Advantage Energy Technology Data Center Migration—Part A
Brian Smith, network administrator at Advanced Energy Technology (AET), has been given the responsibility of implementing the migration of a large data center to a new office location. Careful planning is needed because AET operates in the highly competitive petroleum industry. AET is one of five national software companies that provide an accounting and business management package for oil jobbers and gasoline distributors. A few years ago, AET jumped into the “application service provider’ world. Their large data center provides clients with remote access to AET’s complete suite of application software systems. Traditionally, one of AET’s primary competitive advantages has been the company’s trademark IT reliability Due to the complexity of this project. Brian will have to use a parallel method of implementation. Although this will increase project costs, a parallel approach is essential if reliability is not to be compromised.
Currently, AET’s data center is located on the second floor of a renovated old bank building in downtown Corvallis, Oregon. The company is moving to a new, one-level building located in the recently developed industrial complex at the Corvallis International Airport. On February 1, Brian is formally assigned the task by the Vice President of Operations, Dan Whitmore, with the following guidelines:
• From start to finish, it is anticipated the entire project will take three to four months to complete.
• It is essential that AET’s 235 clients suffer no downtime.
Whitmore advises Brian to come back to the Executive Committee on February 15, with a presentation on the scope of the project that includes costs, “first-cut” timeline, and proposed project team members.
Brian had some preliminary discussions with some of AET’s managers and directors from each of the functional departments and then arranged for a full-day scope meeting on February 4 with a few of the managers and technical representatives from operations, systems, facilities, and applications. The scope team determined the following;
Three to four months is a feasible project timeline and first-cut cost estimate is $80,000—$90,000 (this includes the infrastructure upgrade of the new site).
• Critical to the ‘no-downtime” requirement is the need to completely rely on AET’s remote disaster recovery ‘hot” site for full functionality.
• Brian will serve as project manager of a team consisting of one team member each from facilities, operations/systems, operations/telecommunications, systems & applications, and customer service.
Brian’s Executive Committee report was positively received and. after a few modifications and recommendations, he was formally charged with responsibility for the project Brian recruited his team and scheduled their first team meeting (March 1) as the initial task of his project planning process.
Once the initial meeting is conducted Brian can hire the contractors to renovate the new data center. During this time Brian will figure out how to design the network Brian estimates that screening and hiring a contractor will take about one week and that the network design will take about two weeks. The new center requires a new ventilation system. The manufacturer’s requirements include an ambient temperature of 67 degrees to keep all of the data servers running at optimal speeds. The ventilation system has a lead time of three weeks. Brian will also need to order new racks to hold the servers, switches, and other network devices. The racks have a two- week delivery time.
The data center supervisor requested that Brian replace all of the old power supplies and data cables. Brian will need to order these as well. Because Brian has a great relationship with the vendor, they guarantee that it will take only one week lead time for the power supplies and the data cables. Once the new ventilation system and racks arrive, Brian can begin installing them. It will take one week to install the ventilation system and three weeks to install the racks. The renovation of the new data center can begin as soon as the contractors have been hired. The contractors tell Brian that construction will take 20 days. Once the construction begins and after Brian installs the ventilation system and racks, the city inspector must approve the construction of the raised floor.
The city inspector will take two days to approve the infrastructure. After the city inspection and after the new power supplies and cables have arrived, Brian can install the power supplies and run the cables. Brian estimates that it will take five days to install the power supplies and one week to run all of the data cables. Before Brian can assign an actual date for taking the network off line and switching to the hot remote site, he must get approval from each of the functional units (“Switchover Approval”). Meetings with each of the functional units will require one week During this tune he can initiate a power check to ensure that each of the racks has sufficient voltage. This will require only one day.
Upon completion of the power check, he can take one week to install his test servers. The test servers will test all of the primary network functions and act as a safeguard before the network is taken off line. The batteries must be charged, ventilation installed, and test servers up and running before management can be assured that the new infrastructure is safe, which will take two days. Then they will sign off the Primary Systems check, taking one day of intense meetings. They will also set an official date for the network move.
Brian is happy that everything has gone well thus far and is convinced that the move will go just as smoothly. Now that an official date is set, the network will be shut down for a day. Brian must move all of the network components to the new data center. Brian will do the move over the weekend—two days—when user traffic is at low point.
2. Develop a WBS for Brian’s project. Include duration (days) and predecessors.
Want to see the full answer?
Check out a sample textbook solutionChapter 6 Solutions
PROJECT MANAGEMENT (LOOSELEAF)-W/ACCESS
- What are several strategies to initiate as described in the Leadership Recommendation Project (LRP)?arrow_forwardConsider the case of Nutrorim that you read in Module 1 from a culture, structure, and strategy perspective. Answer the following questions. Be sure to support your reasoning with evidence from the case and course concepts.arrow_forwardWhat are the stages of team development and their information?arrow_forward
- Please original work Name of fiction technology company: TESC technology Corp Background information: You are the chairman of the board for a large technology company. You are seeking a new CEO to replace your recently departed company founder. You are seeking an innovative leader for your organization. What do you think are the most important characteristics for the leader to have? Explain why each is important. How will you determine if an individual has those characteristics? Discuss how executives can ensure a successful fit. Please cite in text references and add weblinksarrow_forwardPlease original work Background information: Building a Knowledge Based Culture To operate efficiently in today’s technology driven environment, business leaders have realized the importance of building knowledge-based cultures and practices into the very fiber of their organizations. How do you design a knowledge-based culture using the training and development processes? What type of innovation is this in a successful high-tech firm? In a stable firm with little external change? Explain. Please cite in text references and add weblinkarrow_forwardConsider the case of Nutrorim that you read in Module 1 from a culture, structure, and strategy perspective. Answer the following questions. Be sure to support your reasoning with evidence from the case and course concepts. What impact has the democratic culture had on the company’s ability to make good, effective, decisions? How do you think this culture evolved?arrow_forward
- Please original work CEO of a Consulting Management firm Background information: You are in charge of creating a balanced scorecard and the strategy map for an organization of your choice. discuss how you would approach the CEO of your current or a previous organization in order to gather executive input on creating a strategy map. Provide five key questions would you ask and provide the reason for asking each. What concerns would you have about this executive interview? Why? Please cite in text references and add weblinksarrow_forwardWhat is the net operating income for yeararrow_forwardthe importance of aligning the scope delivery with the scope definition and maintaining a formal change control process. Clearly documenting and evaluating the impact of every potential change helps ensure that any updates remain realistic and properly authorized. In your experience, what strategies or tools have you found most helpful for communicating these changes to the broader team so that everyone stays informed and on the same page?arrow_forward
- What is a good survey design on leadership in management that gather primary data that reveals the Values, Assumptions, Beliefs, and Expectations (VABEs) that relies on the key ten (10) questions that begin "the purpose of thequestion is ?"arrow_forwardDocument for Analysis Please read the following poorly-written email, then create an outline for a more effective email, and post it to this Discussion. Here are some questions to ask yourself while you create an outline: What is the real purpose of this message? Could you make it more "direct"? Which words and phrases are overly complicated, clichéd, too informal, or overly formal? Could you replace them with more simple, familiar words or phrases? Which sentences or words are overly negative? Could they be positively phrased? Are there "I/we" (writer-focused) sentences that could use a "you" (audience-focused) attitude? This email is to Inglesina, an Italian maker of very high-quality and stylish home accessories and decor items. Fabulous Home Accents is writing to Inglesina because they want to sell Inglesina products on their website. However, Inglesina is very selective about who sells their product. Here's the email; it needs work! "Our e-tailing company, Fabulous Home Accents,…arrow_forwardOnce you know your decision-making style, read the case and answer the following questions. Be sure to use case examples and your understanding of Rowe's Decision Making Styles to support your arguments.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning