
3.2
4.8
4
1.6
2.1
2.8
0.9
1.5
18
5.3
2.9
3.4
4.8
4.6
5
2.6
3.0
1.4
4.6
1.9
19
2.7
3.6
2.9
4.1
5.2
6
0.8
2.7
5.8
3.7
4.5
20
4.7
2.0
2.0
3.1
1.8
7
2.6
3.5
3.1
3.6
1.4
8
3.4
6.1
1.5
2.5
2.8
9
3.1
2.5
2.2
2.9
1.8
10
2.4
4.8
5.9
3.2
4.4
11
1.9
2.7
3.4…
Webster Chemical’s nominal weight for filling tubes of caulk is 8.00 ounces ± 0.60 ounces. The target process capability ratio is 1.33. The current distribution of the filling process is centered on 8.054 ounces with a standard deviation of 0.192 ounces. Compute the process capability ratios Cp and Cpk to assess whether the filling process is capable and set properly.
Chapter 3 Solutions
Operations and Supply Chain Management, 9th Edition WileyPLUS Registration Card + Loose-leaf Print Companion
Ch. 3.S - Prob. 1QCh. 3.S - Prob. 2QCh. 3.S - Prob. 3QCh. 3.S - Prob. 4QCh. 3.S - Prob. 5QCh. 3.S - Prob. 6QCh. 3.S - Prob. 7QCh. 3.S - The Great Lakes Company, a grocery store chain,...Ch. 3.S - Prob. 2PCh. 3.S - Prob. 3P
Ch. 3.S - The Fast Break Computer Company assembles personal...Ch. 3.S - Prob. 5PCh. 3 - Using Sampling and Statistics to Analyze...Ch. 3 - Prob. 2.1ASCCh. 3 - Prob. 3.1ASCCh. 3 - Prob. 4.1ASCCh. 3 - Prob. 5.1ASCCh. 3 - Prob. 1QCh. 3 - Prob. 2QCh. 3 - Prob. 3QCh. 3 - Prob. 4QCh. 3 - Prob. 5QCh. 3 - Prob. 6QCh. 3 - Prob. 7QCh. 3 - Prob. 8QCh. 3 - Prob. 9QCh. 3 - Prob. 10QCh. 3 - Prob. 11QCh. 3 - Prob. 1PCh. 3 - Prob. 2PCh. 3 - Prob. 3PCh. 3 - Prob. 4PCh. 3 - Prob. 5PCh. 3 - Prob. 6PCh. 3 - Prob. 7PCh. 3 - Prob. 8PCh. 3 - Prob. 9PCh. 3 - Prob. 10PCh. 3 - Prob. 11PCh. 3 - Prob. 12PCh. 3 - Prob. 13PCh. 3 - Prob. 14PCh. 3 - Prob. 15PCh. 3 - Prob. 16PCh. 3 - Prob. 17PCh. 3 - Prob. 18PCh. 3 - Prob. 20PCh. 3 - Prob. 21PCh. 3 - Prob. 22PCh. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 26PCh. 3 - Prob. 27PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 34PCh. 3 - Prob. 36PCh. 3 - Prob. 37PCh. 3 - Prob. 38PCh. 3 - Prob. 39PCh. 3 - Prob. 40PCh. 3 - Elon Corporation manufactures parts for an...Ch. 3 - Prob. 42PCh. 3 - Prob. 44PCh. 3 - Prob. 45PCh. 3 - Prob. 46PCh. 3 - Prob. 47PCh. 3 - Metropolitan General Hospital is a city-owned...Ch. 3 - Prob. 50PCh. 3 - Prob. 51PCh. 3 - The Shuler Motor Mile is a high-volume discount...Ch. 3 - Prob. 1.1CPCh. 3 - Prob. 2.1CPCh. 3 - Improving Service Time at Daves Burgers Daves...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- hw3q3arrow_forwardAnalysis of the output of a process has suggested that the variability is nonrandom on several occasions recently. However, each time an investigation of the process has not revealed any assignable causes. What are some of the possible explanations for not finding any causes?arrow_forwardA team of undergraduate business students was asked to recommend improvement to the data entry process at the county appraiser’s office. The team identified several types of errors, such as posting an incorrect name or entering an incorrect parcel number. The deed abstractors were asked to keep a record of the errors in data entry that were sent to them. The following table is a frequency distribution of errors: Defect Total Posting error in name Posting error in parcel Property sold after tax bills were mailed Inappropriate call transfer (not part of deeds>mapping) Posting error in legal description>incompletelegal description Deeds received after tax bills printed Correspondence errors Miscellaneous errors 23 21 5 18 4 6 2 1 a. Construct a Pareto diagram of these defects in data entry.b. What recommendations would you suggest to the county appraiser?arrow_forward
- 7arrow_forwardA manufacturing company produces steel rods. The length of these rods is critical to their customers. The company aims to manufacture rods with a mean length of 150 cm. However, due to variability in the manufacturing process, the lengths of the rods follow a normal distribution. The company's quality control department samples 30 rods and finds that they have a mean length of 151 cm and a standard deviation of 2 cm. Calculate the Process Capability Index (Cp) and the Process Performance Index (Ppk) for this process. Assume the customer's specification limits are 147 cm and 153 cm for the length of the rods.arrow_forwardhw3q4arrow_forward
