Question
Chapter 14, Problem 34P
Summary Introduction
To determine: The number of pizzas that should be made for each game.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The Silver Star Bicycle Company will be manufacturing both men's and women's models of its Easy-Pedal 10-speed bicycles during the next two months.
Management wants to develop a production schedule indicating how many bicycles of each model should be produced in each month. Current demand
forecasts call for 150 men's and 125 women's models to be shipped during the first month and 200 men's and 150 women's models to be shipped during the
second month. Additional data are shown:
Production
Labor Requirements (hours)
Current
Model
Costs
Manufacturing
Assembly
Inventory
Men's
$120
2.0
1.5
20
Women's
$90
1.6
1.0
30
Last month the company used a total of 1000 hours of labor. The company's labor relations policy will not allow the combined total hours of labor
(manufacturing plus assembly) to increase or decrease by more than 100 hours from month to month. In addition, the company charges monthly inventory at
the rate of 2% of the production cost based on the inventory levels at the end of…
You are responsible of developing the six-month aggregate production plan at Sodas Galore, a
manufacturer of soft drinks. Your company makes three types of sodas: regular, diet and
super-caffeinated. All three types are made using the same production process, and the
switching costs can be ignored as they are so minimal. The S&OP team case created the
following forecast of demand for the next six months. In addition to the sales forecast, the
company has also developed planning values that are also shown in the next table.
Month
Sales Forecast (cases)
Softdrinks Planning Values
January
24,000
Current workforce
8 workers
32,000 Average monthly output per worker
32,000 Inventory holding cost
46,000 Regular wage rate
February
4,000 cases per month
$.30 per case per month
$20.00 per hour
March
April
May
60,000 Regular production hours/month
44,000 Overtime wage rate
160 hours
June
$30.00 per hour
240,000 Hiring cost
$1,000 per worker
$1.15 per case
Total
Subcontracting cost
Firing/layoff…
Mr. Zulhakim being assigned by his manager to develop their production planning for Year
2022. Table 3 shows the information that he able to obtain from the sales & marketing
department. After doing the planning, Mr Zulhakim need to present it to his manager. Factory
developed a demand forecast based on Table 3 with supplier charges about RM300.00 per unit.
The demand forecast is stated as week but, in this planning, it is being considered as an annual
quantity for the operation. Ordering cost is RM150.00. Annual holding cost is 10 percent of a
purchased price.
(b)
Develop the ATP of this plan. Initial inventory on hand is 50 units obtained from Year
2021. Lot size for MPS can be obtained by using EOQ model.
Table 3: Demand and Customer confirmed order quantity
8 9 10
2 3
10 40 10 00 30 20 40 20
30
Period (Week)
1
4
5 6
7
Forecast (units)
Customer orders (booked) (unit)
20
8.
2
Chapter 14 Solutions
Operations and Supply Chain Management, 9th Edition WileyPLUS Registration Card + Loose-leaf Print Companion
Ch. 14.S - Prob. 1QCh. 14.S - Prob. 2QCh. 14.S - Prob. 3QCh. 14.S - Prob. 4QCh. 14.S - Prob. 5QCh. 14.S - Prob. 6QCh. 14.S - Prob. 7QCh. 14.S - Prob. 8QCh. 14.S - Prob. 1PCh. 14.S - The Tycron Company produces three electrical...
