Program Plan Intro
Strategic planning:
- It denotes a process that helps managers in identifying anticipated outcomes as well as formulates plans for achieving objectives.
- It uses the capabilities and resources that are available.
- The changing nature of organization and surroundings should be considered.
- It offers a framework and a direction that is clearly defined for guiding decision making at every levels.
- It ensures most effective usage by focusing resources based on priorities.
- It enables organization to be proactive and yield advantage from opportunities as well as trends.
- It enables all units to work organized towards common goal.
- It provides measured to evaluate performances.
- It advances communication among the organization.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Which level of planning breaks down each applicable strategic goal into a series of incremental objectives?
Operational
Strategic
Organizational
Tactical
The main idea and purpose of MODAF Strategical point of view.
Answer:
True or false
Chapter 11 Solutions
Principles of Information Systems (MindTap Course List)
Ch. 11.1 - Prob. 1RQCh. 11.1 - Prob. 2RQCh. 11.1 - Prob. 1CTQCh. 11.1 - Prob. 2CTQCh. 11.2 - Prob. 1RQCh. 11.2 - Prob. 2RQCh. 11.2 - Prob. 1CTQCh. 11.2 - Prob. 2CTQCh. 11 - Prob. 1SATCh. 11 - Analysis of the internal assessment and external...
Ch. 11 - Prob. 3SATCh. 11 - Prob. 4SATCh. 11 - Prob. 5SATCh. 11 - Prob. 6SATCh. 11 - Prob. 7SATCh. 11 - Prob. 8SATCh. 11 - Prob. 9SATCh. 11 - Prob. 10SATCh. 11 - According to the Project Management Institute...Ch. 11 - Prob. 12SATCh. 11 - Prob. 1RQCh. 11 - Prob. 2RQCh. 11 - Prob. 3RQCh. 11 - Prob. 4RQCh. 11 - Prob. 5RQCh. 11 - Prob. 6RQCh. 11 - Prob. 7RQCh. 11 - Prob. 8RQCh. 11 - Prob. 9RQCh. 11 - What is a core competency? Project scope? Project...Ch. 11 - Prob. 11RQCh. 11 - Identify and briefly describe the nine areas of...Ch. 11 - Prob. 13RQCh. 11 - Prob. 14RQCh. 11 - Prob. 15RQCh. 11 - Prob. 16RQCh. 11 - Prob. 17RQCh. 11 - Prob. 18RQCh. 11 - Prob. 1DQCh. 11 - Prob. 2DQCh. 11 - Prob. 3DQCh. 11 - Prob. 4DQCh. 11 - Prob. 5DQCh. 11 - Prob. 6DQCh. 11 - Prob. 7DQCh. 11 - Prob. 8DQCh. 11 - Is there a difference between project time...Ch. 11 - Discuss the team dynamics for a highly effective...Ch. 11 - What sort of behaviors would indicate that the...Ch. 11 - Prob. 12DQCh. 11 - Prob. 13DQCh. 11 - How would you respond to a project team member who...Ch. 11 - Prob. 1PSECh. 11 - Prob. 3PSECh. 11 - Prob. 1TACh. 11 - Prob. 2TACh. 11 - Prob. 3TACh. 11 - Prob. 1WECh. 11 - Prob. 2WECh. 11 - Prob. 3WECh. 11 - Prob. 1CECh. 11 - Prob. 2CECh. 11 - Prob. 3CECh. 11 - Prob. 1CTQ1Ch. 11 - Prob. 2CTQ1Ch. 11 - Prob. 3CTQ1Ch. 11 - Prob. 1CTQ2Ch. 11 - Prob. 2CTQ2Ch. 11 - Prob. 3CTQ2
Knowledge Booster
Similar questions
- helparrow_forwardWhat are the critical contrasts between a strategic and gradual approach?arrow_forwardPrepare a Group PowerPoint slide presentation. The PowerPoint Slides must Include the following: Project Charter Requirements analysis Analysis of Alternative Solutions Project Risks Detailed system Specifications WBS Work Breakdown Structure Network Diagra 5arrow_forward
- What is Organization Strategy and Project Selection?arrow_forwardStrategic goals are more focused and short-term in nature than tactical goals.arrow_forwardContrast the critical success factors (CSFs) and SWOT (i.e., strengths, weaknesses, opportunities, and threats) approaches for assessing opportunities as part of a strategic IS planning process. Under what circumstances might one of these approaches be more useful than the other?arrow_forward
- Draw an Activity-On-Arrow (AOA) network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labelling each arrow with the activity letter and estimated durationarrow_forwardThis chart presents an overview of a project's status in terms of tasks, and represents the plan vs actual progress of the tasks in colored horizontal bars across a timeline. Company Name Project Lead TASK Phase 1 Planning Task 1 Document requirements Task 2 Prepare task list Task 3 Assign tasks to members Task 4 Brain storm technology Task 5 Update start and end dats of tasks Phase 2 Design Task 1 Research header component Task 2 Research SQL methodology with PHP CPM chart Gantt chart FDD Diagram PERT chart ASSIGNED TO Jose Project Start: Display Week: PROGRESS 50% 60% 50% 25% 50% 50% Wed, 10/26/2022 1 START 10/26/22 END 10/29/22 10/29/22 10/31/22 10/31/22 11/4/22 11/4/22 11/9/22 10/30/22 11/1/22 10/31/22 11/4/22 11/2/22 11/7/22 Oct 24, 2022 Oct 31, 2022 Nov 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 MTW FSSMTWTFSSMTarrow_forwardList the distinctions between short-term, intermediate, and long-term planning.arrow_forward
- Create a table with activities and realistic estimated durations and develop a Pert chart using AOA method for the WBS. Indicate all the paths including the critical patharrow_forwardThe portfolio manager is the person assigned by the performing organization to achieve the project objectives. The role of a project manager is distinct from a functional manager or operations manager. True False Operations are an organizational function performing the ongoing execution of activities that produce the same product or provide a repetitive service. O True Ealse Karrow_forwardIn general, how could each of the following parameters influence your choice for an organizational, structure? Explain your answers in as much depth as possible. a. The project cost. b. The project schedule (time). c. The project duration. d. The technology requirements. e. The geographical locations. f. The required working relationships with the customer.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Information Systems (MindTap Course...Computer ScienceISBN:9781305971776Author:Ralph Stair, George ReynoldsPublisher:Cengage LearningInformation Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage Learning
- Management Of Information SecurityComputer ScienceISBN:9781337405713Author:WHITMAN, Michael.Publisher:Cengage Learning,Principles of Information Systems (MindTap Course...Computer ScienceISBN:9781285867168Author:Ralph Stair, George ReynoldsPublisher:Cengage LearningCOMPREHENSIVE MICROSOFT OFFICE 365 EXCEComputer ScienceISBN:9780357392676Author:FREUND, StevenPublisher:CENGAGE L
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781305971776
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Management Of Information Security
Computer Science
ISBN:9781337405713
Author:WHITMAN, Michael.
Publisher:Cengage Learning,
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781285867168
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
COMPREHENSIVE MICROSOFT OFFICE 365 EXCE
Computer Science
ISBN:9780357392676
Author:FREUND, Steven
Publisher:CENGAGE L