The Optimal Business Integration Consulting Company has been contracted to execute an Enterprise Resource Planning System. The company has determined that the following activities will need to be performed within the expected durations shown below. Based on the provided schedule, provide the solutions for the following requests: Activity A Predecessor Duration 9 BC A 2 B 4 D A 8 E D 7 F C, E 9 G F 5 H F 4 I F 2 J G, H, I 4 K J 3 L K 1 1. Find out the overall time required to complete the project. 2. Calculate the activities Total Float (Total Slack). 3. Calculate the activities Free Float (Free Slack). 4. Determine the critical path for this project and indicate it on the CPM chart. 5. Identify the activities that can be delayed without affecting the start of the immediate following activities.
The Optimal Business Integration Consulting Company has been contracted to execute an Enterprise Resource Planning System. The company has determined that the following activities will need to be performed within the expected durations shown below. Based on the provided schedule, provide the solutions for the following requests: Activity A Predecessor Duration 9 BC A 2 B 4 D A 8 E D 7 F C, E 9 G F 5 H F 4 I F 2 J G, H, I 4 K J 3 L K 1 1. Find out the overall time required to complete the project. 2. Calculate the activities Total Float (Total Slack). 3. Calculate the activities Free Float (Free Slack). 4. Determine the critical path for this project and indicate it on the CPM chart. 5. Identify the activities that can be delayed without affecting the start of the immediate following activities.
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter9: Decision Making Under Uncertainty
Section: Chapter Questions
Problem 46P
Related questions
Question

Transcribed Image Text:The Optimal Business Integration Consulting Company has been contracted to execute an Enterprise
Resource Planning System. The company has determined that the following activities will need to
be performed within the expected durations shown below. Based on the provided schedule, provide
the solutions for the following requests:
Activity
A
Predecessor
Duration
9
BC
A
2
B
4
D
A
8
E
D
7
F
C, E
9
G
F
5
H
F
4
I
F
2
J
G, H, I
4
K
J
3
L
K
1
1. Find out the overall time required to complete the project.
2. Calculate the activities Total Float (Total Slack).
3. Calculate the activities Free Float (Free Slack).
4. Determine the critical path for this project and indicate it on the CPM chart.
5. Identify the activities that can be delayed without affecting the start of the immediate
following activities.
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 1 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Management, Loose-Leaf Version
Management
ISBN:
9781305969308
Author:
Richard L. Daft
Publisher:
South-Western College Pub

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Management, Loose-Leaf Version
Management
ISBN:
9781305969308
Author:
Richard L. Daft
Publisher:
South-Western College Pub