Chapter 5, Problem 4PA
Summary Introduction
Interpretation: Economic design specification
Concept Introduction:
Reliability is the probability of a product which performs under designed and controlled atmosphere in a given period of time. This is checked to know the accuracy of the product.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Describe a product with bad ergonomics design and give a better design of that product.
Problem 2: Customer complaints
Each question in this problem (Q5-Q8) consists of a customer complaint. From the options below, indicate which dimension of customer utility each complaint relates to.
Ease of use
Timing
Fit
Convenience
Durability
Location
Affordability
Performance
Reliability
Aesthetics
Question 5
“I had to spend 27 minutes on hold before talking to an agent”.
Question 6
“This car is not fuel efficient at all."
Question 7
“When I needed a restroom in the amusement park, I had to walk almost a mile."
Question 8
“I had this suit tailored for me, but now I realize that the shoulders are too wide."
Perform a "product-by-value" analysis on products A, B, C, D, and E.
A
$0.85
B
$0.55
Total Contribution $117,000 $87,000 $54,000
C
$1.05
Unit Contribution
S
The list of products in descending order of their individual dollar contribution to the firm:
The list of products in descending order of their total dollar contribution to the firm:
Based on the product-by-value" analysis, which products are the 3 lowest in total dollar contribution and, therefore, possible candidates for replacement?
should be investigated for replacement
Products
D
$1.65
$61,000
E
$0.85
$76,000
Chapter 5 Solutions
OM (with OM Online, 1 term (6 months) Printed Access Card)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Design Within Reach (DWR) Design Within Reach (DWR) is one of the leading hardwood furniture manufacturers. While DWR has many small competitors, none of them controls a significant market share. Like most furniture manufacturers, DWR sells its products to a wide variety of small furniture stores, none of which represents a large percentage of DWR's sales. DWR can choose among many wood (an undifferentiated commodity) suppliers to find the best price and delivery. The growth rate of the hardwood furniture industry has slowed considerably in recent years. Many consumers purchase "IKEA type" furniture made of composite wood, which is substantially less expensive than hardwood furniture. The level of direct competition in the hardwood furniture industry can best be described as moderate because the slowing growth rate offsets the numerous firms in the industry. low because of the numerous firms in the industry and the slowing growth rate low because of the slowing growth rate and the…arrow_forwardExplain four different categories of potential failure costs and develop a plan to prevent each one.arrow_forwardPrecision Delivery Inc. Case StudyPrecision Delivery Inc. (PDI) is a package pickup and delivery service for homes and small businesses.PDI specializes in packages of 50 pounds or less and has a full-price rebate policy for any pickup ordelivery made outside the customer-designated 15-minute window. PDI advertising proudly states,“Pickup and delivery at your convenience, not ours.”PDI has facilities at 2 locations, Downtown and Suburbia, each servicing customers within a 15-mileradius with pickup and deliveries made by truck or bicycle. Customers designate a 15-minute windowfor their packages to be picked up or delivered. PDI charges customers $5 per package plus $1 perpound (50-pound maximum).PDI Sales Operators receive pickup and delivery requests by phone from customers. Dispatchers issueinstructions to Field Operators for pickups and deliveries. To ensure prompt service, Dispatchers planfor 30 minutes of travel time, one way, for each pickup or delivery and target arrival time for…arrow_forward
- Precision Delivery Inc. Case StudyPrecision Delivery Inc. (PDI) is a package pickup and delivery service for homes and small businesses.PDI specializes in packages of 50 pounds or less and has a full-price rebate policy for any pickup ordelivery made outside the customer-designated 15-minute window. PDI advertising proudly states,“Pickup and delivery at your convenience, not ours.”PDI has facilities at 2 locations, Downtown and Suburbia, each servicing customers within a 15-mileradius with pickup and deliveries made by truck or bicycle. Customers designate a 15-minute windowfor their packages to be picked up or delivered. PDI charges customers $5 per package plus $1 perpound (50-pound maximum).PDI Sales Operators receive pickup and delivery requests by phone from customers. Dispatchers issueinstructions to Field Operators for pickups and deliveries. To ensure prompt service, Dispatchers planfor 30 minutes of travel time, one way, for each pickup or delivery and target arrival time for…arrow_forwardThe product design group of Iyengar Electric Supplies,Inc., has determined that it needs to design a new series of switches.It must decide on one of three design strategies. The market forecastis for 200,000 units. The better and more sophisticated the designstrategy and the more time spent on value engineering, the less willbe the variable cost. The chief of engineering design, Dr. W. L.Berry, has decided that the following costs are a good estimate of theinitial and variable costs connected with each of the three strategies:a) Low-tech: A low-technology, low-cost process consisting ofhiring several new junior engineers. This option has a fixedcost of $45,000 and variable-cost probabilities of .3 for $.55each, .4 for $.50, and .3 for $.45.b) Subcontract: A medium-cost approach using a good outsidedesign staff. This approach would have a fixed cost of $65,000and variable-cost probabilities of .7 of $.45, .2 of $.40, and .1 of $.35.c) High-tech: A high-technology approach using the very…arrow_forwardBook pdf : https://drive.google.com/file/d/1ojDaUwQu0gxTIn7oJnINvLmeqv5_FMz7/view?usp=drivesdk Question as in the attached photo from page 218 Question 5 Note: Give full explanation with clear indication to the problem’s aspect. Use information provided in table 7.8 , 7.7 (*) Use the weighted-point evaluation system to cal- culate weighted performance scores for each of the software firms. Would the results change if each dimension had a weight of one-third? (**) In Chapter 2, we described order qualifiers as per- formance dimensions on which customers demand a minimum level of performance. Basically, if a supplier fails to meet the minimum requirements on any of the qualifiers, that supplier would be eliminated from contention. How would you incorporate the concept of order qualifiers into the weighted-point evaluation system?arrow_forward
- Provide an example of ratio data that can be collected in a usability test.arrow_forwardCost of quality”. Discuss and explain how it would be achieved for a company.arrow_forwardPowell Motors, an automobile manufacturing company, is interested in purchasing new air filters for its automobiles. The company's buying team has narrowed the alternatives to products proposed by five suppliers-supplier 1, supplier 2, and supplier 3, supplier 4, and supplier 5. To select a supplier, the team is considering two characteristics-reliability and durability. The purchase decision lies on the performance score and the importance weight of each characteristic. The performance scores for reliability of supplier 1, supplier 2, supplier 3, supplier 4, and supplier 5 are 10, 9, 8, 6, and 7. respectively. The performance scores for durability of supplier 1, supplier 2, supplier 3, supplier 4, and supplier 5 are 5, 7, 8, 8, and 6, respectively. The buying team assigns reliability an importance weight of 9 against a score of 8 for durability. According to the multiattribute model of evaluation, the buying team of Powell Motors is most likely to select O supplier 2 O supplier 1 O…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.