Quiz: Consider a process consisting of five resources that are operated eight hours per day. 2 3 4 5 The process works on three different products, A, B, and C: Resources # of Workers for A [Min/Unit] Processing Time Processing Time Processing Time for B [Min/Unit] for C [Min/Unit] 1 2 5 5 5 2 2 3 5 3 1 15 0 0 4 1 0 3 3 5 2 6 Demand for the three different products is as follows: Product A, 40 units per day, Product B, 50 Units per day, and product C, 60 units per day. What is the bottleneck? What is the flow rate for each flow unit assuming that demand must be served in the mix described above (i.e., for every four units of A, there are five units of B and six units of C)?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
icon
Related questions
Question

Consider a process consisting of five resources that are operated eight hours per day. 

Demand for the three different products is as follows: Product A, 40 units per day, Product B, 50 Units per day, and product C, 60 units per day.

What is the bottleneck?

What is the flow rate for each flow unit assuming that demand must be served in the mix described above (i.e., for every four units of A, there are five units of B and six units of C)?

Quiz:
Consider a process consisting of five resources that are operated eight hours per
day.
2
3
4
5
The process works on three different products, A, B, and C:
Resources # of
Workers for A [Min/Unit]
Processing Time
Processing Time
Processing Time
for B [Min/Unit]
for C [Min/Unit]
1
2
5
5
5
2
2
3
5
3
1
15
0
0
4
1
0
3
3
5
2
6
Demand for the three different products is as follows: Product A, 40 units per day,
Product B, 50 Units per day, and product C, 60 units per day.
What is the bottleneck?
What is the flow rate for each flow unit assuming that demand must be served in
the mix described above (i.e., for every four units of A, there are five units of B
and six units of C)?
Transcribed Image Text:Quiz: Consider a process consisting of five resources that are operated eight hours per day. 2 3 4 5 The process works on three different products, A, B, and C: Resources # of Workers for A [Min/Unit] Processing Time Processing Time Processing Time for B [Min/Unit] for C [Min/Unit] 1 2 5 5 5 2 2 3 5 3 1 15 0 0 4 1 0 3 3 5 2 6 Demand for the three different products is as follows: Product A, 40 units per day, Product B, 50 Units per day, and product C, 60 units per day. What is the bottleneck? What is the flow rate for each flow unit assuming that demand must be served in the mix described above (i.e., for every four units of A, there are five units of B and six units of C)?
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,