Question
Chapter 10, Problem 4CS
Summary Introduction
Case summary:
Person K is the vice-president of operations at Company J, which received a request for quote of supplying 400 units per week. Employee must be permitted to perform the task for 17 times. The actual times observed were given below:
Number | Actual time (minutes) |
1 | 2.05 |
2 | 1.92 |
3 | 2.01 |
4 | 1.89 |
5 | 1.77 |
6 | 1.8 |
7 | 1.86 |
8 | 1.83 |
9 | 1.93 |
10 | 1.96 |
11 | 1.95 |
12 | 2.05 |
13 | 1.79 |
14 | 1.82 |
15 | 1.85 |
16 | 1.85 |
17 | 1.99 |
Performance rating is 115%, fatigue allowance is given as 8%, personal allowance is 6%, and delay allowance is 2%. Workday hour is 7.5 hours and the operators would be paid $12.50 per hour for 8 hours.
To determine: Thecost per unit for the task in direct labor cost.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Q2
Q:
Discuss HRM in Construction process perspective.
Subject: Human resources management in construction
Program: construction engineering management
Question
Chapter 10 Solutions
Operations Management
Ch. 10 - Prob. 1DQCh. 10 - Prob. 2DQCh. 10 - Prob. 3DQCh. 10 - Prob. 4DQCh. 10 - Prob. 5DQCh. 10 - Prob. 6DQCh. 10 - Prob. 7DQCh. 10 - Prob. 8DQCh. 10 - Prob. 9DQCh. 10 - Prob. 10DQ
Ch. 10 - Prob. 11DQCh. 10 - Prob. 12DQCh. 10 - Prob. 13DQCh. 10 - Prob. 14DQCh. 10 - Prob. 1PCh. 10 - Draw an activity chart for a machine operator with...Ch. 10 - Prob. 3PCh. 10 - Prob. 4PCh. 10 - Prob. 5PCh. 10 - Prob. 6PCh. 10 - Prob. 7PCh. 10 - Prob. 8PCh. 10 - Prob. 9PCh. 10 - Prob. 10PCh. 10 - Prob. 11PCh. 10 - Prob. 12PCh. 10 - Prob. 13PCh. 10 - Prob. 14PCh. 10 - Prob. 15PCh. 10 - Prob. 16PCh. 10 - Prob. 17PCh. 10 - Prob. 18PCh. 10 - Prob. 19PCh. 10 - Prob. 20PCh. 10 - Prob. 21PCh. 10 - Prob. 22PCh. 10 - Prob. 23PCh. 10 - Prob. 24PCh. 10 - Prob. 25PCh. 10 - Prob. 26PCh. 10 - Prob. 27PCh. 10 - Prob. 28PCh. 10 - Prob. 29PCh. 10 - Prob. 30PCh. 10 - Prob. 31PCh. 10 - Prob. 32PCh. 10 - Prob. 33PCh. 10 - Prob. 34PCh. 10 - Prob. 35PCh. 10 - Prob. 36PCh. 10 - Prob. 37PCh. 10 - Prob. 38PCh. 10 - Prob. 1CSCh. 10 - Prob. 2CSCh. 10 - Prob. 3CSCh. 10 - Prob. 4CSCh. 10 - Prob. 1VCCh. 10 - Prob. 2VCCh. 10 - Prob. 3VCCh. 10 - Prob. 4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Question 2: Organising Write a short essay (250 words) explaining how job specialisation could be used to design a McDonald’s worker’s job. Using examples explain two disadvantages of such a job design.arrow_forwardQuestion 1- Week 31 Ola Ltd, which uses a job costing system, had two jobs in process at the start of the year: Job L1 ($68,000) and Job L2 ($30 000). The following information is available: i) The company applies manufacturing overhead on the basis of machine hours. Budgeted overhead and machine activity for the year were anticipated to be $1,000,000 and 25,000 hours, respectively. ii) The company worked on three jobs during the first quarter (i.e. from 1 January to 31 March). Direct materials used, direct labour incurred and machine hours consumed were as shown in the following table: Job numbers Direct material Direct labour Machine hours L1 $15,000 $30,000 900 L2 33,000 1,600 L3 45,000 65,000 2,000 ii) Manufacturing overhead incurred during the first quarter was $215,000. iv) Ola Ltd completed Job L1 and Job L2 during the first quarter. Job L2 was sold on credit, producing a profit of $30,000 for the company. Required: a) Calculate the company's predetermined overhead rate. b)…arrow_forwardQUESTION 2 Three estimates were 15, 1, and 24, not given in any order. What is the Three-point estimate? Pick closest answer. O 13 14 O 15 O 28arrow_forward
