Task Duration Predecess Early Early Late Start Late Slack (Days) ors Start (ES) Finish (LS) Finish (EF) (LF) A 4 None 10 4 0 4 10 B 3 A 4 7 5 8 1 C 12 A 4 6 6 8 2 D 5 B, C 7 12 7 12 10 E 1 D 12 13 12 13 10 Contextual Note: This table outlines a project consisting of five tasks (A, B, C, D, E) with their respective durations and dependencies. Students will analyze the data to calculate the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF), and Slack for each task, ultimately determining the critical path of the project. Also, you have to draw a diagram (see example below) showing the activity nodes.
Task Duration Predecess Early Early Late Start Late Slack (Days) ors Start (ES) Finish (LS) Finish (EF) (LF) A 4 None 10 4 0 4 10 B 3 A 4 7 5 8 1 C 12 A 4 6 6 8 2 D 5 B, C 7 12 7 12 10 E 1 D 12 13 12 13 10 Contextual Note: This table outlines a project consisting of five tasks (A, B, C, D, E) with their respective durations and dependencies. Students will analyze the data to calculate the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF), and Slack for each task, ultimately determining the critical path of the project. Also, you have to draw a diagram (see example below) showing the activity nodes.
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
Related questions
Question
Answer the question in the attached photo and draw the network that interprets the data

Transcribed Image Text:Task Duration Predecess Early Early
Late Start Late
Slack
(Days)
ors
Start (ES) Finish
(LS)
Finish
(EF)
(LF)
A
4
None
10
4
0
4
10
B
3
A
4
7
5
8
1
C
12
A
4
6
6
8
2
D
5
B, C
7
12
7
12
10
E
1
D
12
13
12
13
10
Contextual Note: This table outlines a project consisting of
five tasks (A, B, C, D, E) with their respective durations and
dependencies. Students will analyze the data to calculate the
Early Start (ES), Early Finish (EF), Late Start (LS), Late
Finish (LF), and Slack for each task, ultimately determining
the critical path of the project. Also, you have to draw a
diagram (see example below) showing the activity nodes.
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Management, Loose-Leaf Version
Management
ISBN:
9781305969308
Author:
Richard L. Daft
Publisher:
South-Western College Pub

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Management, Loose-Leaf Version
Management
ISBN:
9781305969308
Author:
Richard L. Daft
Publisher:
South-Western College Pub

Foundations of Business (MindTap Course List)
Marketing
ISBN:
9781337386920
Author:
William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:
Cengage Learning

Foundations of Business - Standalone book (MindTa…
Marketing
ISBN:
9781285193946
Author:
William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:
Cengage Learning

Understanding Management (MindTap Course List)
Management
ISBN:
9781305502215
Author:
Richard L. Daft, Dorothy Marcic
Publisher:
Cengage Learning