Textbook Question
Chapter 6, Problem 14E
You are managing a product upgrade project for Bangkokagogo. Given the project network that follows, complete the forward and backward pass, compute activity slack, and identify the critical path. Use this information to create a Gantt chart for the project. Be sure to show slack for noncritical activities.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
Prepare a plan for a small project of moderate complexity (at least 12 activities, with some interdependencies between activities).
Your plan should identify the activity by their beginning and ending nodes and by short, descriptive titles. Estimate the times to
complete the activities. Prepare a PERT/CPM network. Determine critical path and the expected time for completing the project
(Activity Analysis and Event Analysis). Choose a project of some personal interest and knowledge (e.g. building a house, selling a
house, political campaign etc.) Your project will be judged by how completely it identifies all activities, the reasonableness of your
time estimates and the correctness of your analysis.
UPLOAD YOUR ANSWER HERE AS IMAGE/PDF.
Use the Program Evaluation and Review Technique to represent the project in an activity network. In conjunction with the Critical Path Method, use the activity network to find the shortest time possible to complete the project, to identify the critical jobs in the project, and to determine the earliest and latest that each activity can start and finish without making the project completion longer.a=1, b=1, c=6, d=5, e=2, f=5; andab=1x1=1, bc=1x6=6, cd=6x5=30, de=5x2=10, ef=2x5=10, af=1x5=5.
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede:
Duration (weeks)
Precedes
B, C
E
F
F
Activity
A (start)
What is the total slack for the non critical path(s) in the project?
BOE
C
F (end)
1
2.
2182
This exercise contains only parts b, c, and d.
b) The activities on the critical path are
c) The total project completion time for Rafay Ishfaq's software firm is weeks. (Enter your response as a whole number.)
d) Determine the slack time for each of the activities. (Enter your responses as whole numbers.)
ABC EF
11
Activity Slack Time (weeks)
week(s) (Enter your response as a whole number.)
Chapter 6 Solutions
PROJECT MANAGEMENT (LOOSELEAF)-W/ACCESS
Ch. 6 - How does the WBS differ from the project network?Ch. 6 - How are WBS and project networks linked?Ch. 6 - Why bother creating a WBS? Why not go straight to...Ch. 6 - Why is slack important to the project manager?Ch. 6 - What is the difference between free slack and...Ch. 6 - Why are lags used in developing project networks?Ch. 6 - What is a hammock activity, and when is it used?Ch. 6 - Here is a partial work breakdown structure for a...Ch. 6 - Draw a project network from the following...Ch. 6 - Draw a project network from the following...
Ch. 6 - Draw a project network from the following...Ch. 6 - Draw a project network from the following...Ch. 6 - From the following information, develop an AON...Ch. 6 - The project information for the custom order...Ch. 6 - You have signed a contract to build a garage for...Ch. 6 - You are creating a customer database for the...Ch. 6 - K. Nelson, project manager of Print Software....Ch. 6 - A large Southeast city is requesting federal...Ch. 6 - You are creating a customer database for the...Ch. 6 - You are completing a group term paper. Given the...Ch. 6 - You are managing a product upgrade project for...Ch. 6 - You are creating a database for the Oklahoma City...Ch. 6 - The planning department of an electronics firm has...Ch. 6 - Using Microsoft Project, set up the network and...Ch. 6 - The optical disk project team has started...Ch. 6 - From the following information, compute the early,...Ch. 6 - Given the following information, compute the...Ch. 6 - Given the information in the following lag...Ch. 6 - Given the network below, compute the early, late,...Ch. 6 - The CyClon project team has started gathering...Ch. 6 - Advantage Energy Technology Data Center...Ch. 6 - Advantage Energy Technology Data Center...Ch. 6 - Advantage Energy Technology Data Center...Ch. 6 - The GE Company is preparing a bid to build the new...Ch. 6 - The GE Company is preparing a bid to build the new...Ch. 6 - The G&E Company is preparing a bid to build the...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.Similar questions
- A project's activities must be completed in the sequence indicated below. Activity Immediately Preceding Activity Duration in Weeks A - 3 B - 20 C - 15 D - 10 E - 5 F A 4 G D 3 H D, E 10 I F 3 J B 10 K G, H 7 L B, I 5 The project ends with the intersection of activities: C, J, K and L 1- Use CPM to construct (Draw) the project Network and find the critical path. 2- How long is the project expected to takearrow_forwardThe following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Duration (weeks) This exercise contains only parts b, c, and d. b) The activities on the critical path are A-B-F Activity A (start) BU C E F (end) 1 2362 10 Precedes B, C F E F c) The total project completion time for Rafay Ishfaq's software firm is 13 weeks. (Enter your response as a whole number.) d) Determine the slack time for each of the activities. (Enter your responses as whole numbers.) Activity Slack Time (weeks)arrow_forwardYou are the project manager of the software installation project in the table below. You would like to find the minımum-cost schedule for your project. There is a $500-per-week penalty for each week the project is delayed beyond week 25. In addition, your project team determined that indirect project costs are $2,000 per week. Normal Cost Crash Time Crash Cost ($) 3,000 3,000 10,000 Normal Time (weeks) Immediate Activity Predecessor(s) (weeks) (S) A 1 3,000 6,000 C A 9. 8. 12,000 8 2. А, В 10 3,000 9.000 4,000 5,000 2,000 3.000 5,000 9,000 7,000 12 6. E, F 2 1 G 5.000 C, F 8 2,000 8.000 a. What would be your target completion week? The target completion week is week (Enter your response as an integer.)arrow_forward
- Consider the project described in the table below: Activity Duration A B C D E F G H 9 4 8 8 5 7 4 6 OEST-9 and LCT = 15 OEST=9 and LCT = 13 Immediate Predecessor What is the earliest start time (EST) and latest completion time (LCT) of activity B? OEST=9 and LCT = 20 OEST-9 and LCT-17 - A A A B B,C C,D E,F,Garrow_forwardDraw the network diagram based on the information given below. Calculate the ES, EF, LS, LF and slack for each activity and identify the critical path. Can the project be completed in 40 weeks? Activity Preceding Activity Time (Weeks) ES EF LS LF Slack A 10 B 8 C A, B 6 D A 8 E B 9 F C, D 7 G D, E 12 H F, G 10 b) Assume that activity A actually finished at the 9th week, activity B actually finished at the 10th Recalculate the expected project completion time. Which activities would you focus on in order to get the project back on schedule?arrow_forwardUsing the below project network diagram, what is the Earliest Start (ES) time of activity G? The duration of each activity is presented within the parentheses in front of each activity. For example, activity A(2) in this project takes 2 weeks. Type your answer in the textbox below. A(2) E(6) D(3) C(2) G(3) B(5) F(6)arrow_forward
- Draw the network diagram based on the information given below. Calculate the ES, EF, LS, LF and slack for each activity and identify the critical path. Can the project be completed in 40 weeks? Assume that activity A actually finished at the 9th week, activity B actually finished at the 10th Recalculate the expected project completion time. Which activities would you focus on in order to get the project back on schedule? Activity Preceding Activity Time (Weeks) ES EF LS LF Slack A 10 B 8 C A, B 6 D A 8 E B 9 F C, D 7 G D, E 12 H F, G 10arrow_forwardConsider the following data (ETB and days). Draw activity network of the project. Crash the activities step by step until all paths are critical. Activity Normal Time Normal Cost Crash Time Crash Cost 1-2 20 600 17 720 1-3 25 200 25 200 2-3 10 300 8 440 2-4 12 400 6 700 3-4 5 300 2 420 4-5 10 300 5 600 4-6 5 600 3 900 5-7 10 500 5 800 6-7 8 400 3 700arrow_forwardYou may need to use the appropriate technology to answer this question. Consider the PERT/CPM network with estimated times in weeks