Operations Management
11th Edition
ISBN: 9780132921145
Author: Jay Heizer
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Question
Chapter 10, Problem 33P
a)
Summary Introduction
To determine: The standard time.
Introduction: Time study is the basis that helps set the standard time; it would time a sample of the performance of the worker.
b)
Summary Introduction
To determine: The normal time of the worker.
Introduction: Time study is the basis that helps set the standard time; it would time a sample of the performance of the worker.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Tim Nelson's job as an inspector for La-Z-Boy is to inspect 130 chairs per day.a) If he works an 8-hour day, how many minutes is be allowed for each inspection (i.e., what is his "standard time")?b) If he is a llowed a 6% fat igue a llowance, a 6% delay allowance,and 6% for personal time, what is the normal time that he is assumed to take to perform each inspection?
5. The manager of Asombrado Bounty Office, Charles Badillo, estimates his employees are idle 25%of the time. With that problem, how many work samples are needed to consider within 3%accuracy and have 95.45% confidence level.
6. At ASP Micro Manufacturing, Inc. workers press semiconductor into predrilled slots on printed-circuit boards. Determine the normal time of the operation in seconds. The elemental motions for normal time used by the company are as follows:• Reach 6 inches for semiconductors 10.5 TMU• Grasp the semiconductors 8.0 TMU• Move semiconductor to printed-circuit board 9.5 TMU• Position semiconductor 20.1 TMU• Press semiconductor into slots 20.3 TMU• Move board aside 15.8 TMU
7. The semiconductor used in Costin Calculator has 5 components with the consistency of 90%, 95%,98%, 90%, and 99%, respectively. How reliable is one product of calculator?
tof
instion
The owner of Kat Motel wants to develop a time standard for the task of cleaning a cat cage. In a preliminary
study, she observed one of her workers perform this task six times, with the following results:
Observation
1
2
3
5
6
Time (seconds) 58
51
62
70
4
64
40
What is the standard time for this task if the employee performance rating is 3, and an allowance of (n) percent
of job time is used?
minutes.
Qu
1
Finis
Time:
Chapter 10 Solutions
Operations Management
Ch. 10 - Prob. 1DQCh. 10 - Prob. 2DQCh. 10 - Prob. 3DQCh. 10 - Prob. 4DQCh. 10 - Prob. 5DQCh. 10 - Prob. 6DQCh. 10 - Prob. 7DQCh. 10 - Prob. 8DQCh. 10 - Prob. 9DQCh. 10 - Prob. 10DQ
Ch. 10 - Prob. 11DQCh. 10 - Prob. 12DQCh. 10 - Prob. 13DQCh. 10 - Prob. 14DQCh. 10 - Prob. 1PCh. 10 - Draw an activity chart for a machine operator with...Ch. 10 - Prob. 3PCh. 10 - Prob. 4PCh. 10 - Prob. 5PCh. 10 - Prob. 6PCh. 10 - Prob. 7PCh. 10 - Prob. 8PCh. 10 - Prob. 9PCh. 10 - Prob. 10PCh. 10 - Prob. 11PCh. 10 - Prob. 12PCh. 10 - Prob. 13PCh. 10 - Prob. 14PCh. 10 - Prob. 15PCh. 10 - Prob. 16PCh. 10 - Prob. 17PCh. 10 - Prob. 18PCh. 10 - Prob. 19PCh. 10 - Prob. 20PCh. 10 - Prob. 21PCh. 10 - Prob. 22PCh. 10 - Prob. 23PCh. 10 - Prob. 24PCh. 10 - Prob. 25PCh. 10 - Prob. 26PCh. 10 - Prob. 27PCh. 10 - Prob. 28PCh. 10 - Prob. 29PCh. 10 - Prob. 30PCh. 10 - Prob. 31PCh. 10 - Prob. 32PCh. 10 - Prob. 33PCh. 10 - Prob. 34PCh. 10 - Prob. 35PCh. 10 - Prob. 36PCh. 10 - Prob. 37PCh. 10 - Prob. 38PCh. 10 - Prob. 1CSCh. 10 - Prob. 2CSCh. 10 - Prob. 3CSCh. 10 - Prob. 4CSCh. 10 - Prob. 1VCCh. 10 - Prob. 2VCCh. 10 - Prob. 3VCCh. 10 - Prob. 4VC
Knowledge Booster
Similar questions
- The owner of Kat Motel wants to develop a time standard for the task of cleaning a cat cage. In a preliminary study, she observed one of her workers perform this task six times, with the following results: Observation 1 2 3 4 5 6 Time (seconds) 52.7 70 53.3 90.3 80.6 86.7 If the employee performance rating is 1.50, what is the standard time for this task with an allowance of 20 percent of job time is used? seconds.arrow_forwardhelp pleasearrow_forwardTOYS AND JOB DESIGN AT THE HOVEY AND BEARD COMPANY The following is a situation that occurred in the Hovey and Beard Company, as reported by J. V. Clark. This company manufactured a line of wooden toys. One part of the process involved spray painting partially assembled toys, after which the toys were hung on moving hooks that carried them through a drying oven. The operation, staffed entirely by women, was plagued with absenteeism, high turnover, and low morale. Each woman at her paint booth would take a toy from the tray beside her, position it in a fixture, and spray on the color according to the required pattern. She then would release the toy and hang it on the conveyor hook. The rate at which the hooks moved had been calculated so that each woman, once fully trained, would be able to hang a painted toy on each hook before it passed beyond her reach. The women who worked in the paint room were on a group incentive plan that tied their earnings to the…arrow_forward
