Concept explainers
Using Microsoft Project, set up the network and determine the critical path for Phase 1 of the Whistler Ski Resort project. The project workweek will be 5 days (M-F).
Whistler Ski Resort Project
Given the fact that the number of skiing visitors to Whistler, B.C., Canada, has been increasing at an exciting rate, thanks to the 2010 Winter Olympics, the Whistler Ski Association has been considering construction of another ski lodge and ski complex. The results of an economic feasibility study just completed by members of the staff show that a winter resort complex near the base of Whistler Mountain could be a very profitable venture. The area is accessible by car, bus, train, and air. The board of directors has voted to build the 10-million-dollar complex recommended in the study. Unfortunately, due to the short summer season, the complex will have to be built in stages. The first stage (year 1) will contain a day lodge, chair lift, rope tow, generator house (for electricity), and a parking lot designed to accommodate 400 cars and 30 buses. The second and third stages will include a hotel, ice rink, pool, shops, two additional chair lifts, and other attractions. The board has decided that stage one should begin no later than April 1 and be completed by October 1, in time for the next skiing season. You have been assigned the task of project manager, and it is your job to coordinate the ordering of materials and construction activities to ensure the project’s completion by the required date.
After looking into the possible sources of materials, you are confronted with the following time estimates. Materials for the chair lift and rope tow will take 30 days and 12 days, respectively, to arrive once the order is submitted. Lumber for the day lodge, generator hut, and foundations will take 9 days to arrive. The electrical and plumbing materials for the day lodge will take 12 days to arrive. The generator will take 12 days to arrive. Before actual construction can begin on the various facilities, a road to the site must be built; this will take 6 days. As soon as the road is in. clearing can begin concurrently on the sites of the day lodge, generator house, chair lift, and rope tow. It is estimated that the clearing task at each site will take 6 days, 3 days, 36 days, and 6 days, respectively. The clearing of the main ski slopes can begin after the area for the chair lift has been cleared; this will take 84 days.
The foundation for the day lodge will take 12 days to complete. Construction of the main framework will take an additional 18 days. After the framework is completed, electrical wiring and plumbing can be installed concurrently. These should take 24 and 30 days, respectively. Finally, the finishing construction on the day lodge can begin; this will take 36 days.
Installation of the chair lift towers (67 days) can begin once the site is cleared, lumber delivered, and the foundation completed (6 days). Also, when the chair lift site has been cleared, construction of a permanent road to the upper towers can be started; this will take 24 days. While the towers are being installed, the electric motor to drive the chair lift can be installed; the motor can be installed in 24 days. Once the towers are completed and the motor installed, it will take 3 days to install the cable and an additional 12 days to install the chairs.
Installation of the towers for the rope tow can begin once the site is cleared and the foundation is built and poured; it takes 4 days to build the foundation, pour the concrete and let it cure, and 20 days to install the towers for the rope tow. While the towers are being erected, installation of the electric motor to drive the rope tow can begin; this activity will take 24 days. After the towers and motor are installed, the rope tow can be strung in 1 day. The parking lot can be cleared once the rope tow is finished; this task will take 18 days.
The foundation for the generator house can begin at the same time as the foundation for the lodge; this will take 6 days. The main framework for the generator house can begin once the foundation is completed; framing will take 12 days. After the house is framed, the diesel generator can be installed in 18 days. Finishing construction on the generator house can now begin and will take 12 more days.
Assignment:
Identify the critical path on your network.
Can the project be completed by October 1?
Want to see the full answer?