Ch. 14.S - Prob. 3PCh. 14.S - The Pinewood Cabinet and Furniture Company...Ch. 14.S - The Mystic Coffee Shop blends coffee on the...Ch. 14.S - Prob. 6PCh. 14.S - Prob. 7PCh. 14.S - Prob. 8PCh. 14.S - Prob. 9PCh. 14.S - Prob. 10PCh. 14.S - Prob. 11PCh. 14.S - Prob. 12PCh. 14.S - Prob. 13PCh. 14.S - Prob. 14PCh. 14.S - Prob. 15PCh. 14.S - Prob. 16PCh. 14.S - Prob. 17PCh. 14.S - Prob. 18PCh. 14.S - Prob. 19PCh. 14.S - Prob. 20PCh. 14.S - Prob. 22PCh. 14.S - Prob. 23PCh. 14.S - Prob. 24PCh. 14.S - Prob. 25PCh. 14.S - Prob. 27PCh. 14.S - Prob. 28PCh. 14.S - Prob. 1.1CPCh. 14.S - Prob. 1.2CPCh. 14.S - Prob. 1.3CPCh. 14.S - Prob. 1.4CPCh. 14.S - Prob. 1.5CPCh. 14.S - Prob. 1.6CPCh. 14.S - Prob. 1.7CPCh. 14.S - Prob. 1.8CPCh. 14.S - Prob. 1.9CPCh. 14.S - Prob. 2.1CPCh. 14 - Prob. 1.1ASCCh. 14 - Prob. 1.2ASCCh. 14 - Supply and Demand in the Spirits Industry A...Ch. 14 - Supply and Demand in the Spirits Industry A...Ch. 14 - Supply and Demand in the Spirits Industry A...Ch. 14 - Disneys Magic Numbers Sales and operations...Ch. 14 - Disneys Magic Numbers Sales and operations...Ch. 14 - Prob. 1QCh. 14 - List several alternatives for adjusting capacity....Ch. 14 - Prob. 3QCh. 14 - How do linear programming, the linear decision...Ch. 14 - Prob. 5QCh. 14 - What options are available for altering the...Ch. 14 - Prob. 7QCh. 14 - Prob. 8QCh. 14 - Explain the process of collaborative planning. How...Ch. 14 - Prob. 11QCh. 14 - Prob. 12QCh. 14 - Prob. 1PCh. 14 - Prob. 2PCh. 14 - Prob. 3PCh. 14 - Prob. 4PCh. 14 - Mamas Stuffin is a popular food item during the...Ch. 14 - Prob. 6PCh. 14 - Slopes Sleds (SS) makes skis, snowboards, and...Ch. 14 - Prob. 8PCh. 14 - Midlife Shoes, Inc, is a manufacturer of sensible...Ch. 14 - Design a production plan for Mamas Stuffin in...Ch. 14 - Design a production plan for FansForYou in Problem...Ch. 14 - Prob. 16PCh. 14 - Prob. 17PCh. 14 - Prob. 18PCh. 14 - Prob. 19PCh. 14 - Prob. 20PCh. 14 - Prob. 21PCh. 14 - Prob. 22PCh. 14 - How many units are available-to-promise in period...Ch. 14 - Complete the available-to-promise table below.Ch. 14 - Complete the available-to-promise table below.Ch. 14 - Calculate the available-to-promise row in the...Ch. 14 - Complete the following table. How many Bs are...Ch. 14 - Managers at the Dew Drop Inn are concerned about...Ch. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Prob. 31PCh. 14 - Prob. 32PCh. 14 - The Forestry Club sells Christmas trees each year...Ch. 14 - Prob. 34PCh. 14 - Tariott Hotel rents rooms for 125 a night that...Ch. 14 - Prob. 36PCh. 14 - Prob. 1.1CPCh. 14 - Prob. 1.2CPCh. 14 - Prob. 1.3CP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Scenario 3 Ben Gibson, the purchasing manager at Coastal Products, was reviewing purchasing expenditures for packaging materials with Jeff Joyner. Ben was particularly disturbed about the amount spent on corrugated boxes purchased from Southeastern Corrugated. Ben said, I dont like the salesman from that company. He comes around here acting like he owns the place. He loves to tell us about his fancy car, house, and vacations. It seems to me he must be making too much money off of us! Jeff responded that he heard Southeastern Corrugated was going to ask for a price increase to cover the rising costs of raw material paper stock. Jeff further stated that Southeastern would probably ask for more than what was justified simply from rising paper stock costs. After the meeting, Ben decided he had heard enough. After all, he prided himself on being a results-oriented manager. There was no way he was going to allow that salesman to keep taking advantage of Coastal Products. Ben called Jeff and told him it was time to rebid the corrugated contract before Southeastern came in with a price increase request. Who did Jeff know that might be interested in the business? Jeff replied he had several companies in mind to include in the bidding process. These companies would surely come in at a lower price, partly because they used lower-grade boxes that would probably work well enough in Coastal Products process. Jeff also explained that these suppliers were not serious contenders for the business. Their purpose was to create competition with the bids. Ben told Jeff to make sure that Southeastern was well aware that these new suppliers were bidding on the contract. He also said to make sure the suppliers knew that price was going to be the determining factor in this quote, because he considered corrugated boxes to be a standard industry item. Is Ben Gibson acting legally? Is he acting ethically? Why or why not?arrow_forwardScenario 3 Ben Gibson, the purchasing manager at Coastal Products, was reviewing purchasing expenditures for