Chapter 14, Problem 2P
a)
Summary Introduction
To determine: The quarterly operation plan production for the company B to chase demand using
Introduction: Quarterly operation planning is subjective to annual sales and operation planning. The purpose of this plan is to achieve short term goal that helps to drive company’s long term strategy. The period of quarterly operation planning is 90 days.
b)
Summary Introduction
To determine: The quarterly operation plan production for the company C to set mixed strategy using forecasted demand.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 4 clamps. The base is assembled from 1 clamp and\ 1 housing. Each clamp has 1 handle and 2 castings.Each housing has 1 bearing and 2 shafts.There is no inventory on hand.
C) Compute the net quantities needed if there are 25 of the base and 75 of the clamp in stock.
(Product structure picture attached)
Base = (?) units
Spring = (?) units
Clamp = (?) units
Housing = (?) units
Handle = (?) units
Casting = (?) units
Bearing = (?) units
Shaft = (?) units
In the context of an Accident and Emergency Department, high demand variation can be addressed by having:
Select one alternative:
Yield Management.
Over staffing and preferential access.
Marketing.
Standby capacity and flexible staffing.
Demand management.
As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 4 clamps. The base is assembled from 2 clamps and 1 housing. Each clamp has 1handle and 1 casting. Each housing has 2 bearings and 2 shafts. There is no inventory on hand.
c) Compute the net quantities needed if there are 25 of the base and 100 of the clamp in stock.
Base:
units (enter your response as a whole number).
Spring:
units
Clamp:
units
Housing:
units
Handle
units
Casting:
units
Bearing:
units
Shaft:
units
Chapter 14 Solutions
Operations and Supply Chain Management, 9th Edition WileyPLUS Registration Card + Loose-leaf Print Companion
Ch. 14.S - Prob. 1QCh. 14.S - Prob. 2QCh. 14.S - Prob. 3QCh. 14.S - Prob. 4QCh. 14.S - Prob. 5QCh. 14.S - Prob. 6QCh. 14.S - Prob. 7QCh. 14.S - Prob. 8QCh. 14.S - Prob. 1PCh. 14.S - The Tycron Company produces three electrical...
Ch. 14.S - Prob. 3PCh. 14.S - The Pinewood Cabinet and Furniture Company...Ch. 14.S - The Mystic Coffee Shop blends coffee on the...Ch. 14.S - Prob. 6PCh. 14.S - Prob. 7PCh. 14.S - Prob. 8PCh. 14.S - Prob. 9PCh. 14.S - Prob. 10PCh. 14.S - Prob. 11PCh. 14.S - Prob. 12PCh. 14.S - Prob. 13PCh. 14.S - Prob. 14PCh. 14.S - Prob. 15PCh. 14.S - Prob. 16PCh. 14.S - Prob. 17PCh. 14.S - Prob. 18PCh. 14.S - Prob. 19PCh. 14.S - Prob. 20PCh. 14.S - Prob. 22PCh. 14.S - Prob. 23PCh. 14.S - Prob. 24PCh. 14.S - Prob. 25PCh. 14.S - Prob. 27PCh. 14.S - Prob. 28PCh. 14.S - Prob. 1.1CPCh. 14.S - Prob. 1.2CPCh. 14.S - Prob. 1.3CPCh. 14.S - Prob. 1.4CPCh. 14.S - Prob. 1.5CPCh. 14.S - Prob. 1.6CPCh. 14.S - Prob. 1.7CPCh. 14.S - Prob. 1.8CPCh. 14.S - Prob. 1.9CPCh. 14.S - Prob. 2.1CPCh. 14 - Prob. 1.1ASCCh. 14 - Prob. 1.2ASCCh. 14 - Supply and Demand in the Spirits Industry A...Ch. 14 - Supply and Demand in the Spirits Industry A...Ch. 14 - Supply and Demand in the Spirits Industry A...Ch. 14 - Disneys Magic Numbers Sales and operations...Ch. 14 - Disneys Magic Numbers Sales and operations...Ch. 14 - Prob. 1QCh. 14 - List several alternatives for adjusting capacity....Ch. 14 - Prob. 3QCh. 14 - How do linear programming, the linear decision...Ch. 14 - Prob. 5QCh. 14 - What options are available for altering the...Ch. 14 - Prob. 7QCh. 14 - Prob. 8QCh. 14 - Explain the process of collaborative planning. How...Ch. 14 - Prob. 11QCh. 14 - Prob. 12QCh. 14 - Prob. 1PCh. 14 - Prob. 2PCh. 14 - Prob. 3PCh. 14 - Prob. 4PCh. 14 - Mamas Stuffin is a popular food item during the...Ch. 14 - Prob. 6PCh. 14 - Slopes Sleds (SS) makes skis, snowboards, and...Ch. 14 - Prob. 8PCh. 14 - Midlife Shoes, Inc, is a manufacturer of sensible...Ch. 14 - Design a production plan for Mamas Stuffin in...Ch. 14 - Design a production plan for FansForYou in Problem...Ch. 14 - Prob. 16PCh. 14 - Prob. 17PCh. 14 - Prob. 18PCh. 14 - Prob. 19PCh. 14 - Prob. 20PCh. 14 - Prob. 21PCh. 14 - Prob. 22PCh. 14 - How many units are available-to-promise in period...Ch. 14 - Complete the available-to-promise table below.Ch. 14 - Complete the available-to-promise table below.Ch. 14 - Calculate the available-to-promise row in the...Ch. 14 - Complete the following table. How many Bs are...Ch. 14 - Managers at the Dew Drop Inn are concerned about...Ch. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Prob. 31PCh. 14 - Prob. 32PCh. 14 - The Forestry Club sells Christmas trees each year...Ch. 14 - Prob. 34PCh. 14 - Tariott Hotel rents rooms for 125 a night that...Ch. 14 - Prob. 36PCh. 14 - Prob. 1.1CPCh. 14 - Prob. 1.2CPCh. 14 - Prob. 1.3CP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Sniparrow_forwardDevelop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 11,000; winter, 8,000; spring, 6,000; summer, 13,000. Inventory at the beginning of fall is 500 units. At the beginning of fall you currently have 30 workers, but you plan to hire temporary workers at the beginning of summer and lay them off at the end of summer. In addition, you have negotiated with the union an option to use the regular workforce on overtime during winter or spring if overtime is necessary to prevent stockouts at the end of those quarters. Overtime is not available during the fall. Relevant costs are hiring, $100 for each temp; layoff $200 for each worker laid off; inventory holding, $5 per unit-quarter; backorder, $10 per unit; straight time, $5 per hour; overtime, $8 per hour. Assume that the productivity is 0.5 unit per worker hour, with eight hours per day and 60 days per season. a. What is the total cost for this plan?arrow_forwardDevelop a production schedule to produce the exact production requirements by varying the workforce size for the following problem. Use the example in the chapter as a guide (Plan 1).The monthly forecasts for Product X for January, February, and March are 1,000, 1,500, and 1,200, respectively. Safety stock policy recommends that half of the forecast for that month be defined as safety stock. There are 22 working days on January, 19 in February, and 21 in March. The beginning inventory is 500 units.Manufacturing cost is $200 per unit, storage cost is $3 per unit per month, standard pay rate is $6 per hour, overtime rate is $9 per hour, cost of stock out is $10 per unit per month, marginal cost of subcontracting is $10 per unit, hiring and training cost is $200 per worker, layoff cost is $300 per worker, and worker productivity is 0.1 unit per hour. Assume that you start off with 50 workers and that they work 8 hours per day.arrow_forward
- A newly opened BackPack Company in Kitwe, produces a line of backpacks. The manager, Jill Bwalya, is interested in using a level aggregate plan. Inventories and back orders will be used to handle demand fluctuations. Given the following data below; Cost dataRegular-time labour cost per hour K10.00Overtime labour cost per hour K15.00Subcontracting cost per unit (labour only) K84.00Holding cost per unit per period K10.00Back-order cost per unit per period K20.00Hiring cost per employee K600.00Firing cost per employee K450.00Capacity dataBeginning workforce 210 employeesBeginning inventory 400 unitsLabour standard per unit 6 hoursRegular time available per period 160 hours Overtime available per period…arrow_forwardAs a new account assistant, Miss Fizah has been assigned to calculate the amount that should appear on Terrar Bhd’s financial statement for inventory under the lower-of-cost-or-NRV (LCRNV) rule as applied to each item in inventory. The company applies the loss method and uses an Allowance Account to record for the write down of the inventory to net realisable value (NRV). However, Madam Rabiatul, Terrar Bhd’s accountant had an argument with Mr. Zaman, senior accountant of the company regarding the method to be used to record the write down of the inventories. Madam Rabiatul wants to use the loss method to write down inventory because it is more clearly discloses the decline in the net realisable value and does not distort the cost of goods sold. But, Mr. Zaman prefers the cost-of-goods-sold method to write down because it does not call attention to the decline in net realizable value. With regards to the argument between Madam Rabiatul and Mr. Zaman: (a) What is the issue facing Madam…arrow_forwardSmart Manufacturing Company (SMC) manufactures a variety of products other than the drum components for printers. Their high selling mobile juicer cup JG-142 has the following expected demand sales figures (in units) over the coming six months: Month 2 3 4 5 Expected Demand (units) 17680 23040 21120 16640 21760 The following planning parameters apply: Current number of workers Output rate per worker Number of regular time hours Number of working days Regular time labour cost Overtime labour cost Planning Parameters 26 4 units/hour 8 hours/day 20 days/month Maximum overtime hours allowed Hiring cost (including training) Layoff cost Inventory carrying cost Backorder cost Opening inventory Planned ending inventory (end of month 6) Material Cost Subcontracting Cost with material Maximum subcontracting allowed $14.00 /hour $21.00 /hour 6 18300 20% of regular worker-hours/month $950 /worker $1780 /worker $1.75 /unit/month Total 118540 $7.00/unit backordered 400 units 900 units $15 /unit $35…arrow_forward
- Please Help. At the bottom it also asks for total cost if you can find that as well. thanksarrow_forwardDemand for stereo headphones and music players for joggers has caused Nina Industries to grow almost 50 percent over the past year. The number of joggers continues to expand, so Nina expects demand for headsets to also expand, because, as yet, no safety laws have been passed to prevent joggers from wearing them. Demand for the players for this year was as follows: MONTH DEMAND (UNITS) January 4,150 February 4,250 March 3,950 April 4,350 May 4,950 June 4,650 July 5,250 August 4,850 September 5,350 October 5,650 November 6,250 December 5,950 a. Using linear regression analysis, what would you estimate demand to be for each month next year? Using a spreadsheet, follow the general format in Exhibit 3.8. (Do not round intermediate calculations. Round your answers to 2 decimal places.) b. To be reasonably confident of meeting demand, Nina decides to use 3 standard errors of estimate for safety. How many additional units should be held to meet this…arrow_forwardThe forecasted demand for fudge for the next four months is 110, 140, 230, and 160 pounds. What is the recommended production rate if a level strategy is adopted with no backorders or stockouts? What is the ending inventory for month 4 under this plan? Round your answers to the nearest whole number. Production rate: pounds/month Ending inventory (month 4): pounds What is the level production rate with no ending inventory in month 4? Round your answer to one decimal place. Production rate: pounds/montharrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.