a)
To determine: The duration needed to finish last unit.
Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.
a)
Answer to Problem 8P
Explanation of Solution
Given information:
Formula:
Calculation of duration needed to finish last unit:
Time to complete last unit can be calculate by computing the time of completion of first unit and then computing the time to complete last unit.
Estimation of time to complete first unit:
At 90% learning curve, the unit factor for 1 unit is 0.783 (using learning curve coefficient table)
The time for completing the first unit is calculated by dividing 14.5 with the unit factors 0.783 which yields 18.52 hours.
Estimation of time to last unit:
At 90% learning curve, the unit factor for 25 units are 0.613 (using learning curve coefficient table)
The time for completing last unit (25th units) is calculated by multiplying 18.52 with the unit factors 0.613 which yields 11.35 hours.
Hence, the duration needed to finish last unit is 11.35 hours.
b)
To determine: The duration needed to finish tenth unit.
Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.
b)
Answer to Problem 8P
Explanation of Solution
Given information:
Formula:
Estimation of duration needed to finish tenth unit:
At 90% learning curve, the unit factor for tenth unit is 0.705.
The time for completing tenth units is calculated by multiplying 18.52 with 0.705 which yields 13.06 hours.
Hence, the duration needed to finish tenth unit is 13.06 hours.
c)
To estimate: The average time per unit for 25 units.
Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.
c)
Answer to Problem 8P
Explanation of Solution
Given information:
Formula:
Calculation of average time per unit for 25 units:
The average time per unit for 25 units is calculated by computing the duration for all 25 units and taking average for the durations.
Estimation of time to complete 25 units:
At 90% learning curve, the unit factor for 25 units is 17.713.
The duration for 25 units is calculated by multiplying 18.52 with 17.713 which yields 328.04 hours.
Estimation of average time of 25 units:
The average time for 25 units is calculated by dividing 328.04 with 25 which gives 13.12 hours.
Hence, the average time per unit for 25 units is 13.12 hours.
Want to see more full solutions like this?
Chapter 7 Solutions
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
- The supply chain is a conventional notion, but organizations are only really interested in making products that they can sell to customers. Provided they have reliable supplies of materials and reasonable transport for finished products, logistics is irrelevant. Do you think this is true? If yes, explain, and if no, clearly explain as well.arrow_forwardworking as a program operations managerarrow_forward12 X1, X230 1 x =0x2 write the Following linear Programming model by 1- general Form Canonical Forms Canonical formY 2- Standard Form Max Z=35X+ 4 X 2 +6 X3 ST. X+2X2-5x3 = 40 3X, + 6X2 + 7x 3 = 30 7x, +lox2 x3 = 50 X3 X 2 X 3 <0arrow_forward
- a/ a Minimum cost assign each worker for one job at Jobs J1 12 33 WI 2 4 6 W2 5 W3 5 33 6 7arrow_forwardوبة واضافة هذه القيمة الى القيم Ex: Assign each job for each worker at minimum total Cost عمل لكل عامل وبأقل كلفة ممكنة obs الأعمال Workors العمال J1 J2 J3 J4 W₁ 15 13 14 12 W2 11 12 15 13 W3 13 12 10 11 W4 15 17 14 16arrow_forwardThe average completion time (flow time) for the sequence developed using the FCFS rule = 11.75 days (round your response to two decimal places). The percentage utilization for the sequence developed using the FCFS rule = 42.55 % (enter your response as a percentage rounded to two decimal places). b) Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): An Alabama lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left: Job Due Date A 212 B 209 C 208 D 210 Duration (days) 6 3 3 8 Sequence 1 Job B 2 3 4 A D The average tardiness (job lateness) for the sequence developed using the SPT rule = 5.00 days (round your response to two decimal places). The average completion time (flow time) for the sequence developed using the SPT rule = 10.25 days…arrow_forward
- With the aid of examples, fully discuss any five (5) political tactics used in organisations.arrow_forwarda. With the aid of examples, define discrimination. b. Fully discuss any four (4) types of discrimination in the workplacearrow_forwardRead the Following Extract and Answer the Questions that Follows:The word politics has a somewhat negative connotation. It suggests that someone is attempting touse means or to gain ends that are not sanctioned by the organisation. Political behaviour, as we’vedefined it is quite neutral. Similarly, power is not inherently negative. Whether a person viewspower and politics as unsavoury topics depends on several considerations, most important perhapsbeing where the individual stands on a specific issue in each situation. Nonetheless, most managersare reluctant to admit to political character of their own work settings.Discuss any Five (5) Political tactics you know.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.