Textbook Question
Chapter 6, Problem 8E
You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 17 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 17 working days.
Draw a project network given the information below. Complete the forward and backward pass, compute the activity slack, and identify the critical path. Do you expect to receive a bonus or a penalty on this project?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
You are the project manager of the software installation project in the table below. You would like to find the minımum-cost
schedule for your project. There is a $500-per-week penalty for each week the project is delayed beyond week 25. In
addition, your project team determined that indirect project costs are $2,000 per week.
Normal Cost Crash Time Crash Cost
($)
3,000
3,000
10,000
Normal Time
(weeks)
Immediate
Activity
Predecessor(s)
(weeks)
(S)
A
1
3,000
6,000
C
A
9.
8.
12,000
8
2.
А, В
10
3,000
9.000
4,000
5,000
2,000
3.000
5,000
9,000
7,000
12
6.
E, F
2
1
G
5.000
C, F
8
2,000
8.000
a. What would be your target completion week?
The target completion week is week (Enter your response as an integer.)
Prepare a plan for a small project of moderate complexity (at least 12 activities, with some interdependencies between activities).
Your plan should identify the activity by their beginning and ending nodes and by short, descriptive titles. Estimate the times to
complete the activities. Prepare a PERT/CPM network. Determine critical path and the expected time for completing the project
(Activity Analysis and Event Analysis). Choose a project of some personal interest and knowledge (e.g. building a house, selling a
house, political campaign etc.) Your project will be judged by how completely it identifies all activities, the reasonableness of your
time estimates and the correctness of your analysis.
UPLOAD YOUR ANSWER HERE AS IMAGE/PDF.
Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut two days from the project's duration,
to project cost and activity
should be crashed second, adding
to project cost.
activity
should be crashed first, adding
Activity
Normal Time Normal Cost
Crash Time
Crash Cost
8 days
$6,000
7 days
$6,400
10 days
$4,000
9 days
$5,000
B
A; $400 and then A; $400
nA; $400 and then B; $1000
n B; $1000 and then A; $400
B; $1000 and then B; $1000
Chapter 6 Solutions
PROJECT MANAGEMENT (LOOSELEAF)-W/ACCESS
Ch. 6 - How does the WBS differ from the project network?Ch. 6 - How are WBS and project networks linked?Ch. 6 - Why bother creating a WBS? Why not go straight to...Ch. 6 - Why is slack important to the project manager?Ch. 6 - What is the difference between free slack and...Ch. 6 - Why are lags used in developing project networks?Ch. 6 - What is a hammock activity, and when is it used?Ch. 6 - Here is a partial work breakdown structure for a...Ch. 6 - Draw a project network from the following...Ch. 6 - Draw a project network from the following...
Ch. 6 - Draw a project network from the following...Ch. 6 - Draw a project network from the following...Ch. 6 - From the following information, develop an AON...Ch. 6 - The project information for the custom order...Ch. 6 - You have signed a contract to build a garage for...Ch. 6 - You are creating a customer database for the...Ch. 6 - K. Nelson, project manager of Print Software....Ch. 6 - A large Southeast city is requesting federal...Ch. 6 - You are creating a customer database for the...Ch. 6 - You are completing a group term paper. Given the...Ch. 6 - You are managing a product upgrade project for...Ch. 6 - You are creating a database for the Oklahoma City...Ch. 6 - The planning department of an electronics firm has...Ch. 6 - Using Microsoft Project, set up the network and...Ch. 6 - The optical disk project team has started...Ch. 6 - From the following information, compute the early,...Ch. 6 - Given the following information, compute the...Ch. 6 - Given the information in the following lag...Ch. 6 - Given the network below, compute the early, late,...Ch. 6 - The CyClon project team has started gathering...Ch. 6 - Advantage Energy Technology Data Center...Ch. 6 - Advantage Energy Technology Data Center...Ch. 6 - Advantage Energy Technology Data Center...Ch. 6 - The GE Company is preparing a bid to build the new...Ch. 6 - The GE Company is preparing a bid to build the new...Ch. 6 - The G&E Company is preparing a bid to build the...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.Similar questions
- The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Duration (weeks) This exercise contains only parts b, c, and d. b) The activities on the critical path are A-B-F Activity A (start) BU C E F (end) 1 2362 10 Precedes B, C F E F c) The total project completion time for Rafay Ishfaq's software firm is 13 weeks. (Enter your response as a whole number.) d) Determine the slack time for each of the activities. (Enter your responses as whole numbers.) Activity Slack Time (weeks)arrow_forwardThe following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Duration (weeks) Precedes B, C E F F Activity A (start) What is the total slack for the non critical path(s) in the project? BOE C F (end) 1 2. 2182 This exercise contains only parts b, c, and d. b) The activities on the critical path are c) The total project completion time for Rafay Ishfaq's software firm is weeks. (Enter your response as a whole number.) d) Determine the slack time for each of the activities. (Enter your responses as whole numbers.) ABC EF 11 Activity Slack Time (weeks) week(s) (Enter your response as a whole number.)arrow_forwardConsider the project described in the table below: Activity Duration A B C D E F G H 9 4 8 8 5 7 4 6 OEST-9 and LCT = 15 OEST=9 and LCT = 13 Immediate Predecessor What is the earliest start time (EST) and latest completion time (LCT) of activity B? OEST=9 and LCT = 20 OEST-9 and LCT-17 - A A A B B,C C,D E,F,Garrow_forward