packaging materials with Jeff Joyner. Ben was particularly disturbed about the amount spent on corrugated boxes purchased from Southeastern Corrugated. Ben said, I dont like the salesman from that company. He comes around here acting like he owns the place. He loves to tell us about his fancy car, house, and vacations. It seems to me he must be making too much money off of us! Jeff responded that he heard Southeastern Corrugated was going to ask for a price increase to cover the rising costs of raw material paper stock. Jeff further stated that Southeastern would probably ask for more than what was justified simply from rising paper stock costs. After the meeting, Ben decided he had heard enough. After all, he prided himself on being a results-oriented manager. There was no way he was going to allow that salesman to keep taking advantage of Coastal Products. Ben called Jeff and told him it was time to rebid the corrugated contract before Southeastern came in with a price increase request. Who did Jeff know that might be interested in the business? Jeff replied he had several companies in mind to include in the bidding process. These companies would surely come in at a lower price, partly because they used lower-grade boxes that would probably work well enough in Coastal Products process. Jeff also explained that these suppliers were not serious contenders for the business. Their purpose was to create competition with the bids. Ben told Jeff to make sure that Southeastern was well aware that these new suppliers were bidding on the contract. He also said to make sure the suppliers knew that price was going to be the determining factor in this quote, because he considered corrugated boxes to be a standard industry item. As the Marketing Manager for Southeastern Corrugated, what would you do upon receiving the request for quotation from Coastal Products?arrow_forwardThe Tinkan Company produces one-pound cans for the Canadian salmon industry. Each year the salmon spawn during a 24-hour period and must be canned immediately. Tinkan has the following agreement with the salmon industry. The company can deliver as many cans as it chooses. Then the salmon are caught. For each can by which Tinkan falls short of the salmon industrys needs, the company pays the industry a 2 penalty. Cans cost Tinkan 1 to produce and are sold by Tinkan for 2 per can. If any cans are left over, they are returned to Tinkan and the company reimburses the industry 2 for each extra can. These extra cans are put in storage for next year. Each year a can is held in storage, a carrying cost equal to 20% of the cans production cost is incurred. It is well known that the number of salmon harvested during a year is strongly related to the number of salmon harvested the previous year. In fact, using past data, Tinkan estimates that the harvest size in year t, Ht (measured in the number of cans required), is related to the harvest size in the previous year, Ht1, by the equation Ht = Ht1et where et is normally distributed with mean 1.02 and standard deviation 0.10. Tinkan plans to use the following production strategy. For some value of x, it produces enough cans at the beginning of year t to bring its inventory up to x+Ht, where Ht is the predicted harvest size in year t. Then it delivers these cans to the salmon industry. For example, if it uses x = 100,000, the predicted harvest size is 500,000 cans, and 80,000 cans are already in inventory, then Tinkan produces and delivers 520,000 cans. Given that the harvest size for the previous year was 550,000 cans, use simulation to help Tinkan develop a production strategy that maximizes its expected profit over the next 20 years. Assume that the company begins year 1 with an initial inventory of 300,000 cans.arrow_forward
- A manager is attempting to put together an agregate plan for the coming nine months. She has obtained a forecast of expected demand for the planning horizon. The plan must deal with highly seasonal demand; demand is relatively high in periods 3 and 4 and again in period 8, as can be seen from the following forecast. Period 1 2 3 4 5 6 7 8 9 TotalForecast 190 230 260 280 210 170 160 260 180 1,940 The department now has 20 ful-time employees, each of whom produces 10 units of output per period at cost of $6 per unit. Beging inventory for period 1 is zero. Inventory carrying cost is $5 per unit per period, and backlog cost is $10 per unit per period. a. Will the current work force be able to handle the forecast demand? b. Determine the total cost of the plan, including production, inventory, and backorder cost.arrow_forwardThe forecasted demand for fudge for the next four months is 110, 140, 230, and 