Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
12th Edition
ISBN: 9781259580093
Author: William J Stevenson
Publisher: McGraw-Hill Education
bartleby

Concept explainers

Question
Book Icon
Chapter 7.S, Problem 9P

a)

Summary Introduction

To determine: The unit cost for 20 units.

Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.

a)

Expert Solution
Check Mark

Answer to Problem 9P

The unit cost for 20 units is $80.31.

Explanation of Solution

Given information:

Laborcost=$8.50perhourSetupcost=$50.00Materialcost=$20.00perunitLearningcurve=90%

Overhead=50%oflabor,materialsandsetupcostT1=5hoursPurchasecost=$88.50perunit

Formula:

Tn=T1×Unitfactor

Calculation of unit cost for 20 units:

The time to compute the unit cost for 20 units is to compute the average cost for 20 units. It can be computed by finding labor cost, material cost, overhead cost and total cost. From the total cost, the average cost is computed.

Estimation of labor, material, overheads and total cost:

At 90% learning curve, the unit factor for 20 unit is 14.608 (using learning curve coefficient table)

T120=T1×14.608=5×14.608=73.04hours

The time for completing the 20 units is calculated by multiplying 5 with the unit factors 14.608 which yields 73.04 hours.

Laborcost=73.04hours×8.50perhour=$620.84

The labor cost is calculated by multiplying 73.045 hours with 8.50 which yields $620.84.

Materialcost=20units×$20perunit=$400.00

Material cost is calculated by multiplying 20 units with $20 per unit which yields $400.

Overheadcost=0.50×($620.84+$400.00+$50.0)=$535.42

The overhead cost calculated by taking 50% of labor, material and setup cost which accounts to $535.42

Totalcost=Setupcost+Laborcost+Materialcost+Overheadcost=$50+$620.84+$535.42+$400.00=$1,606.26

The total cost is calculated by summing up labor cost, material cost and overhead cost which is adding $50, $620.84, $535.42 and $400.00 which yields $1,606.26.

Averagecostperunit=$1,606.2620=$80.31

The average cost per unit is calculated by dividing $1,606.26 with 20 which yields $80.31.

Hence, the unit cost for 20 units is $80.31.

b)

Summary Introduction

To determine: The minimum production quantity necessary to make the production cost less than the purchase cost.

Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.

b)

Expert Solution
Check Mark

Answer to Problem 9P

The minimum production quantity necessary to make the production cost less than the purchase cost is $88.46.

Explanation of Solution

Given information:

Laborcost=$8.50perhourSetupcost=$50.00Materialcost=$20.00perunitLearningcurve=90%

Overhead=50%oflabor,materialsandsetupcostT1=5hoursPurchasecost=$88.50perunit

Formula:

Tn=T1×Unitfactor

Calculation of minimum production quantity necessary to make the production cost less than the purchase cost:

The production cost per unit is $80.31 per unit for 20 units and it is less than the purchase cost which is $88.50 per unit. By trial and error approach the numbers which accounts to less than the purchase cost is computed which are 10 units.

Estimation of labor, material, overheads and total cost:

At 90% learning curve, the unit factor for 10 unit is 7.994 (using learning curve coefficient table)

T110=T1×7.994=5×7.994=39.97hours

The time for completing 10 units is calculated by multiplying 5 with the unit factors 7.994 which yields 39.97 hours.

Laborcost=39.97hours×8.50perhour=$339.75

The labor cost is calculated by multiplying 39.97 hours with 8.50 which yields $339.75.

Materialcost=10units×$20perunit=$200.00

Material cost is calculated by multiplying 10 units with $20 per unit which yields $200.

Overheadcost=0.50×($339.75+$200.00+$50.0)=$294.88

The overhead cost calculated by taking 50% of labor, material and setup cost which accounts to $294.88

Totalcost=Setupcost+Laborcost+Materialcost+Overheadcost=$50+$339.75+$294.88+$200.00=$884.63

The total cost is calculated by summing up labor cost, material cost and overhead cost which is adding $50, $339.75, $294.88 and $200 which yields $884.63.

Averagecostperunit=$884.6310=$88.46

The average cost per unit is calculated by dividing $884.63 with 10 which yields $88.46 which is less than $88.50.

Hence, the minimum production quantity necessary to make the production cost less than the purchase cost is $88.46.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
At the Ford automobile Highland plant, assume the one-millionth vehicle was produced in 1916 at a cost of $8084 (in 2013 US$), by how much did the Ford company reduce his cost with each doubling of cumulative output from 1916 to 1927?
At the Ford automobile Highland plant,in 1913, how long did the average worker stay with the plant and what was the average tenure of a worker?
Community Federal Bank in Dothan, Alabama, recently increased its fees to customers who use employees as tellers. Management is interested in whether its new tee policy has increased the number of customers now using its automatic teller machines to that point that more machines are required. The following table provides the number of automatic teller transactions by week. Use trend projection with regression to forecast usage for weeks 13-16.

Chapter 7 Solutions

Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)

Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Understanding Management (MindTap Course List)
Management
ISBN:9781305502215
Author:Richard L. Daft, Dorothy Marcic
Publisher:Cengage Learning
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Management, Loose-Leaf Version
Management
ISBN:9781305969308
Author:Richard L. Daft
Publisher:South-Western College Pub
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College