Homework #3 Due: Saturday, Nov. 23, 2024 The following bar chart shows the activities for a project. The total project cost is $1,545. Total Activity Cost 2 3 Time (weeks) 456 7 8 9 10 A $120 B $35 C $80 D $270 E $60 F $180 G $270 H $90 J $160 K $60 L $220 $1,545 After three weeks, Activities A, C, E, half of B, quarter of F, and two thirds of H are completed for a cost of $435. At this point in time (three weeks after the start date), what is the status of the project in terms of budget (over or under budget) and schedule (ahead or behind schedule)? Use SPI and CPI to determine your answers.

Engineering Fundamentals: An Introduction to Engineering (MindTap Course List)
5th Edition
ISBN:9781305084766
Author:Saeed Moaveni
Publisher:Saeed Moaveni
Chapter2: Preparing For An Engineering Career
Section2.3: Study Habits And Strategies
Problem 2BYG
icon
Related questions
Question

hand writing please and take your time
and thanks for you

Homework #3
Due: Saturday, Nov. 23, 2024
The following bar chart shows the activities for a project. The total project cost is $1,545.
Total
Activity
Cost
2
3
Time (weeks)
456
7
8
9
10
A
$120
B
$35
C
$80
D
$270
E
$60
F
$180
G
$270
H
$90
J
$160
K
$60
L
$220
$1,545
After three weeks, Activities A, C, E, half of B, quarter of F, and two thirds of H are completed
for a cost of $435. At this point in time (three weeks after the start date), what is the status of the
project in terms of budget (over or under budget) and schedule (ahead or behind schedule)? Use
SPI and CPI to determine your answers.
Transcribed Image Text:Homework #3 Due: Saturday, Nov. 23, 2024 The following bar chart shows the activities for a project. The total project cost is $1,545. Total Activity Cost 2 3 Time (weeks) 456 7 8 9 10 A $120 B $35 C $80 D $270 E $60 F $180 G $270 H $90 J $160 K $60 L $220 $1,545 After three weeks, Activities A, C, E, half of B, quarter of F, and two thirds of H are completed for a cost of $435. At this point in time (three weeks after the start date), what is the status of the project in terms of budget (over or under budget) and schedule (ahead or behind schedule)? Use SPI and CPI to determine your answers.
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Recommended textbooks for you
Engineering Fundamentals: An Introduction to Engi…
Engineering Fundamentals: An Introduction to Engi…
Civil Engineering
ISBN:
9781305084766
Author:
Saeed Moaveni
Publisher:
Cengage Learning
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning
Solid Waste Engineering
Solid Waste Engineering
Civil Engineering
ISBN:
9781305635203
Author:
Worrell, William A.
Publisher:
Cengage Learning,
Residential Construction Academy: House Wiring (M…
Residential Construction Academy: House Wiring (M…
Civil Engineering
ISBN:
9781285852225
Author:
Gregory W Fletcher
Publisher:
Cengage Learning
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,
Residential Construction Academy: House Wiring (M…
Residential Construction Academy: House Wiring (M…
Civil Engineering
ISBN:
9781337402415
Author:
Gregory W Fletcher
Publisher:
Cengage Learning