- Nine observations from a work measurement study using continuous timing are shown below. Allowances are determined as: personal, five percent; fatigue, six percent; delay, five percent. Use the Work Measurement Excel template to determine the standard time for this operation. Work Observation Element 1 2 3 4 5 6 7 8 9 Performance Rating A 0.10 0.15 0.08 0.06 0.11 0.10 0.16 0.15 0.16 115% B 0.23 0.18 0.23 0.22 0.25 0.24 0.29 0.28 0.28 95% C 0.49 0.52 0.49 0.48 0.47 0.47 0.52 0.49 0.51 105% D 0.62 0.67 0.64 0.59 0.70 0.68 0.68 0.67 0.70 90% E 0.71 0.74 0.73 0.70 0.81 0.81 0.78 0.81 0.83 105% F 1.03 1.03 1.01 1.01 1.08 1.12 1.03 1.09 1.11 100% Round your answer to two decimal places. minutesarrow_forwardBased on a careful work study in the Hofstetter Corp., the results shown in the following table have been observed: a) Compute the normal time for each work element.b) If the allowance for this type of work is 15%, what is the standard time?c) How many observations are needed for a 95% confidence level within ±5% accuracy? (Hint: Calculate the sample size of each element.)arrow_forwardA time study was conducted on a job that contains four elements. The observed times and performance ratings for six cycles are shown in the following table. OBSERVATIONS (minutes per cycle) Element 1 2 3 4 Performance Rating 80% 75 120 105 1 0.51 1.51 0.86 1.11 Click here for the Excel Data File Element 1 2 3 4 Element 1 2 3 4 2 0.56 1.51 0.86 1.16 a. Determine the average cycle time for each element. (Round your answers to 3 decimal places.) Average cycle 3 0.46 1.46 0.76 1.11 Normal time 4 5 6 0.46 0.46 0.46 1.46 1.46 1.51 0.81 0.81 0.86 1.16 1.16 1.21 b. Find the normal time for each element. (Round your answers to 3 decimal places.)arrow_forward
- How many work cycles should be timed to estimate the average cycle time to within 2 percent ofthe sample mean with a confidence of 99 percent if a pilot study yielded these times (minutes):5.2, 5.5, 5.8, 5.3, 5.5, and 5.1? The standard deviation is .253 minutes per cycle.arrow_forwardA job was timed for 60 cycles and had an average of 1.25 minutes per piece. The performance rating was 95 percent, and workday allowances are 9 percent. Determine each of the following: a. Observed time. (Round your answer to 2 decimal place.) Observed time minutes b. Normal time. (Round your answer to 2 decimal places.) Normal time minutes c. Standard time. (Round your answer to 2 decimal places.) Standard time minutesarrow_forwardClaudine Soosay recorded the following times assemblinga watch. Determine (a) the average time, (b) the normaltime, a nd (c) the standard time taken by her, using a performancerating of95% and a personal allowance of 8%.arrow_forward
- Nine observations from a work measurement study using continuous timing are shown below. Allowances are determined as: personal, five percent; fatigue, six percent; delay, six percent. Use the Work Measurement Excel template to determine the standard time for this operation. Work Observation Element 1 2 3 4 5 6 7 8 9 Performance Rating A 0.09 0.13 0.06 0.05 0.11 0.09 0.14 0.13 0.14 85% B 0.25 0.18 0.23 0.20 0.24 0.24 0.27 0.26 0.26 115% C 0.47 0.51 0.47 0.46 0.49 0.49 0.51 0.47 0.48 110% D 0.61 0.69 0.65 0.60 0.71 0.67 0.67 0.69 0.73 90% E 0.72 0.76 0.74 0.68 0.79 0.81 0.76 0.80 0.81 115% F 1.02 1.04 0.98 1.02 1.08 1.12 1.04 1.07 1.09 85% Round your answer to two decimal places. minutesarrow_forwardNine observations from a work measurement study using continuous timing are shown below. Allowances are determined as: personal, five percent; fatigue, five percent; delay, seven percent. Use the Work Measurement Excel template to determine the standard time for this operation. Work Observation Element 1 2 3 4 5 6 7 8 9 Performance Rating A 0.11 0.14 0.10 0.09 0.12 0.11 0.15 0.14 0.15 105% B 0.24 0.20 0.21 0.22 0.24 0.23 0.28 0.26 0.26 85% C 0.46 0.48 0.46 0.44 0.48 0.48 0.48 0.46 0.49 100% D 0.64 0.66 0.65 0.59 0.71 0.69 0.69 0.66 0.71 115% E 0.70 0.74 0.74 0.68 0.79 0.83 0.77 0.80 0.84 100% F 1.01 1.05 1.01 1.00 1.09 1.12 1.05 1.06 1.12 95% Round your answer to two decimal places. minutesarrow_forwardThe Dubuque Cement Company packs 80-pound bagsof concrete mix. Time-study data for the filling activity are shown inthe following table. Because of the high physical demands of the job,the company's policy is a 23% allowance for workers.a) Compute the standard time for the bag-packing task.b) How many observations are necessary for 99% confidence,within ±5% accuracy?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.