- Thirty patients who check out of the Rock Creek County Regional Hospital each week are asked to complete a ques-tionnaire about hospital service. Since patients do not feel well when they are in the hospital, they typically are very critical of the service. The number of patients who indi-cated dissatisfaction of any kind with the service for each 30-patient sample for a 16-week period is as follows:Construct a control chart to monitor customer satisfactionat the hospital using 3 limits and determine if the processis in control.arrow_forwardBill Kime's bowling ball factory makes bowling balls of adult size and weight only. The standard deviation in the weight of a bowling ball produced at the factory is known to be 0.39 pounds. Each day for 24 days, the average weight, in pounds, of 9 of the bowling balls produced that day has been assessed as follows Day 1 2 3 4 5 6 Average (lb) 9.9 9.9 10.1 10.1 99 99 Day 7 8 9 10 11 12 Average (lb) Day Average (b) 13 14 15 16 17 18 10.1 10.0 10.0 10.1 10.1 10.0 9.9 10.1 10.1 10.0 10.1 10.1 Day 19 20 21 22 23 24 Average (lb) 99 10.0 10.1 9.9 10.0 10.0 a) Establish a control chart for monitoring the average weights of the bowling balls in which the upper and lower control limits are each two standard deviations from the mean What are the values of the control limits? Upper Control Limit (UCL)=b (Round your response to two decimal places)arrow_forwardA machine is used to fill cans of motor oil additive. A single sample can is selected every hour and the net weight of the can is obtained. Since the filling process is automated, it has very stable variability, and long experience indicates that s = 0.02 oz. The process target (process mean when in control) is 8.02 oz. A tabular cusum is being used for this process with standardized values h=4.5 and k=0.5. If the values of Cumulative sums at the end of measurement 7 were C," + = 0.030 and C,¯ = 0.0 , and measurement 8 is equal to Xg = 8.071, what will be the Cumulative sum at the end of measurement 8, that is C3 + = ? 0.041 0.071 0.051 0.046 0.061arrow_forward
- com sells books, videos, DVDs, and CDs through its internet Web site. The company ships thousands of orders each day from seven national distribution centers. BooksCDs.com wants to monitor the quality of its distribution process, specifically the number of “problems” orders. A problem order is one that is delivered to a customer late (i.e., after five days), incorrect or incomplete. The company sampled 500 orders every other day for 20 samples and tracked them to final customer delivery. The results of which are as follows: Sample Numbers of Problems Orders Sample Numbers of Problems Orders 1 2 3 4 5 6 7 8 9 10 9 21 18 12 25 41 18 19 26 28 11 12 13 14 15 16 14 22 36 17 38 24 15 12 10 16 17 18 19 20 Construct an appropriate control chart for this process using 3-sigma limits and indicate if the process was out of control. Show work, show how to do the computationarrow_forwardThe IRS is concerned with improving the accuracy of tax information given by its representatives over the telephone. Previous studies involved asking a set of 25 questions of a large number of IRS telephone representatives to determine the proportion of correct responses. Historically, the averageproportion of correct responses has been 72 percent. Recently, IRS representatives have been receiving more training. On April 26, the set of 25 tax questions were again asked of 20 randomly selected IRS telephone representatives. The numbers of correct answers were 18, 16, 19, 21, 20, 16,21, 16, 17, 10, 25, 18, 25, 16, 20, 15, 23, 19, 21, and 19. a. What are the upper and lower control limits for the appropriate p-chart for the IRS? Use z = 3. b. Is the tax information process in statistical control?arrow_forwardArana is a company that produces homemade Rotini pasta. They use statistical process control to monitor the manufacturing process. The company collects five samples, each containing six packs of pasta. Below is the sample data, but the standard deviation of the process output is unknown. If an R chart is created using three-sigma limits (i.e., z = 3) to monitor the variability of products, what would be the upper control limit for this R chart? Sample 1 Sample 2 Sample 3 Pack 1 452.3 451.6 448.6 Sample 4 454.7 Sample 5 448.9 7.614 9.328 11.653 13.427 Pack 2 452.8 451.2 455.6 451.7 453.4 Pack 3 456 454.6 456.5 451 456.7 Pack 4 457.2 455.3 451.9 452.6 456.3 Pack 5 457.8 452.2 455.6 454.7 452.4 Pack 6 451.8 451.9 448.3 458.4 456arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.