- Suppose you are the project manager for the following project: First, draw a network diagram for the project. Determine the critical path and slack times for all of the tasks. This completes your plan for the project schedule. During project execution, you become aware of the need to change the duration of Task 4 to five days. Meanwhile, Task 3 has been finished one day early, so it only took one day to do. What, if any, effects do these changes have on your project? What would have happened if you had not been monitoring the status of the project?arrow_forwardTwo activities on the same critical path are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity ________ should be crashed first, adding ________ to project cost.arrow_forwardYou may need to use the appropriate technology to answer this question. A project consists of five activities as shown in the following table. Activity Floor sanding Floor buffing Paint mixing Wall painting Ceiling painting Start Optimistic Time (hr) Most Probable Time (hr) Start Floor Buffing Paint Mixing Naturally, paint mixing precedes the painting activities. Also, (a) Construct the PERT/CPM network for this problem. Floor Sanding 4 Paint Mixing 4 0.5 3 3 Paint Wall Paint Ceiling Paint Ceiling Paint Wall 5 5 1 4 7.5 Floor Sanding Pessimistic Time (hr) Floor Buffing Finish 6 Finish 6 ceiling painting and floor sanding must be dor 1.5 11 9 i Start Start prior to floor buffing. Floor Sanding Paint Mixing Floor Buffing Paint Mixing Paint Ceiling Paint Wall Paint Wall Paint Ceiling Floor Buffing Floor Sanding Finish Finisharrow_forward
- Two activities on the same critical path are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity. should be crashed first, adding. to project cost. Activity Normal Time Normal Cost Crash Time Crash Cost One Two 8 days 10 days $6,000 $4,000 7 days 8 days One; $800 One: $6,800 Two; $500 Two; $5,000 One or Two should be crashed; $1,300 $6,800 $5,000arrow_forwardManagement & Science University (MSU) have appointed you as a project manager to conduct a Joint Application Design (JAD) session with members from various departments. As a project manager, you are required to develop a specific schedule for the tasks listed below. The estimated task duration for each shown in parentheses. First, you must contact and brief the participants and explain their responsibilities (1 day). Then you must obtain approval from their department managers (3 days). After you have obtained the approval, you can begin the two tasks where you can prepare the agenda for the JAD session (7 days) and arrange the meeting room (2 days) When the agenda is ready, you can start two more concurrent tasks which are preparing the information packets (4 days) and to create visual aids (8 days). When the meeting room is arranged and information packets are ready, you can send out an email to all participants (1 day). Finally, after the e-mail is sent to participants and the…arrow_forwardDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A 7 − E 5 B B 8 − F 6 B C 4 A G 11 C, E D 3 A H 7 D , F Part 2 Dave's earliest start (ES) and earliest finish (EF) are: Part 3 Part 4 Part 5 Part 6 Part 7 Part 8 Part 9 Part 10 Dave's latest start (LS) and latest finish (LF) are:…arrow_forward
- Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A 7 − E 4 B B 6 − F 5 B C 4 A G 10 C, E D 2 A H 8 D , F Part 2 Dave's earliest start (ES) and earliest finish (EF) are: Part 3 Part 4 Part 5 Part 6 Part 7 Part 8 Part 9 Part 10 Dave's latest start (LS) and latest finish (LF) are:…arrow_forwardYou have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 30 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 30 working days. Given the information below, complete the forward and backward pass, compute activity slack, and identify the critical activities. Time (days) 4 3 5 2 ID A BC с D E F G H I J K Description Prepare site Pour foundation Erect frame Roof Windows Doors Electrical Rough-in frame Door opener Paint Cleanup The project will take The critical activities are The early start on Activity D is The late start on Activity E is The slack on Activity E is The slack on Activity F is Predecessor None A (BUCCU с с с D, E, F, G F, G H, I J A, B, C, F, H, J, K MAN MA 4 2 5 3 2 4 28 days. 7 days. days. 10 days. days.arrow_forwardDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: O Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) E F A B C D Dave's earliest start (ES) and earliest finish (EF) are: 5 8 00 2 2 Activity HOT G ES Н EF 5 5 5 10 7 B B C, E D.Farrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Understanding BusinessManagementISBN:9781259929434Author:William NickelsPublisher:McGraw-Hill EducationManagement (14th Edition)ManagementISBN:9780134527604Author:Stephen P. Robbins, Mary A. CoulterPublisher:PEARSONSpreadsheet Modeling & Decision Analysis: A Pract...ManagementISBN:9781305947412Author:Cliff RagsdalePublisher:Cengage Learning
- Management Information Systems: Managing The Digi...ManagementISBN:9780135191798Author:Kenneth C. Laudon, Jane P. LaudonPublisher:PEARSONBusiness Essentials (12th Edition) (What's New in...ManagementISBN:9780134728391Author:Ronald J. Ebert, Ricky W. GriffinPublisher:PEARSONFundamentals of Management (10th Edition)ManagementISBN:9780134237473Author:Stephen P. Robbins, Mary A. Coulter, David A. De CenzoPublisher:PEARSON
Understanding Business
Management
ISBN:9781259929434
Author:William Nickels
Publisher:McGraw-Hill Education
Management (14th Edition)
Management
ISBN:9780134527604
Author:Stephen P. Robbins, Mary A. Coulter
Publisher:PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract...
Management
ISBN:9781305947412
Author:Cliff Ragsdale
Publisher:Cengage Learning
Management Information Systems: Managing The Digi...
Management
ISBN:9780135191798
Author:Kenneth C. Laudon, Jane P. Laudon
Publisher:PEARSON
Business Essentials (12th Edition) (What's New in...
Management
ISBN:9780134728391
Author:Ronald J. Ebert, Ricky W. Griffin
Publisher:PEARSON
Fundamentals of Management (10th Edition)
Management
ISBN:9780134237473
Author:Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:PEARSON
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY