Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
12th Edition
ISBN: 9781259580093
Author: William J Stevenson
Publisher: McGraw-Hill Education
Question
Book Icon
Chapter 7.S, Problem 8P

a)

Summary Introduction

To determine: The duration needed to finish last unit.

Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.

a)

Expert Solution
Check Mark

Answer to Problem 8P

The duration needed to finish last unit is 11.35 hours.

Explanation of Solution

Given information:

T5=14.5hoursTotalunits=25Learningcurve=90%

Formula:

Tn=T1×Unitfactor

Calculation of duration needed to finish last unit:

Time to complete last unit can be calculate by computing the time of completion of first unit and then computing the time to complete last unit.

Estimation of time to complete first unit:

At 90% learning curve, the unit factor for 1 unit is 0.783 (using learning curve coefficient table)

T5=T1×0.783600=T1×0.783T1=14.50.783=18.52hours

The time for completing the first unit is calculated by dividing 14.5 with the unit factors 0.783 which yields 18.52 hours.

Estimation of time to last unit:

At 90% learning curve, the unit factor for 25 units are 0.613 (using learning curve coefficient table)

T25=T1×Timefactor=18.52×0.613=11.35hours

The time for completing last unit (25th units) is calculated by multiplying 18.52 with the unit factors 0.613 which yields 11.35 hours.

Hence, the duration needed to finish last unit is 11.35 hours.

b)

Summary Introduction

To determine: The duration needed to finish tenth unit.

Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.

b)

Expert Solution
Check Mark

Answer to Problem 8P

The duration needed to finish tenth unit is 13.06 hours.

Explanation of Solution

Given information:

T5=14.5hoursTotalunits=25Learningcurve=90%

Formula:

Tn=T1×Unitfactor

Estimation of duration needed to finish tenth unit:

At 90% learning curve, the unit factor for tenth unit is 0.705.

Tn=T1×Unitfactor=18.52×0.705=13.06hours

The time for completing tenth units is calculated by multiplying 18.52 with 0.705 which yields 13.06 hours.

Hence, the duration needed to finish tenth unit is 13.06 hours.

c)

Summary Introduction

To estimate: The average time per unit for 25 units.

Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.

c)

Expert Solution
Check Mark

Answer to Problem 8P

The average time per unit for 25 units is 13.12 hours.

Explanation of Solution

Given information:

T5=14.5hoursTotalunits=25Learningcurve=90%

Formula:

Tn=T1×Unitfactor

Calculation of average time per unit for 25 units:

The average time per unit for 25 units is calculated by computing the duration for all 25 units and taking average for the durations.

Estimation of time to complete 25 units:

At 90% learning curve, the unit factor for 25 units is 17.713.

T125=T1×Timefactor=18.52×17.713=328.04hours

The duration for 25 units is calculated by multiplying 18.52 with 17.713 which yields 328.04 hours.

Estimation of average time of 25 units:

Averagetime=328.0425=13.12hours

The average time for 25 units is calculated by dividing 328.04 with 25 which gives 13.12 hours.

Hence, the average time per unit for 25 units is 13.12 hours.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Discuss how training and development programs can be best presented to ultimately change the behavior of employees, often without their knowledge or awareness.
Doctor E
Considering contemporary challenges in business, analyze a real-world case where a company successfully navigated a major shift in its marketing strategy to adapt to changing market dynamics. Discussion Question and Prompt: Identify the key factors that contributed to the success of their marketing strategy in the face of contemporary issues. How can businesses draw insights from this case to inform their own marketing strategies amid current business challenges?

Chapter 7 Solutions

Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)

Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Understanding Management (MindTap Course List)
Management
ISBN:9781305502215
Author:Richard L. Daft, Dorothy Marcic
Publisher:Cengage Learning
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
Management, Loose-Leaf Version
Management
ISBN:9781305969308
Author:Richard L. Daft
Publisher:South-Western College Pub
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,