Operations Management
13th Edition
ISBN: 9781259667473
Author: William J Stevenson
Publisher: McGraw-Hill Education
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 7.S, Problem 4P
Summary Introduction
To estimate: The amount of time needed to complete the third and fourth unit.
Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A job is known to have a learning percentage equal to 82. If the first unit had a completion time of20 hours, estimate the times that will be needed to complete the third and fourth units.
The first unit of a job took 40 hours to complete. The work has a learning percentage of 88. The manager wants time estimates for units 2, 3, 4, and 5. Develop those time estimates.
The product S takes 67 hours for production of 1 unit, where learning curve rate is 67% and what will be the total time taken by 4th unit of product S using incremental unit time method ?
Chapter 7 Solutions
Operations Management
Ch. 7.S - Prob. 1DRQCh. 7.S - Prob. 2DRQCh. 7.S - Prob. 3DRQCh. 7.S - Prob. 4DRQCh. 7.S - Prob. 5DRQCh. 7.S - Prob. 6DRQCh. 7.S - Prob. 7DRQCh. 7.S - Prob. 8DRQCh. 7.S - Prob. 9DRQCh. 7.S - Prob. 10DRQ
Ch. 7.S - Prob. 1PCh. 7.S - Prob. 2PCh. 7.S - Prob. 3PCh. 7.S - Prob. 4PCh. 7.S - Prob. 5PCh. 7.S - Prob. 6PCh. 7.S - Prob. 7PCh. 7.S - Prob. 8PCh. 7.S - Prob. 9PCh. 7.S - Prob. 10PCh. 7.S - Prob. 11PCh. 7.S - Prob. 12PCh. 7.S - Prob. 13PCh. 7.S - Prob. 14PCh. 7.S - Prob. 15PCh. 7.S - Prob. 16PCh. 7.S - Prob. 17PCh. 7.S - Prob. 18PCh. 7.S - Prob. 19PCh. 7.S - Prob. 1CQCh. 7.S - Prob. 2CQCh. 7.S - Prob. 3CQCh. 7 - Prob. 1DRQCh. 7 - What are some of the main advantage and...Ch. 7 - Prob. 3DRQCh. 7 - Prob. 4DRQCh. 7 - Prob. 5DRQCh. 7 - Prob. 6DRQCh. 7 - Prob. 7DRQCh. 7 - What are motion study principles? How are they...Ch. 7 - Prob. 9DRQCh. 7 - Prob. 10DRQCh. 7 - Prob. 11DRQCh. 7 - Prob. 12DRQCh. 7 - Prob. 13DRQCh. 7 - Prob. 14DRQCh. 7 - Prob. 15DRQCh. 7 - Prob. 16DRQCh. 7 - Prob. 17DRQCh. 7 - Prob. 18DRQCh. 7 - Prob. 19DRQCh. 7 - Prob. 1TSCh. 7 - Prob. 2TSCh. 7 - Prob. 3TSCh. 7 - Prob. 1CTECh. 7 - Prob. 2CTECh. 7 - Prob. 3CTECh. 7 - Prob. 1PCh. 7 - Prob. 2PCh. 7 - Prob. 3PCh. 7 - Given these observed times (in minutes) for four...Ch. 7 - Prob. 5PCh. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Prob. 9PCh. 7 - Prob. 10PCh. 7 - Prob. 11PCh. 7 - Prob. 12PCh. 7 - Prob. 13PCh. 7 - An analyst made the following observations about...Ch. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - Prob. 19P
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Suppose a manufacturer of copiers has concluded that an 82% learning curve applies to the time a beginning service technician takes to diagnose a faulty copying machine. The estimated time the technician takes to install the first copier is 3.2 hrs. Estimate how long will the technician take to diagnose the 10th copier. Plot the learning curve (include time estimates of 50 units in your plot). If another technician has an estimated learning curve of 80%, which technician is expected to learn faster? PLOT the learning curve, please.arrow_forwardazmine Peters, the operations manager at Frontiers Inc., wants to estimate the learning rate for a new task her company will undertake. Jazmine has obtained completion time estimates for the first eight repetitions of this type of task as shown below. UNIT COMPLETION TIME (in hours) 1 33 2 30.361 3 28.915 4 27.931 5 27.191 6 26.602 7 26.113 8 25.7arrow_forwardSara Bredbenner and Blake DeYoung are teammates at a discount store; their new job is assembling swing sets for customers. Assembly of a swing set has a learning rate of 90%. They forgot to time their effort on the first swing set, but spent 4 hours on the second set. They have 6 more sets to do. Determine approximately how much time will be (was) required for: a) the 1st unit.arrow_forward
- Wind Company expects an 85% learning curve. The first batch of a new product required 500 hours. The first four batches should take an average of how many hours (in two decimal places)arrow_forwardGirish Shambu and Delores Reisel are teammates at a discount store; their new job is assembling bicycles for customers. Assembly of a bike has a learning rate of 75%. They forgot to time their effort on the first bike, but spent 5 hours on the second. They have 6 more bikes to do. Determine approximately how much time will be (was) required for: a) The 1st unit= hours (round your response to two decimal places). b) The 8th unit-hours (round your response to two decimal places). c) The total amount of hours to build the 8 units-hours (round your response to two decimal places).arrow_forwardGirish Shambu and William Reisel are teammates at a discount store; their new job is assembling bicycles for customers. Assembly of a bike has a learning rate of 70%. They forgot to time their effort on the first bike but spent 4 hours on the second. They have 6 more bikes to do. Determine approximately how much time will be (was) required for: a) The 1st unit = (round your answer to two decimal places)arrow_forward
- For an 80% learning curve, if the 100th unit produced required 280 hours, how long will it take to produce the 400th unit? Show your calculations.arrow_forwardAn aircraft company has an order to refurbish the interiors of 18 jet aircraft. The work has a learning curve percentage of 80. On the basis of experience with similar jobs, the industrial engineering department estimates that the first plane will require 300 hours to refurbish. Estimate the amount of time needed to complete:a. The fifth planeb. The first five planesc. All 18 planesarrow_forwardKara is supposed to have a learning percentage of 82. Times for the first four units were 30.5, 28.4,27.2, and 27.0 minutes. Does a learning percentage of 82 seem reasonable? Justify your answerusing appropriate calculations.arrow_forward
- An aircraft company has an order to refurbish the interiors of 30 jet aircraft. The work has a learning curve percentage of 80. On the basis of experience with similar jobs, the industrial engineering department estimates that the first plane will require 200 hours to refurbish. Estimate the amount of time needed to complete: (please explain the steps so I can understand how to get to the answer) a. The tenth plane. b. The first ten planes. c. All 30 planes.arrow_forwardAn airline employee responsible for quarterly schedules was measured for the following repetitions. Job 8 16 hours Job 20 12 hours (a) Find out this employee learning curve (b) On what repetition will this employee reach less than 10 hours. Please do fast ASAParrow_forwardThe product TRX takes 9.99 hours for production of 1 unit, where learning curve rate is 77% and what will be the total time taken by 8th unit of product TRX using incremental unit time method ?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.