160 pounds. What is the recommended production rate if a level strategy is adopted with no backorders or stockouts? What is the ending inventory for month 4 under this plan? Round your answers to the nearest whole number. Production rate: pounds/month Ending inventory (month 4): pounds What is the level production rate with no ending inventory in month 4? Round your answer to one decimal place. Production rate: pounds/montharrow_forwardMaruti Suzuki plants at Gurgaon and Maneshar also manufacture the Nexa range of Cars. The production planning is done based on the sales estimate provided by the marketing department. The demand forecast for the next twelve months provided assumes normal distribution of Nexa Cars with mean monthly demand of 18000 and standard deviation 900. The production planning has targeted 600 Nexa cars assembly per day with standard deviation 30. One of the outsourced component used in the car is tyre, which is procured from the MRF Plant at Chennai at the rate of Rs. 3,500 per tyre. The ordering cost is Rs. 500,000 per order and it takes 5 days to receive the order. The holding cost is 10 % of the cost of item per annum. If you are the Purchase manager for the material planning of the outsourced components, determine the inventory management policy* to minimize the inventory cost in context of tyres. Assume 30 working days in a month. Suppose Bridgestone plant at Maneshar offers the next day…arrow_forward
- a) For an upcoming red carpet evening, a company is selling tickets at $60 per person at a large theatre which has a capacity of 10,000 people. Each attendant is expected to buy $12 of food and merchandise at the film evening. The cost of providing the food and merchandise is estimated to be $5 per person. All other ancillary services will be provided by the theatre. Initial analysis indicates that the ancillary cost of providing food and merchandise, as well as the staff needed to handle ticket sales, may be described as a semi-variable cost. Data on these costs and tickets sold from three similar events held at the venue have been collected and are tabulated below: Tickets Sold Cost ($) 2100 6640 3824 11284 4650 13525 Use the high-low method to estimate the total cost function relating to these ancillary costs. b) The company will be renting the theatre which will host the upcoming red carpet evening. The budgeted fixed cost of both renting the theatre and paying the…arrow_forwardOn August, a light business bought $3600 worth of lamps. At the beginning of September, the store had $1400 in lights on hand, and by the end of September, it projected to have $1600 in lamps on hand to meet some of the forecasted October sales. And what's the August planned cost of goods sold?arrow_forwardMicromedia offers computer training seminars on a variety of topics. In the seminars each student works at a personal computer, practicing the particular activity that the instructor is presenting. Micromedia is currently planning a two-day seminar on the use of Microsoft Excel in statistical analysis. The projected fee for the seminar is 600 dollars per student. The cost for the conference room, instructor compensation, lab assistants, and promotion is 9600 dollars. Micromedia rents computers for its seminars at a cost of 60 dollars per computer per day. a. Develop a model for the total cost to put on the seminar. Let x represent the number of students who enroll in the seminar. b. Develop a model for the total profit if x students enroll in the seminar. c. Micromedia has forecasted an enrollment of 30 students for the seminar. How much profit will be earned if its forecast is accurate? d. Compute the breakeven point. e. Write a report and recommendation based on the analysisarrow_forward
- production planning and control please helparrow_forwardproduction planning and control please helparrow_forwardA manager has prepared a forecast of expected aggregate demand for the next six months. Develop an aggregate plan to meet this demand given this additional information: A level production rate of 1000 units per month can be used. Backorders are allowed, and they are charged at the rate of $20 per unit per month. Inventory holding costs are $1 per unit per month in ending inventory. Determine the cost of this plan if regular time cost is $10 per unit and beginning inventory is zero. Overtime costs $16 per unit and subcontracting costs $20 per unit. In the 4th month, overtime is not possible. While outsourcing is not allowed in the 3rd month. Overtime capacity is 100 units and subcontracting capacity is 100 units per month. Month Forecast 1 800 2 960 3 1120 4 1440 5…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning