Concept explainers
(a)
To find: the learning curve for this employee.
(a)
Answer to Problem 36E
The learning curve of the employee is
Explanation of Solution
Given information:
The management at a plastics factory has found that the maximum number of units a worker can produce in a day is 30. The learning curve for the number
Calculation:
After 20 days on the job, a new employee produces 19 units.
Therefore substitute
Hence, the learning curve of the employee is
(b)
To find: how many days does the model predict will pass before this employee is producing 25 units per day.
(b)
Answer to Problem 36E
36 days should pass before this employee is producing 25 units per day.
Explanation of Solution
Given information:
Calculation:
Now employee produces 25 units per day.
Therefore substitute
Hence, 36 days should pass before this employee is producing 25 units per day.
Chapter 3 Solutions
EBK PRECALCULUS W/LIMITS
- Calculus: Early TranscendentalsCalculusISBN:9781285741550Author:James StewartPublisher:Cengage LearningThomas' Calculus (14th Edition)CalculusISBN:9780134438986Author:Joel R. Hass, Christopher E. Heil, Maurice D. WeirPublisher:PEARSONCalculus: Early Transcendentals (3rd Edition)CalculusISBN:9780134763644Author:William L. Briggs, Lyle Cochran, Bernard Gillett, Eric SchulzPublisher:PEARSON
- Calculus: Early TranscendentalsCalculusISBN:9781319050740Author:Jon Rogawski, Colin Adams, Robert FranzosaPublisher:W. H. FreemanCalculus: Early Transcendental FunctionsCalculusISBN:9781337552516Author:Ron Larson, Bruce H. EdwardsPublisher:Cengage Learning