Given the following information, answer the following: Task Description Immediate predecessors Optimistic time Most likely time Pessimistic time Expected Time A Identify equipment requirements None 4 6 8 6 B Solicit bids from vendors None 6 8 16 9 C Select a system/vendor A,B 2 4 6 4 D Place order for system C 8 10 24 12 E redesign warehouse layout C 7 10 13 10 F Implement new warehouse design E 4 6 8 6 G Design system interfaced c 4 6 20 8 H Integrate the interface into the system D, F, G 4 6 8 6 I Install the system D, F 4 6 14 7 J train system operators H 3 4 5 4 k test system I, J 2 4 6 4   Task Normal cost Crashed  time Additional cost to crash 1 week A 1000 4 450 B 1000 7 400 C 1500 2 600 D 2000 8 300 E 5000 7 1000 F 3000 4 550 G 8000 5 750 H 5000 4 700 I 10000 4 800 J 4000 3 400 K 5000 3 500 B-C-E-F-H-J-K =  9+4+10+6+6+4+4 = 43 weeks to complete on normal time= critical path What is the total cost required for completing this project on normal time?  What is the probability of completing the project in 40 weeks? Round calculations to at least 4 decimal places. 3. If Kerry Goins wishes to finish the project 2 weeks sooner, which activity(ies) should be crashed?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question
100%

Given the following information, answer the following:

Task

Description

Immediate predecessors

Optimistic time

Most likely time

Pessimistic time

Expected Time

A

Identify equipment requirements

None

4

6

8

6

B

Solicit bids from vendors

None

6

8

16

9

C

Select a system/vendor

A,B

2

4

6

4

D

Place order for system

C

8

10

24

12

E

redesign warehouse layout

C

7

10

13

10

F

Implement new warehouse design

E

4

6

8

6

G

Design system interfaced

c

4

6

20

8

H

Integrate the interface into the system

D, F, G

4

6

8

6

I

Install the system

D, F

4

6

14

7

J

train system operators

H

3

4

5

4

k

test system

I, J

2

4

6

4

 

Task

Normal cost

Crashed  time

Additional cost to crash 1 week

A

1000

4

450

B

1000

7

400

C

1500

2

600

D

2000

8

300

E

5000

7

1000

F

3000

4

550

G

8000

5

750

H

5000

4

700

I

10000

4

800

J

4000

3

400

K

5000

3

500

B-C-E-F-H-J-K =  9+4+10+6+6+4+4 = 43 weeks to complete on normal time= critical path

  1. What is the total cost required for completing this project on normal time? 
    What is the probability of completing the project in 40 weeks? Round calculations to at least 4 decimal places.
    3. If Kerry Goins wishes to finish the project 2 weeks sooner, which activity(ies) should be crashed?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 4 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.