- Question 1 Rock View Restaurant is a new fast food restaurant chain. The Operations Manager has divided its normal drive-through service process into the following tasks: Tasks Description Task Time Predecessors (In Seconds) A Take order 25 None Receive payment 20 A Gather drinks 35 A D Gather food 32 A Put food etc. in bag 25 C,D F Give food to 10 В.Е customer Currently, Rock View Restaurant has a single window with one person who takes the order, gather the food, collects the money and gives the food to the customer. This takes an average of 147 seconds per customer so only 25.5 cars can be served. Rock View Restaurant wants to increase its drive-through capacity to 60 cars per hour by forming a multi-window line. iv. Using the LOT heuristic, assign the tasks to the windows to produce the desired service rate making sure that the precedence relationship is maintained. Calculate the efficiency of the newly design process. V.arrow_forwardd) What is the probability of completing in 21 weeks?arrow_forwardq1arrow_forward
- C Case Study: Designing a Comprehensive Employee Orientation Program for XYZ Global Corporation Background:XYZ Global Corporation, a multinational conglomerate, is undergoing a significant expansion, with new hires joining from diverse cultural backgrounds and professional experiences. The Human Resources department has been tasked with designing a comprehensive employee orientation program to ensure a seamless onboarding experience for all employees. Question- Identify the key topics and information to be covered during the orientation.arrow_forwardQuestion 5 Which of the following knowledge area deals with identifying people, groups or organizations that could impact or be impacted by a project of building a 3-mile long bridge connecting two island cities of a country? Not yet answered Marked out of 1.00 P Flag question Select one: a. Communication Plan b. Project Communications Management C. Project Stakeholder Management d. Project Integration Management e. Operation department.arrow_forwardtime (hours) pH 7.00 7.30 6.99 7.00 Assignment 1 2 7.12 7.25 7.12 7.20 3 720 7.16 720 7.16 4 6.98 7.00 6.94 7.00 5 6.99 6.99 6.99 6.98 6 7.00 6.93 7.02 6.93 7 6.92 7.00 6.92 7.02 Construct the X-Bar charts and R- charts 6.88 6.82 6.94 6.99 7.10 7.00 7.00 7.00 for reporting your results 10 721 7.02 721 7.04 11 7.01 6.86 7.01 6.90 12 6.86 6.98 6.90 6.98 13 6.90 7.00 6.87 7.00 14 7.01 7.04 7.01 7.05 15 7.00 6.95 7.00 6.99 16 7.09 7.20 7.03 7.20 17 6.89 7.14 6.87 7.15 18 6.98 6.80 6.98 6.89 19 7.00 6.90 7.00 6.90 20 7.20 7.00 723 7.00 21 7.04 7.03 7.08 7.00 22 6.90 6.92 6.98 6.92 23 7.00 7.00 7.00 7.00 24 7.00 6.97 7.01 6.98arrow_forward
- Question 1 Rock View Restaurant is a new fast food restaurant chain. The Operations Manager has divided its normal drive-through service process into the following tasks: Tasks Description Predecessors Take order Receive payment Gather drinks Gather food Put food etc. in bag Give food to Task Time (In Seconds) 25 20 35 32 25 A None A C. A A C,D В.Е E 10 customer Currently, Rock View Restaurant has a single window with one person who takes the order, gather the food, collects the money and gives the food to the customer. This takes an average of 147 seconds per customer so only 25.5 cars can be served. Rock View Restaurant wants to increase its drive-through capacity to 60 cars per hour by forming a multi-window line. i. Draw the precedence diagram to represent the process at Rock View Restaurant. ii. Calculate the cycle time in seconds. i. Calculate the minimum number of windows that Rock View Restaurant will need to serve 60 cars per hour. Using the LOT heuristic, assign the tasks to…arrow_forwardQuestion 20 1pts Given the flow diagram of an assembly line below, using a cycle time of 2.7 minutes, assip l the tasks in the first workstater by waing shortest task time first rule. 0.5 1.0 0.1 0.5 6. 3.5 Tsks 1. 2 Tasks 1,3 OTasks 1.2. 3, 4 Task 5 Tasks 1, 2. 4 Question 21arrow_forwardQuestion 12 A project oriented process flow is more flexible than an assembly line orientation. Group of answer choices a. True b. Falsearrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.