Immediate Predecessor(s) The following information is known about a proiect to upgrade a point-of-sale system at Kids and Tots Apparel: Question Viewer Activity А Activity Time (days) 7 233535 ABCDEFG G a. Choose the correct network diagram for this project. ○ A. Q ○ B. A A B, C D E E Q Question Viewer (B2 3 (DM) A Start 7 3 (F3) 5 E GM) G (05) Finish ☑ D. A 7 B 2 Start-9-9 F 3 D 3 5 G 3 b. Determine the critical path and project duration. The critical path is path A-C-D-E-G and the project duration is 23 days. (Enter your response as an integer.) c. Calculate the slack for each activity. (Enter your responses as integers.) Slack Activity A (days) B 0 D EFG 5 Finish ✓

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Immediate Predecessor(s)
The following information is known about a proiect to upgrade a point-of-sale system at Kids and Tots Apparel:
Question Viewer
Activity
А
Activity Time (days)
7
233535
ABCDEFG
G
a. Choose the correct network diagram for this project.
○ A.
Q
○ B.
A
A
B, C
D
E
E
Q
Transcribed Image Text:Immediate Predecessor(s) The following information is known about a proiect to upgrade a point-of-sale system at Kids and Tots Apparel: Question Viewer Activity А Activity Time (days) 7 233535 ABCDEFG G a. Choose the correct network diagram for this project. ○ A. Q ○ B. A A B, C D E E Q
Question Viewer
(B2
3
(DM)
A
Start
7
3
(F3)
5
E
GM)
G
(05)
Finish
☑
D.
A
7
B
2
Start-9-9
F
3
D
3
5
G
3
b. Determine the critical path and project duration.
The critical path is path A-C-D-E-G and the project duration is 23 days. (Enter your response as an integer.)
c. Calculate the slack for each activity. (Enter your responses as integers.)
Slack
Activity
A
(days)
B
0
D
EFG
5
Finish ✓
Transcribed Image Text:Question Viewer (B2 3 (DM) A Start 7 3 (F3) 5 E GM) G (05) Finish ☑ D. A 7 B 2 Start-9-9 F 3 D 3 5 G 3 b. Determine the critical path and project duration. The critical path is path A-C-D-E-G and the project duration is 23 days. (Enter your response as an integer.) c. Calculate the slack for each activity. (Enter your responses as integers.) Slack Activity A (days) B 0 D EFG 5 Finish ✓
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.