Question
Chapter 7.S, Problem 16P
Summary Introduction
To determine: The number of repetitions needed to achieve the standards.
Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The time study of a work operation at a restaurant yielded an observed time of 4 minutes. The analysis rated the observed worker at 85%. This means the worker performed at 85% of normal when the study was made. The firm uses a 13% allowance factor. The restaurant wants to compute the normal time and the standard time for this operation;
From a time study, the worker’s average observed time for a particular task is shown to be 5.6 minutes. The analyst feels the worker was performing their task, on average, about 25% faster than normal. What would be the resulting standard time assuming a 20% allowance for fatigue and personal needs?
United Research Associates (URA) had received a contract to produce two units of a new cruise missile guidance control. The ?rst unit took 4,000 hours to complete and cost $30,000 in materials and equipment usage. The second took 3,200 hours and cost $21,000 in materials and equipment usage. Labor cost is charged at $18 per hour.The prime contractor has now approached URA and asked to submit a bid for the cost of producing another 20 guidance controls.a. What will the last unit cost to build?b. What will be the average time for the 20 missile guidance controls?c. What will the average cost be for guidance control for the 20 in the contract?
Chapter 7 Solutions
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
Ch. 7.S - Prob. 1DRQCh. 7.S - Prob. 2DRQCh. 7.S - Prob. 3DRQCh. 7.S - Prob. 4DRQCh. 7.S - Prob. 5DRQCh. 7.S - Prob. 6DRQCh. 7.S - Prob. 7DRQCh. 7.S - Prob. 8DRQCh. 7.S - Prob. 9DRQCh. 7.S - Prob. 10DRQ
Ch. 7.S - Prob. 1PCh. 7.S - Prob. 2PCh. 7.S - Prob. 3PCh. 7.S - Prob. 4PCh. 7.S - Prob. 5PCh. 7.S - Prob. 6PCh. 7.S - Prob. 7PCh. 7.S - Prob. 8PCh. 7.S - Prob. 9PCh. 7.S - Prob. 10PCh. 7.S - Prob. 11PCh. 7.S - Prob. 12PCh. 7.S - Prob. 13PCh. 7.S - Prob. 14PCh. 7.S - Prob. 15PCh. 7.S - Prob. 16PCh. 7.S - Prob. 17PCh. 7.S - Prob. 18PCh. 7.S - Prob. 19PCh. 7.S - Prob. 1CQCh. 7.S - Prob. 2CQCh. 7.S - Prob. 3CQCh. 7 - Prob. 1DRQCh. 7 - What are some of the main advantage and...Ch. 7 - Prob. 3DRQCh. 7 - Prob. 4DRQCh. 7 - Prob. 5DRQCh. 7 - Prob. 6DRQCh. 7 - Prob. 7DRQCh. 7 - What are motion study principles? How are they...Ch. 7 - Prob. 9DRQCh. 7 - Prob. 10DRQCh. 7 - Prob. 11DRQCh. 7 - Prob. 12DRQCh. 7 - Prob. 13DRQCh. 7 - Prob. 14DRQCh. 7 - Prob. 15DRQCh. 7 - Prob. 16DRQCh. 7 - Prob. 17DRQCh. 7 - Prob. 18DRQCh. 7 - Prob. 19DRQCh. 7 - Prob. 1TSCh. 7 - Prob. 2TSCh. 7 - Prob. 3TSCh. 7 - Prob. 1CTECh. 7 - Prob. 2CTECh. 7 - Prob. 1PCh. 7 - Prob. 2PCh. 7 - Prob. 3PCh. 7 - Given these observed times (in minutes) for four...Ch. 7 - Prob. 5PCh. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Prob. 9PCh. 7 - Prob. 10PCh. 7 - Prob. 11PCh. 7 - Prob. 12PCh. 7 - Prob. 13PCh. 7 - An analyst made the following observations about...Ch. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - Prob. 19PCh. 7 - Prob. 1CQCh. 7 - Prob. 2CQCh. 7 - Prob. 3CQCh. 7 - Prob. 4CQ
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- After training, Mary Fernandez, a computer technician, had an average observed time for memory-chip tests of 12 seconds. Mary's performance rating is 95%. The firm has a personal fatigue and delay allowance of 12%. a) The normal time for this process = seconds (round your response to two decimal places). b) The standard time for this process = seconds (round your response to two decimal places).arrow_forwardWhat are the main purposes of measuring work in order to establish working time standards?arrow_forwardThe “worker” in this scenario had to perform a candy-sorting task and the rest of the class had to record the observed times (OT) for the task. It was decided that the rating for the “worker” was 100%. Given the following table, find the standard time for each element. Write your answers in order from Element #1 --> Element #5. Answers must have one decimal place: e.g. 3.0 or 12.5. Round up if necessary. Assume a total allowance of 5%. In your equation you will use for ST, consider allowance to be 0.05. Element Trail 1 Trial 2 Standard Time 1 Walk to podium 3 sec 3 sec 2 Fill mug 5 sec 6 sec 3 Walk to desk/sit 5 sec 4 sec 4 Sort Candy 12 sec 12 sec 5 Walk to desk 4 sec 4 secarrow_forward
- You want to know the standard time of a welding process. The analyst has obtained the followingi information: average timed time - 1.30 minutes rhythm assessment - 110 fixed supplements - 5% variable supplements - 2% Determine the standard time, in minutes, of the welding process: a) 143 min b) 145 min c) 150 min d) 153 minarrow_forwardAt Dominos pizza the time study restaurant yielded an average observed time of 4.0 minutes. The analyst rates the observed worker at 85%.this means the worker performed at 85% of normal when the study was made. The firm uses a 13% allowance factor. What is the standard time for this operation. 9.3 min 3.4 min ✓ 3.9 min 3.8 minarrow_forwardA worker-machine operation was found to involve 3.3 minutes of machine time per cycle in the course of 40 cycles of stopwatch study. The worker’s time averaged 1.9 minutes per cycle, and the worker was given a rating of 120 percent (machine rating is 100 percent). Midway through the study, the worker took a 10-minute rest break. Assuming an allowance factor of 12 percent of work time, determine the standard time for this job.arrow_forward
- After training, Mary Fernandez, a computer technician, had an average observed time for memory-chip tests of 15 seconds. Mary's performance rating is 105%. The firm has a personal fatigue and delay allowance of 12%. a) The normal time for this process = seconds (round your response to two decimal places). b) The standard time for this process =seconds (round your response to two decimal places).arrow_forwardThe snapback timing method was used to obtain the average times and performance ratings for work elements in a manual repetitive task. (See table below). All elements are worker-controlled and were performance rated at 80%. Element e is an irregular element performed every five cycles. A 15% allowance for personal time, fatigue, and delays isapplied to the cycle. Determine (a) the normal time and (b) the standard time for this cycle. If the worker’s performance during actual production is 120% on all manual elements for 7 actual hours worked on an 8-hour shift, (c) how many units will be producedarrow_forwardA recently negotiated union contract allows workers in a shipping department 24 minutes for rest, 10 minutes for personal time, and 14 minutes for delays for each four hours worked. A time study analyst observed a job that is performed continuously and found an average time of 6.0 minutes percycle for a worker she rated at 95 percent. What standard time is applicable for that operation?arrow_forward
- Of the session management best practices, which are the top three in importance? Describe each best practice with some detail.arrow_forwardA customer service department has the following resolution response time data: Average Response Time First contact 0.25 hr. Service scheduling 0.50 hr. Wait for service 24.00 hrs. Service 1.50 hrs. Total resolution time 26.25 hrs. What is the value-added ratio (rounded to one decimal place) in this process? a. 8.6% b. 91.4% c. 5.7% d. 28.6%arrow_forwardA Methods and Measurements Analyst needs to develop a time standard for a certain task. The task involves use of a ruler, square, and portable electric saw to mark and cut the "notch" in a rafter (a standard carpentry task of home construction). In a preliminary study, he observed one of his workers performing this task five times. The observations were made in an air-conditioned, well-lit training facility, at ground level, with all tools and equipment clean and readily available. Observation: 1 2 3 4 5 Task time (seconds): 82 74 80 83 76 a. What is the actual average time for this task? b. What is the normal time for this task if the employee worked at a 20% faster pace than is typical for adequately trained workers? c. What is standard time for this task if allowances sum to 14%? d. If the analyst then thought more carefully about his experiment and decided that the allowances needed to be increased to match the real (outside, not air-conditioned)…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.