Chapter 7.S, Problem 9P

a)

Summary Introduction

To determine: The unit cost for 20 units.

Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.

a)

Expert Solution
Check Mark

Answer to Problem 9P

The unit cost for 20 units is $80.31.

Explanation of Solution

Given information:

Laborcost=$8.50perhourSetupcost=$50.00Materialcost=$20.00perunitLearningcurve=90%

Overhead=50%oflabor,materialsandsetupcostT1=5hoursPurchasecost=$88.50perunit

Formula:

Tn=T1×Unitfactor

Calculation of unit cost for 20 units:

The time to compute the unit cost for 20 units is to compute the average cost for 20 units. It can be computed by finding labor cost, material cost, overhead cost and total cost. From the total cost, the average cost is computed.

Estimation of labor, material, overheads and total cost:

At 90% learning curve, the unit factor for 20 unit is 14.608 (using learning curve coefficient table)

T120=T1×14.608=5×14.608=73.04hours

The time for completing the 20 units is calculated by multiplying 5 with the unit factors 14.608 which yields 73.04 hours.

Laborcost=73.04hours×8.50perhour=$620.84

The labor cost is calculated by multiplying 73.045 hours with 8.50 which yields $620.84.

Materialcost=20units×$20perunit=$400.00

Material cost is calculated by multiplying 20 units with $20 per unit which yields $400.

Overheadcost=0.50×($620.84+$400.00+$50.0)=$535.42

The overhead cost calculated by taking 50% of labor, material and setup cost which accounts to $535.42

Totalcost=Setupcost+Laborcost+Materialcost+Overheadcost=$50+$620.84+$535.42+$400.00=$1,606.26

The total cost is calculated by summing up labor cost, material cost and overhead cost which is adding $50, $620.84, $535.42 and $400.00 which yields $1,606.26.

Averagecostperunit=$1,606.2620=$80.31

The average cost per unit is calculated by dividing $1,606.26 with 20 which yields $80.31.

Hence, the unit cost for 20 units is $80.31.

b)

Summary Introduction

To determine: The minimum production quantity necessary to make the production cost less than the purchase cost.

Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.

b)

Expert Solution
Check Mark

Answer to Problem 9P

The minimum production quantity necessary to make the production cost less than the purchase cost is $88.46.

Explanation of Solution

Given information:

Laborcost=$8.50perhourSetupcost=$50.00Materialcost=$20.00perunitLearningcurve=90%

Overhead=50%oflabor,materialsandsetupcostT1=5hoursPurchasecost=$88.50perunit

Formula:

Tn=T1×Unitfactor

Calculation of minimum production quantity necessary to make the production cost less than the purchase cost:

The production cost per unit is $80.31 per unit for 20 units and it is less than the purchase cost which is $88.50 per unit. By trial and error approach the numbers which accounts to less than the purchase cost is computed which are 10 units.

Estimation of labor, material, overheads and total cost:

At 90% learning curve, the unit factor for 10 unit is 7.994 (using learning curve coefficient table)

T110=T1×7.994=5×7.994=39.97hours

The time for completing 10 units is calculated by multiplying 5 with the unit factors 7.994 which yields 39.97 hours.

Laborcost=39.97hours×8.50perhour=$339.75

The labor cost is calculated by multiplying 39.97 hours with 8.50 which yields $339.75.

Materialcost=10units×$20perunit=$200.00

Material cost is calculated by multiplying 10 units with $20 per unit which yields $200.

Overheadcost=0.50×($339.75+$200.00+$50.0)=$294.88

The overhead cost calculated by taking 50% of labor, material and setup cost which accounts to $294.88

Totalcost=Setupcost+Laborcost+Materialcost+Overheadcost=$50+$339.75+$294.88+$200.00=$884.63

The total cost is calculated by summing up labor cost, material cost and overhead cost which is adding $50, $339.75, $294.88 and $200 which yields $884.63.

Averagecostperunit=$884.6310=$88.46

The average cost per unit is calculated by dividing $884.63 with 10 which yields $88.46 which is less than $88.50.

Hence, the minimum production quantity necessary to make the production cost less than the purchase cost is $88.46.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
The annual demand for water bottles at Mega Stores is 500 units, with an ordering cost of Rs. 200 per order. If the annual inventory holding cost is estimated to be 20%. of unit cost, how frequently should he replenish his stocks? Further, suppose the supplier offers him a discount on bulk ordering as given below. Can the manager reduce his costs by taking advantage of either of these discounts? Recommend the best ordering policy for the store. Order size Unit cost (Rs.) 1 – 49 pcs. 20.00 50 – 149 pcs. 19.50 150 – 299 pcs. 19.00 300 pcs. or more 18.00
Help answer showing level work and formulas
I need to forecast using a 3-Period-Moving-Average-Monthly forecasting model which I did but then I need to   use my forecast numbers to generate a Master Production Schedule (MPS)  I have to Start with actual sales (my own test data numbers) for August-2022 Oct-2022 i need to create MPS to supply demand starting November-2022  April 2023  I just added numbers without applying formulas to the mps on the right side of the spreadsheet because I do not know how to do it. The second image is the example of what it should look like. Thank You.

Chapter 7 Solutions

Operations Management

Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.