The following bar chart shows the activities required to complete a project in one year. After six months on the job (July 1), the contractor concluded that 20% of Activity F was completed, 80% of Activity C was completed, and 40% of Activity B was completed (and Activities A, B, and D are also completed). The project has cost the contractor "to date" total of $53,500. Using the Earned Value method, determine the Earned Value, Planned Value, Schedule Variance and Cost Variance. State whether the project is over or under budget AND whether it is ahead of or behind schedule. JAN FEB MAR APRIL MAY JUN JUL AUGS A - $5000 F-$30000 B-$12000 D-$20000 C-$8000 G-$6000 E-$12000 H-$7000 J-$5000 NOV DEC K-$6000 Q Q Q

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter17: Elemental Estimating
Section: Chapter Questions
Problem 6RQ
icon
Related questions
Question
The following bar chart shows the activities required to complete a project in
one year. After six months on the job (July 1), the contractor concluded that 20% of
Activity F was completed, 80% of Activity C was completed, and 40% of Activity B
was completed (and Activities A, B, and D are also completed). The project has cost
the contractor "to date" total of $53,500.
Using the Earned Value method, determine the Earned Value, Planned Value,
Schedule Variance and Cost Variance. State whether the project is over or under
budget AND whether it is ahead of or behind schedule.
JAN FEB MAR APRIL MAY JUN JUL AUGS
A - $5000
F-$30000
B-$12000
D-$20000
C-$8000
G-$6000
E-$12000
H-$7000
J-$5000
NOV DEC
K-$6000
Q
Q
Q
Transcribed Image Text:The following bar chart shows the activities required to complete a project in one year. After six months on the job (July 1), the contractor concluded that 20% of Activity F was completed, 80% of Activity C was completed, and 40% of Activity B was completed (and Activities A, B, and D are also completed). The project has cost the contractor "to date" total of $53,500. Using the Earned Value method, determine the Earned Value, Planned Value, Schedule Variance and Cost Variance. State whether the project is over or under budget AND whether it is ahead of or behind schedule. JAN FEB MAR APRIL MAY JUN JUL AUGS A - $5000 F-$30000 B-$12000 D-$20000 C-$8000 G-$6000 E-$12000 H-$7000 J-$5000 NOV DEC K-$6000 Q Q Q
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,
Construction Materials, Methods and Techniques (M…
Construction Materials, Methods and Techniques (M…
Civil Engineering
ISBN:
9781305086272
Author:
William P. Spence, Eva Kultermann
Publisher:
Cengage Learning
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning
Engineering Fundamentals: An Introduction to Engi…
Engineering Fundamentals: An Introduction to Engi…
Civil Engineering
ISBN:
9781305084766
Author:
Saeed Moaveni
Publisher:
Cengage Learning
Residential Construction Academy: House Wiring (M…
Residential Construction Academy: House Wiring (M…
Civil Engineering
ISBN:
9781285852225
Author:
Gregory W Fletcher
Publisher:
Cengage Learning
Solid Waste Engineering
Solid Waste Engineering
Civil Engineering
ISBN:
9781305635203
Author:
Worrell, William A.
Publisher:
Cengage Learning,