shown in the following figure. The project is scheduled to begin on May 1. Start Activity A B C D E F G A H The three-time estimate approach was used to calculate the expected times and the following table gives the variance for each activity. Variance 1.0 0.4 1.3 0.9 0.2 0.7 0.5 B 0.9 E 1 D C 4 F G 3 H 7 Finish 4 (a) Give the expected project completion date and the critical path. (Enter your critical path as a comma-separated list.) The expected project completion is weeks from May 1 with a critical path of (b) Based only on the critical path, by what date are you 99% sure the project will be completed? (Round your answer to one decimal place.) weeks from May 1.arrow_forward
- When developing a schedule network diagram, the project manager must take into account the dependencies between activities as well as the start and finish relationships between activities. List and describe the four types of schedule activity relationships List and describe the four types of schedule activity dependencies Include examples of each item above, that do not come from the PMBOK.arrow_forwardSuppose you are the project manager for the following project: First, draw a network diagram for the project. Determine the critical path and slack times for all of the tasks. This completes your plan for the project schedule. During project execution, you become aware of the need to change the duration of Task 4 to five days. Meanwhile, Task 3 has been finished one day early, so it only took one day to do. What, if any, effects do these changes have on your project? What would have happened if you had not been monitoring the status of the project?arrow_forwardYou may need to use the appropriate technology to answer this question. A project consists of five activities as shown in the following table. Activity Floor sanding Floor buffing Paint mixing Wall painting Ceiling painting Start Optimistic Time (hr) Most Probable Time (hr) Start Floor Buffing Paint Mixing Naturally, paint mixing precedes the painting activities. Also, (a) Construct the PERT/CPM network for this problem. Floor Sanding 4 Paint Mixing 4 0.5 3 3 Paint Wall Paint Ceiling Paint Ceiling Paint Wall 5 5 1 4 7.5 Floor Sanding Pessimistic Time (hr) Floor Buffing Finish 6 Finish 6 ceiling painting and floor sanding must be dor 1.5 11 9 i Start Start prior to floor buffing. Floor Sanding Paint Mixing Floor Buffing Paint Mixing Paint Ceiling Paint Wall Paint Wall Paint Ceiling Floor Buffing Floor Sanding Finish Finisharrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Understanding BusinessManagementISBN:9781259929434Author:William NickelsPublisher:McGraw-Hill EducationManagement (14th Edition)ManagementISBN:9780134527604Author:Stephen P. Robbins, Mary A. CoulterPublisher:PEARSONSpreadsheet Modeling & Decision Analysis: A Pract...ManagementISBN:9781305947412Author:Cliff RagsdalePublisher:Cengage Learning
- Management Information Systems: Managing The Digi...ManagementISBN:9780135191798Author:Kenneth C. Laudon, Jane P. LaudonPublisher:PEARSONBusiness Essentials (12th Edition) (What's New in...ManagementISBN:9780134728391Author:Ronald J. Ebert, Ricky W. GriffinPublisher:PEARSONFundamentals of Management (10th Edition)ManagementISBN:9780134237473Author:Stephen P. Robbins, Mary A. Coulter, David A. De CenzoPublisher:PEARSON
Understanding Business
Management
ISBN:9781259929434
Author:William Nickels
Publisher:McGraw-Hill Education
Management (14th Edition)
Management
ISBN:9780134527604
Author:Stephen P. Robbins, Mary A. Coulter
Publisher:PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract...
Management
ISBN:9781305947412
Author:Cliff Ragsdale
Publisher:Cengage Learning
Management Information Systems: Managing The Digi...
Management
ISBN:9780135191798
Author:Kenneth C. Laudon, Jane P. Laudon
Publisher:PEARSON
Business Essentials (12th Edition) (What's New in...
Management
ISBN:9780134728391
Author:Ronald J. Ebert, Ricky W. Griffin
Publisher:PEARSON
Fundamentals of Management (10th Edition)
Management
ISBN:9780134237473
Author:Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:PEARSON
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY