More Info Overall Process uestion Viewer ...ributes Average demand: 2,700/week (1,400 "L"; 1,300 "S") Batch size: 1,000 Number of shifts per day: 1 Availability: 8 hours per shift with two 30 minute lunch breaks Process Step 1 Press Process Step 2 Pierce & Form Process Step 3 Finish Grind Process Step 4 Supplier Information Information Flow Shipping Cycle time 4 seconds Setup time = 2 hours Uptime = 90% Operators = 1 Every Part Every = 1 week WIP 1 day of sheets (before Press) Cycle time = 30 seconds Setup time 30 minutes Uptime = 100% Operators = 1 WIP = 1,000 "L", 1,350 "S" (before Pierce & Form) Cycle time 45 seconds Setup time=45 minutes Uptime = 100% Operators = 1 WIP=200 "L", 1,450 "S" (before Finish Grind) WIP=600 "L", 1,300 "S" (after Finish Grind) One shipment a day in trays of 60 pieces All communications from customer are electronic: Question Viewer nfo Process Step 2 Pierce & Form Process Step 3 Finish Grind WIP = 1 day of sheets (before Press) Cycle time 30 seconds Setup time 30 minutes Uptime 100% = Operators = 1 WIP = 1,000 "L", 1,350 "S" (before Pierce & Form) Cycle time=45 seconds Setup time=45 minutes Uptime = 100% Operators = 1 WIP = 200 "L", 1,450 "S" (before Finish Grind) Process Step 4 Shipping Supplier WIP = 600 "L", 1,300 "S" (after Finish Grind) One shipment a day in trays of 60 pieces Information Information Flow All communications from customer are electronic: 180/90/60/30/day Forecasts Daily Order All communications to supplier are electronic 4-week Forecast Weekly Fax There is a weekly schedule manually delivered to Press, Pierce & Form, and Finish Grind and a Daily Ship Schedule manually delivered to Shipping All material is pushed Print Done
More Info Overall Process uestion Viewer ...ributes Average demand: 2,700/week (1,400 "L"; 1,300 "S") Batch size: 1,000 Number of shifts per day: 1 Availability: 8 hours per shift with two 30 minute lunch breaks Process Step 1 Press Process Step 2 Pierce & Form Process Step 3 Finish Grind Process Step 4 Supplier Information Information Flow Shipping Cycle time 4 seconds Setup time = 2 hours Uptime = 90% Operators = 1 Every Part Every = 1 week WIP 1 day of sheets (before Press) Cycle time = 30 seconds Setup time 30 minutes Uptime = 100% Operators = 1 WIP = 1,000 "L", 1,350 "S" (before Pierce & Form) Cycle time 45 seconds Setup time=45 minutes Uptime = 100% Operators = 1 WIP=200 "L", 1,450 "S" (before Finish Grind) WIP=600 "L", 1,300 "S" (after Finish Grind) One shipment a day in trays of 60 pieces All communications from customer are electronic: Question Viewer nfo Process Step 2 Pierce & Form Process Step 3 Finish Grind WIP = 1 day of sheets (before Press) Cycle time 30 seconds Setup time 30 minutes Uptime 100% = Operators = 1 WIP = 1,000 "L", 1,350 "S" (before Pierce & Form) Cycle time=45 seconds Setup time=45 minutes Uptime = 100% Operators = 1 WIP = 200 "L", 1,450 "S" (before Finish Grind) Process Step 4 Shipping Supplier WIP = 600 "L", 1,300 "S" (after Finish Grind) One shipment a day in trays of 60 pieces Information Information Flow All communications from customer are electronic: 180/90/60/30/day Forecasts Daily Order All communications to supplier are electronic 4-week Forecast Weekly Fax There is a weekly schedule manually delivered to Press, Pierce & Form, and Finish Grind and a Daily Ship Schedule manually delivered to Shipping All material is pushed Print Done
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question

Transcribed Image Text:More Info
Overall Process
uestion Viewer
...ributes
Average demand: 2,700/week (1,400 "L"; 1,300 "S")
Batch size: 1,000
Number of shifts per day: 1
Availability: 8 hours per shift with two 30 minute lunch breaks
Process Step 1
Press
Process Step 2
Pierce & Form
Process Step 3
Finish Grind
Process Step 4
Supplier
Information
Information Flow
Shipping
Cycle time 4 seconds
Setup time = 2 hours
Uptime = 90%
Operators = 1
Every Part Every = 1 week
WIP 1 day of sheets (before Press)
Cycle time = 30 seconds
Setup time 30 minutes
Uptime = 100%
Operators = 1
WIP = 1,000 "L", 1,350 "S" (before Pierce & Form)
Cycle time 45 seconds
Setup time=45 minutes
Uptime = 100%
Operators = 1
WIP=200 "L", 1,450 "S" (before Finish Grind)
WIP=600 "L", 1,300 "S" (after Finish Grind)
One shipment a day in trays of 60 pieces
All communications from customer are electronic:

Transcribed Image Text:Question Viewer nfo
Process Step 2
Pierce & Form
Process Step 3
Finish Grind
WIP = 1 day of sheets (before Press)
Cycle time 30 seconds
Setup time 30 minutes
Uptime 100%
=
Operators = 1
WIP = 1,000 "L", 1,350 "S" (before Pierce & Form)
Cycle time=45 seconds
Setup time=45 minutes
Uptime = 100%
Operators = 1
WIP = 200 "L", 1,450 "S" (before Finish Grind)
Process Step 4 Shipping
Supplier
WIP = 600 "L", 1,300 "S" (after Finish Grind)
One shipment a day in trays of 60 pieces
Information
Information Flow
All communications from customer are electronic:
180/90/60/30/day Forecasts
Daily Order
All communications to supplier are electronic
4-week Forecast
Weekly Fax
There is a weekly schedule manually delivered to Press, Pierce & Form, and
Finish Grind and a Daily Ship Schedule manually delivered to Shipping
All material is pushed
Print
Done
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.