Textbook Question
Chapter 6, Problem 16E
The planning department of an electronics firm has set up the activities for developing and production of a new MP3 Player. Given the information below develop a project network using Microsoft Project. Assume a five-day workweek and the project starts on January 4,, 2017.
The project team has requested that you create a network for the project, and determine if the project can be completed in 45 weeks.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Prepare a plan for a small project of moderate complexity (at least 12 activities, with some interdependencies between activities).
Your plan should identify the activity by their beginning and ending nodes and by short, descriptive titles. Estimate the times to
complete the activities. Prepare a PERT/CPM network. Determine critical path and the expected time for completing the project
(Activity Analysis and Event Analysis). Choose a project of some personal interest and knowledge (e.g. building a house, selling a
house, political campaign etc.) Your project will be judged by how completely it identifies all activities, the reasonableness of your
time estimates and the correctness of your analysis.
UPLOAD YOUR ANSWER HERE AS IMAGE/PDF.
Michael Bai is the project manager for a project to host the graduation ceremony at your university campus, and he needs your
advice on developing the project schedule.
Explain to Michael the main steps he needs to complete when developing the project schedule (include: identify activities,
determine sequence/network, estimate activity durations, and construct the critical path).
Give examples from the project to host the graduation ceremony at your university campus to support your answer.
You are the project manager of the software installation project in the table below. You would like to find the minımum-cost
schedule for your project. There is a $500-per-week penalty for each week the project is delayed beyond week 25. In
addition, your project team determined that indirect project costs are $2,000 per week.
Normal Cost Crash Time Crash Cost
($)
3,000
3,000
10,000
Normal Time
(weeks)
Immediate
Activity
Predecessor(s)
(weeks)
(S)
A
1
3,000
6,000
C
A
9.
8.
12,000
8
2.
А, В
10
3,000
9.000
4,000
5,000
2,000
3.000
5,000
9,000
7,000
12
6.
E, F
2
1
G
5.000
C, F
8
2,000
8.000
a. What would be your target completion week?
The target completion week is week (Enter your response as an integer.)
Chapter 6 Solutions
PROJECT MANAGEMENT (LOOSELEAF)-W/ACCESS
Ch. 6 - How does the WBS differ from the project network?Ch. 6 - How are WBS and project networks linked?Ch. 6 - Why bother creating a WBS? Why not go straight to...Ch. 6 - Why is slack important to the project manager?Ch. 6 - What is the difference between free slack and...Ch. 6 - Why are lags used in developing project networks?Ch. 6 - What is a hammock activity, and when is it used?Ch. 6 - Here is a partial work breakdown structure for a...Ch. 6 - Draw a project network from the following...Ch. 6 - Draw a project network from the following...
Ch. 6 - Draw a project network from the following...Ch. 6 - Draw a project network from the following...Ch. 6 - From the following information, develop an AON...Ch. 6 - The project information for the custom order...Ch. 6 - You have signed a contract to build a garage for...Ch. 6 - You are creating a customer database for the...Ch. 6 - K. Nelson, project manager of Print Software....Ch. 6 - A large Southeast city is requesting federal...Ch. 6 - You are creating a customer database for the...Ch. 6 - You are completing a group term paper. Given the...Ch. 6 - You are managing a product upgrade project for...Ch. 6 - You are creating a database for the Oklahoma City...Ch. 6 - The planning department of an electronics firm has...Ch. 6 - Using Microsoft Project, set up the network and...Ch. 6 - The optical disk project team has started...Ch. 6 - From the following information, compute the early,...Ch. 6 - Given the following information, compute the...Ch. 6 - Given the information in the following lag...Ch. 6 - Given the network below, compute the early, late,...Ch. 6 - The CyClon project team has started gathering...Ch. 6 - Advantage Energy Technology Data Center...Ch. 6 - Advantage Energy Technology Data Center...Ch. 6 - Advantage Energy Technology Data Center...Ch. 6 - The GE Company is preparing a bid to build the new...Ch. 6 - The GE Company is preparing a bid to build the new...Ch. 6 - The G&E Company is preparing a bid to build the...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.Similar questions
- Define project. Define the term project objective, and give some examples. List some examples of resources that are used on a project. Define scope, schedule, cost, and customer satisfaction. Why are these con-sidered to be constraints? List and describe the main phases of the project life cycle.arrow_forwardPrepare a draft project charter for the Global Treps project. Assume that the project will take six months to complete and have a budget of $120,000. Use the project charter template provided in this text and the sample project charter provided in Table 4-1 as guides.You will be the project manager, and Dr. K. will be the project sponsor. Other team members will include Bobby, Ashok, Kim, and Alfreda.You plan to hold four shark tank like events plus develop the Global Treps site and application.arrow_forwardThe name of the project is: Organizing a food drive to provide to a Family Support Network. Develop an analytical report of the above project with specific focus on the components and questions/statements listed below: (1) State the name of the project and give a brief description of the project. (2) Outline the problem(s) that the project was initiated to solve or the opportunity it exploited. (3) Describe the technique or method used to select the project. (4) Identify and describe at least five (5) characteristics that make this endeavour a project. (5) Identify the project developmental approach used for the project. Give reasons or justification for your conclusion(s). Hint: (Agile, Waterfall/Traditional, or Hybrid approach?) (6) Using your knowledge of the project life cycle and information gathered from the examination of the project documents, describe the phases of the project and the key activities/tasks associated with each phase of the project. (7) List and describe…arrow_forward
- Calculate early start, early finish, late start, late finish, and float for each of the activities in the project schedule network below. The duration of each activity is given. DENT" Use the table below to complete the problem: A early start early finish. late start late finish float ? B C D Earrow_forwardJake, a project manager for XYS Company, is developing the project plan for the implementation of a new technique to reduce the level of carbon dioxide emitted after a manufacturing process. Sara, a project manager for ABG Company, is developing a project plan to survey customers about how they have implemented a new product. Describe the similarities and differences of at least three project constraints that Jake and Sara may face during their projects.arrow_forwardUse the Program Evaluation and Review Technique to represent the project in an activity network. In conjunction with the Critical Path Method, use the activity network to find the shortest time possible to complete the project, to identify the critical jobs in the project, and to determine the earliest and latest that each activity can start and finish without making the project completion longer.a=1, b=1, c=6, d=5, e=2, f=5; andab=1x1=1, bc=1x6=6, cd=6x5=30, de=5x2=10, ef=2x5=10, af=1x5=5.arrow_forward
- Explain the concept of "project portfolio analysis" and its role in strategic project management. How does it help organizations prioritize and manage multiple projects?arrow_forwardSuppose you are the project manager for the following project: First, draw a network diagram for the project. Determine the critical path and slack times for all of the tasks. This completes your plan for the project schedule. During project execution, you become aware of the need to change the duration of Task 4 to five days. Meanwhile, Task 3 has been finished one day early, so it only took one day to do. What, if any, effects do these changes have on your project? What would have happened if you had not been monitoring the status of the project?arrow_forwardSwimming Pool Installation: You are the project manager working for Mack's Pool Co. Your project consists of installing a new swimming pool at the local country club before Memorial Day weekend (pool opening weekend). You would like to find the minimum cost schedule for your project. There is a $9,000 per week penalty for each week the project is delayed beyond week 9. In addition, your project team determined that indirect costs are $15,000 per week. ACTIVITY Immediate Predecessor (s) NORMAL TIME (NT) CRASH TIME (CT) Normal Cost (NC) Crash Cost (CC) A -- 2 1 7,000 10,000 B -- 2 2 3,000 3,000 C A 3 1 12,000 40,000 D B 3 2 12,000 28,000 E C 1 1 8,000 8,000 F D, E 5 3 5,000 15,000 G E 3 2 9,000 18,000 Before crashing, the project duration is _________ week(s). The total cost of the project if we do nothing is $ __________ (round to the nearest dollar). The minimum cost…arrow_forward
- When developing a schedule network diagram, the project manager must take into account the dependencies between activities as well as the start and finish relationships between activities. List and describe the four types of schedule activity relationships List and describe the four types of schedule activity dependencies Include examples of each item above, that do not come from the PMBOK.arrow_forwardYou may need to use the appropriate technology to answer this question. Use the following network with activities and times estimated in days to answer the questions. A project network with 13 activities and 17 directed arcs is shown. Activity Start is connected to activity A, to activity B, and to activity C. Activity A is connected to activity D, to activity E, and to activity F. Activity B is connected to activity F. Activity C is connected to activity G and to activity H. Activity D is connected to activity K. Activity E is connected to activity I. Activity F is connected to activity I. Activity G is connected to activity I. Activity H is connected to activity J. Activity I is connected to activity K. Activity J is connected to activity K. Activity K is connected to activity Finish. Activity Finish has no arcs directed to other activities. Activity Optimistic Most Probable Pessimistic A 2 5 6 B 1 3 7 C 5 6 9 D 5 12 14 E 3 4 5 F 9 10 13 G 4 6 8 H 3 6 8 I 5 7 12 J 11 12 13 K 1 3 4…arrow_forwardUsing the table above please indicate: The expected duration for the activities #1 & #5 (using PERT estimation) Which activities the project start with? Using duration of 3 for activity #9 and suppose that the total duration of the project is 50. What is the Latest Time to finish and to start for the direct preceding activities of activity #9?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Understanding BusinessManagementISBN:9781259929434Author:William NickelsPublisher:McGraw-Hill EducationManagement (14th Edition)ManagementISBN:9780134527604Author:Stephen P. Robbins, Mary A. CoulterPublisher:PEARSONSpreadsheet Modeling & Decision Analysis: A Pract...ManagementISBN:9781305947412Author:Cliff RagsdalePublisher:Cengage Learning
- Management Information Systems: Managing The Digi...ManagementISBN:9780135191798Author:Kenneth C. Laudon, Jane P. LaudonPublisher:PEARSONBusiness Essentials (12th Edition) (What's New in...ManagementISBN:9780134728391Author:Ronald J. Ebert, Ricky W. GriffinPublisher:PEARSONFundamentals of Management (10th Edition)ManagementISBN:9780134237473Author:Stephen P. Robbins, Mary A. Coulter, David A. De CenzoPublisher:PEARSON
Understanding Business
Management
ISBN:9781259929434
Author:William Nickels
Publisher:McGraw-Hill Education
Management (14th Edition)
Management
ISBN:9780134527604
Author:Stephen P. Robbins, Mary A. Coulter
Publisher:PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract...
Management
ISBN:9781305947412
Author:Cliff Ragsdale
Publisher:Cengage Learning
Management Information Systems: Managing The Digi...
Management
ISBN:9780135191798
Author:Kenneth C. Laudon, Jane P. Laudon
Publisher:PEARSON
Business Essentials (12th Edition) (What's New in...
Management
ISBN:9780134728391
Author:Ronald J. Ebert, Ricky W. Griffin
Publisher:PEARSON
Fundamentals of Management (10th Edition)
Management
ISBN:9780134237473
Author:Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:PEARSON
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY