Chapter 5, Problem 5P
Summary Introduction
To explain: Determine the arrival rate of the assembly line, for operators to be busy 90% of the time, given that the operator can process 10 items per hour.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The time from when a patient is discharged from North Shore Hospital to the time the discharged patient’s bed is ready to be assigned to a new patient is referred to as the bed assignment turnaround time. If the bed turnaround time is excessive, it can cause problems with patient flow and delay medical procedures throughout the hospital. This can cause long waiting times for physicians and patients thus creating customer dissatisfaction. The admissions RN has assigned a patient care associate to measure the bed turnaround time for a randomly selected bed each morning., afternoon, and evening for 30 days. Following are the bed turnaround time sample observations:
Day
Day
Bed Turnaround Times (min)
1
1
127
135
167
144
151
2
2
140
155
122
135
119
3
3
112
128
97
118
131
4
4
223
135
154
187
150
5
5
181
155
160
172
166
6
6
103
158
145
124
149
7
7
146
135
167
150
178
8
8
104
122
115
137
129
9
9
136
158
137
148
156
10
10
145
163
106
139
170
11
11
84
146
125
98…
12-15 The wheat harvesting season in the American Midwest is short, and most farmers deliver their truckloads of wheat to a giant central storage bin within a two-week span. Because of this, wheat-filled trucks waiting to unload and return to the fields have been known to back up for a block at the receiving bin. The central bin is owned cooperatively, and it is to every farmer’s benefit to make the unloading/storage process as efficient as possible. The cost of grain deterioration caused by unloading delays, the cost of truck rental, and idle driver time are significant concerns to the cooperative members. Although farmers have difficulty quantifying crop damage, it is easy to assign a waiting and unloading cost for truck and driver of $18 per hour. The storage bin is open and operated 16 hours per day, 7 days per week, during the harvest season and is capable of unloading 35 trucks per hour according to an exponential distribution.
Full trucks arrive all day long (during the hours…
The check-out area of a grocery store has the average customer interarrival time = 2 minutes, the average processing time of each cashier = 6 minutes, and in total 4 cashiers. The average waiting time for each customer is 8 minutes. What is the average number of customers in the system (including waiting and using the service)?
a
3
b
7
c
6
d
4
Chapter 5 Solutions
Operations and Supply Chain Management, 9th Edition WileyPLUS Registration Card + Loose-leaf Print Companion
Ch. 5 - Uber and the Sharing Economy First there was...Ch. 5 - Uber and the Sharing Economy First there was...Ch. 5 - Uber and the Sharing Economy First there was...Ch. 5 - Prob. 2.1ASCCh. 5 - Prob. 2.2ASCCh. 5 - Prob. 2.3ASCCh. 5 - Prob. 3.1ASCCh. 5 - Prob. 3.2ASCCh. 5 - Prob. 1QCh. 5 - Prob. 2Q
Ch. 5 - Prob. 3QCh. 5 - Prob. 4QCh. 5 - Prob. 5QCh. 5 - Prob. 6QCh. 5 - Prob. 7QCh. 5 - Prob. 8QCh. 5 - Prob. 9QCh. 5 - Prob. 11QCh. 5 - Prob. 12QCh. 5 - Prob. 13QCh. 5 - Prob. 14QCh. 5 - Prob. 15QCh. 5 - Prob. 16QCh. 5 - Prob. 17QCh. 5 - Prob. 19QCh. 5 - Prob. 20QCh. 5 - Under what conditions will the single-channel,...Ch. 5 - Prob. 22QCh. 5 - Prob. 1PCh. 5 - Prob. 2PCh. 5 - Prob. 3PCh. 5 - Prob. 4PCh. 5 - Prob. 5PCh. 5 - Prob. 6PCh. 5 - Prob. 7PCh. 5 - Prob. 8PCh. 5 - Prob. 9PCh. 5 - Prob. 10PCh. 5 - Prob. 11PCh. 5 - Annie Campbell is a nurse on the evening shift...Ch. 5 - Prob. 13PCh. 5 - Prob. 14PCh. 5 - Prob. 15PCh. 5 - Prob. 16PCh. 5 - Prob. 17PCh. 5 - Prob. 18PCh. 5 - Prob. 19PCh. 5 - Prob. 20PCh. 5 - Prob. 21PCh. 5 - Prob. 22PCh. 5 - Drivers who come to get their licenses at the...Ch. 5 - Prob. 24PCh. 5 - Prob. 25PCh. 5 - Prob. 26PCh. 5 - The Waterfall Buffet in the lower level of the...Ch. 5 - Prob. 28PCh. 5 - Prob. 29PCh. 5 - Prob. 30PCh. 5 - Prob. 31PCh. 5 - The Baytown Post Office has four stations for...Ch. 5 - Prob. 33PCh. 5 - Prob. 34PCh. 5 - Prob. 35PCh. 5 - Prob. 36PCh. 5 - Prob. 37PCh. 5 - Prob. 38PCh. 5 - Prob. 39PCh. 5 - Prob. 40PCh. 5 - Prob. 41PCh. 5 - Prob. 42PCh. 5 - Prob. 43PCh. 5 - Prob. 44PCh. 5 - Prob. 45PCh. 5 - Prob. 46PCh. 5 - Prob. 47PCh. 5 - After reviewing your report above, Tech has...Ch. 5 - Prob. 49PCh. 5 - Prob. 50PCh. 5 - Prob. 1.1CPCh. 5 - Prob. 1.2CPCh. 5 - Prob. 2.1CPCh. 5 - Prob. 2.2CPCh. 5 - Prob. 3.1CPCh. 5 - Prob. 4.1CP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A manufacturing company has a small production line dedicated to the production of a particular product. The line has four stations in serial. Inputs arrive at station 1 and the output from station 1 becomes the input to station 2. The output from station 2 is the input to station 3 and so on. The output from station 4 is the finished product. Station 1 can process 2,700 units per month, station 2 can process 2,500/month, station 3 can process 2,300/month, and station 4 can process 2,100/month. What station sets the maximum possible output from this system? What is that maximum output number?arrow_forwardGiven information: A typical TSA agent at Piedmont Triad International Airport takes approximately 1.15 minutes to screen each passenger that arrives at the security gate. During the day, a passenger arrives at the gate on average every 1.3 minutes. Both the service rate and arrival rate follow a Poisson distribution. Based on this information and the assumption that only one screening line is open at the security gate, answers the following questions. Round calculations to at least 3 decimal places. Note: Round each calculation to at least 3 decimal places. Arrival time =60/1.3=46.153 Server Rate =60/1.15=52.174 L=expected number of passengers in queue =6.780 waiting time in queue =.1469 time spent screening=.1660 please answer the 2 foloowing questions What is percent of the time does the typical TSA agent spend actively screening passengers? Throughout the day, passenger arrival rates vary with the greatest number of passengers arriving about 45 minutes before a flight is…arrow_forwardA bike repair plant is trying to determine how long the average line for a repair process will be. If 13 bikes arrive each hour and must wait 5 minutes in the line, how long will the line be, on average?arrow_forward
- Please build and simulate the following model in ARENA.In this model, car loan applications arrive at processing center approximately every 5 minutes. At this point, 1 of 5 loan officers will review the application to ensure that it is complete. This review step usually takes 15 minutes, but can be as short as 12 minutes or as long as 18 minutes. Applications are sent to an automatic processing machine where they are processed. This process can take from 0.5 to 1.5 hours to complete, but usually requires 1 hour. It is assumed that the automatic processor can process as many applications as needed.After processing, the results are reviewed by a loan officer who will write either an acceptance or rejection document. This task usually takes 7 minutes, but can require anywhere from 5 to 10 minutes to complete.At this point the loan application process is complete, and the acceptance or rejection document is sent to the customer.Run this simulation for one 8-hour day (5 replications).arrow_forwardIf the restaurant runs a sale and the customer arrival rate increases by 20 percent how would this change the total time expected to serve a customer? How would this change the average number of cars in the drive-thru line?arrow_forwardThe time from when a patient is discharged from NorthShore Hospital to the time the discharged patient’s bed isready to be assigned to a new patient is referred to as thebed assignment turnaround time. If the bed turnaroundtime is excessive, it can cause problems with patient flowand delay medical procedures throughout the hospital. Thiscan cause long waiting times for physicians and patientsthus creating customer dissatisfaction. The admissions RNhas assigned a patient care associate to measure the bedturnaround time for a randomly selected bed each morning,afternoon, and evening for 30 days. Following are the bedturnaround time sample observations:a. Develop an x-chart to be used in conjunction with anR-chart using 3 limits to monitor the bed turnaroundtimes and indicate if the process is in control usingthese charts.b. Is the hospital capable of consistently achieving bedturnaround times of 120 minutes 15 minutes withoutimproving the process?arrow_forward