Check out a sample textbook solutionChapter 6 Solutions
PROJECT MANAGEMENT (LOOSELEAF)-W/ACCESS
- Using Microsoft Project, set up the network and determine the critical path for Phase 1 of the project. The project workweek will be 5 days (M—F). Whistler Ski Resort Project Given the fact that the number of skiing visitors to Whistler, B.C., Canada has been increasing at an exciting rate, thanks to the 2010 Winter Olympics, the Whistler Ski Association has been considering construction of another ski lodge and ski complex. The results of an economic feasibility study just completed by members of the staff show that a winter resort complex near the base of Whistler Mountain could be a very profitable venture. The area is accessible by car, bus, train, and air. The board of directors has voted to build the ten-million dollar complex recommended in the study. Unfortunately, due to the short summer season, the complex will have to be built in stages. The first stage (year 1) will contain a day lodge, chair lift, rope tow, generator house (for electricity), and a parking lot designed to…arrow_forward(please try to do math in handwritten) Use the following project data for problem 1 through 5 Activity name Predecessor Activity Activity Duration N 3 M 2 P M,N 4 3 P,Q R,S 2. 1. Prepare an AON Network Diagram 2. Identify all possible paths. Provide that information in a table. The heading of your table should as follow: Path Duration 3. Perform a forward pass and a backward pass. Display your result in an AON diagram.Usethe follow legend for your node(s) Activity ES EF Duration LS LF 4. Prepare a table summarizing the results of your Activity Schedule. The heading of your table should as follows: Activity name ES Slack EF LS LF 5. Identify the critical path. What is the project duration? 2. 4.arrow_forwardSolve asap! a)Find critical path and project completion time for the project network as given below, the require data is available in Table. 1arrow_forward
- You may need to use the appropriate technology to answer this question. Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 42- week completion date requested by the owner. The Mueller project manager prepared the following project network. Start Activity A B с D E Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows. TI G H Optimistic Most Probable 4 6 6 weeks 3 6 5 10 A 5 8 7 12 5 9 8 B 15 6 Pessimistic 12 8 18 7 18 17 20 (b) What is the expected project completion time (in weeks)? 52 13 F E (a) Find the critical path. (Enter your answers as a comma-separated list.) A,C,E,G,H G H Finish (c) Based only on the critical path, what is the estimated probability the project can be completed in 42 weeks as requested by the owner? (Round your answer to four decimal places.) X (d) Based only on the…arrow_forwardReliable Garage is completing production of the J2000 kit car.The following data are available for the project:Activity Activity Time (days) Immediate Predecessor(s)A 2 —B 6 AC 4 BD 5 CE 7 CF 5 CG 5 FH 3 D, E, Ga. Draw the network diagram for the project.b. Determine the project’s critical path and duration.c. What is the slack for each activity?arrow_forwardBelow is information about a project to implement a new manufacturing cell to assemble personal digital assistance devices Calculate the expected time for all tasks and maintain one decimal place. Complete a critical path analysis. Complete forward and backward passes. What is the critical path? What is the project duration? What is the latest start for Activity 4 "Secure patent?"?arrow_forward
- Project Management 3. Jamaica's Highway 2000 project: Identify and justify the project development approach used for the project. Was it agile, waterfall/traditional or hybrid. 4. Was the Jamaica's Highway 2000 project selection method benefits measurements method or constraint optimization method.arrow_forwardThe project described in the following table is scheduled to be completed in 11 weeks. Constructa network diagram using AOA or AON (see Example 5 for either type). Then answer the following questions:a. If you were the manager of this project, would you be concerned? Explain.b. If there is a penalty of $5,000 a week for each week the project is late, what is the probabilityof incurring a penalty of at least $5,000?Path ActivityEstimated Time(weeks)StandardDeviation (wks.)A C 4 0.70D 6 0.90B E 3 0.62F 9 1.90arrow_forwardNeed help with problem 2arrow_forward
- Understanding BusinessManagementISBN:9781259929434Author:William NickelsPublisher:McGraw-Hill EducationManagement (14th Edition)ManagementISBN:9780134527604Author:Stephen P. Robbins, Mary A. CoulterPublisher:PEARSONSpreadsheet Modeling & Decision Analysis: A Pract...ManagementISBN:9781305947412Author:Cliff RagsdalePublisher:Cengage Learning
- Management Information Systems: Managing The Digi...ManagementISBN:9780135191798Author:Kenneth C. Laudon, Jane P. LaudonPublisher:PEARSONBusiness Essentials (12th Edition) (What's New in...ManagementISBN:9780134728391Author:Ronald J. Ebert, Ricky W. GriffinPublisher:PEARSONFundamentals of Management (10th Edition)ManagementISBN:9780134237473Author:Stephen P. Robbins, Mary A. Coulter, David A. De CenzoPublisher:PEARSON