- The Universal Manufacturing Company produces a par-ticular product in an assembly-line operation. One of the machines on the line is a drill press that has a single as-sembly line feeding into it. A partially completed unit ar-rives at the press to be worked on every 8 minutes, on average, according to an exponential distribution. Themachine operator can process an average of 10 parts perhour (Poisson distributed). Determine the average numberof parts waiting to be worked on, the percentage of timethe operator is working, and the percentage of time themachine is idle.arrow_forwardIn the welding operations of a bicycle manufacturer, a bike frame has a flow time of about 16.65 hours. The time in the welding operation is spent as follows: 3 hours waiting in front of the cutting machine for the batch to start, 3 hours waiting for the setup of the machine, 1 hour waiting for the other pieces of the batch to go through cutting, 1 minute at the cutting machine, and 3 hours waiting for the transfer to the welding machine. Then, at the welding machine, the unit spends 2 hour waiting in front of the welding machine for the batch to start, 2 hour waiting for the setup of the welding machine, 0.65 hour waiting for the other pieces of the batch to go through welding, 0.4 minute at the welding machine, and 2 hour waiting for the transfer to the next department. (Round your percentage answer to 4 decimal places.) Determine the exact flow time. What is the value-added percentage of the flow time? percent cetion MacBook Air ww.arrow_forwardFlow and waiting time through a process are affected by seasonal fluctuation in demand. What does this mean? If a corporation wants to limit the impact of this fluctuation, what steps can it take?arrow_forward
- Hilltop Restaurant is located in Dempsey Hill. The restaurant has a capacity of 35 tables to serve customers. When doing its capacity planning and evaluating operational performance, the restaurant adopts the concept of “customer group” and uses it as unit of measurement to measure the workload in the service process. A customer group is a group of one or more people who arrive, get seated at a table, eat and depart. On average, a customer group takes 70 minutes to eat dinner, and then another 25 minutes to eat dessert. On average, a customer group generates a profit of $100 on dinner, and $30 on dessert. (a) Assume that all customer groups eat both dinner and dessert. Estimate the maximum number of customer groups per hour the restaurant can serve (capacity rate) by applying Little’s Law. At what rate (dollars per hour) is profit generated by the restaurant if it operates at capacity rate?arrow_forwardHilltop Restaurant is located in Dempsey Hill. The restaurant has a capacity of 35 tables to serve customers. When doing its capacity planning and evaluating operational performance, the restaurant adopts the concept of “customer group” and uses it as unit of measurement to measure the workload in the service process. A customer group is a group of one or more people who arrive, get seated at a table, eat and depart. On average, a customer group takes 70 minutes to eat dinner, and then another 25 minutes to eat dessert. On average, a customer group generates a profit of $100 on dinner, and $30 on dessert. Now assume that Hilltop leases new space to open a “dessert bar” next door, and has opened up the wall between the two units to allow inside access from the restaurant to the dessert bar. The dessert bar can accommodate 15 tables. With this change, a customer group arrives and is seated at a table in Hilltop restaurant as usual. However, when the customer group finishes eating dinner,…arrow_forwardEat Well is a tiny drive-through quick food restaurant in a shopping malltown, manned by an efficient employee named John. Customers arrive at the counter at a rate of one per 15 minutes on average, with a Poisson delivery for customer entry. Each food order takes John no more than ten minutes to process. a) How many customers are handled on average at any given time? b) The anticipated amount of clients that would be represented. c) Determine the average consumer wait time in the scheme. d) How much of the day is John Idle idle?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,