Chapter 10, Problem 21P
a)
Summary Introduction
To determine: The capability index of the process.
Introduction: Quality is a measure of excellence or a state of being free from deficiencies, defects and important variations. It is obtained by consistent and strict commitment to certain standards to attain uniformity of a product to satisfy consumers’ requirement.
b)
Summary Introduction
To determine: Whether the process is capable.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A process that produces computer chips has a mean of .04 defective chip and a standard deviationof .003 chip. The allowable variation is from .03 to .05 defective.a. Compute the capability index for the process.b. Is the process capable?
6-9. A process that produces computer chips has a mean of .04 defective chip and a standard
deviation of .003 chip. The allowable variation is from .03 to .05 defective.
(a) Compute the capability index for the process
(b) Is the process capable?
1. The overall average on a process you are attempting to monitor is
55.0
units. The process population standard deviation is
1.84.
Sample size is given to be
16.
a) Determine the 3-sigma
x-chart
control limits.
Upper Control Limit
(UCLx)=56.3856.38
units (round your response to two decimal places).
Lower Control Limit
(LCLx)=53.6253.62
units (round your response to two decimal places).
b) Now determine the 2-sigma
x-chart
control limits.
Upper Control Limit
(UCLx)=?
units (round your response to two decimal places).
2.
Sample
Size, n
Mean Factor,
A2
Upper Range,
D4
Lower Range,
D3
2
1.880
3.268
0
3
1.023
2.574
0
4
0.729
2.282
0
5
0.577
2.115
0
6
0.483
2.004
0
7
0.419
1.924
0.076
8
0.373
1.864
0.136
9
0.337
1.816
0.184
10
0.308
1.777
0.223
12
0.266
1.716
0.284
Thirty-five samples of size
7
each were taken from a…
Chapter 10 Solutions
Operations Management
Ch. 10.2 - A potato chip is a delicate thing Fragile A pound...Ch. 10.2 - A potato chip is a delicate thing Fragile A pound...Ch. 10.5 - It's estimated that more than 7 000 hospital...Ch. 10.5 - It's estimated that more than 7 000 hospital...Ch. 10 - Prob. 1DRQCh. 10 - Prob. 2DRQCh. 10 - Prob. 3DRQCh. 10 - Prob. 4DRQCh. 10 - Prob. 5DRQCh. 10 - Prob. 6DRQ
Ch. 10 - Prob. 7DRQCh. 10 - Prob. 8DRQCh. 10 - Prob. 9DRQCh. 10 - Prob. 10DRQCh. 10 - Prob. 11DRQCh. 10 - Prob. 12DRQCh. 10 - Prob. 13DRQCh. 10 - Prob. 14DRQCh. 10 - Prob. 15DRQCh. 10 - Prob. 16DRQCh. 10 - Prob. 1TSCh. 10 - Prob. 2TSCh. 10 - Prob. 3TSCh. 10 - Prob. 1CTECh. 10 - Prob. 2CTECh. 10 - Prob. 3CTECh. 10 - Prob. 4CTECh. 10 - Prob. 1PCh. 10 - Prob. 2PCh. 10 - Prob. 3PCh. 10 - Prob. 4PCh. 10 - Prob. 5PCh. 10 - Prob. 6PCh. 10 - Prob. 7PCh. 10 - Prob. 8PCh. 10 - Prob. 9PCh. 10 - Prob. 10PCh. 10 - Prob. 11PCh. 10 - Prob. 12PCh. 10 - Prob. 13PCh. 10 - Prob. 14PCh. 10 - Prob. 15PCh. 10 - Prob. 16PCh. 10 - Prob. 17PCh. 10 - A production process consists of a three-step...Ch. 10 - Prob. 19PCh. 10 - Prob. 20PCh. 10 - Prob. 21PCh. 10 - Prob. 22PCh. 10 - Prob. 23PCh. 10 - Prob. 24PCh. 10 - Prob. 25PCh. 10 - Prob. 26PCh. 10 - Prob. 27PCh. 10 - Prob. 28PCh. 10 - Prob. 29PCh. 10 - Prob. 1.1CQCh. 10 - Prob. 2.1CQCh. 10 - Prob. 2.2CQCh. 10 - Prob. 2.3CQCh. 10 - Prob. 2.4CQ
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Each of the processes listed is noncentered with respect to the specifications for that process.Compute the appropriate capability index for each, and decide if the process is capable.Process Mean Standard Deviation Lower Spec Upper SpecH 15.0 0.32 14.1 16.0K 33.0 1.00 30.0 36.5T 18.5 0.40 16.5 20.1arrow_forwardA metal fabricator produces connecting rods with an outer diameter that has a 1 ± 0.04 inch specification. A machine operator takes several sample measurements over time and determines the sample mean outer diameter to be 1.003 inches with a standard deviation of 0.020 inch. Calculate the process capability index.arrow_forwardThe overall average on a process you are attempting to monitor is 60.0 units. The process population standard deviation is 1.72. Sample size is given to be 4. Part 2 a) Determine the 3-sigma x-chart control limits. Upper Control Limit (UCLx)=enter your response here units (round your response to two decimal places). Part 3 Lower Control Limit (LCLx)=enter your response here units (round your response to two decimal places). Part 4 b) Now determine the 2-sigma x-chart control limits. Upper Control Limit (UCLx)=enter your response here units (round your response to two decimal places). Part 5 Lower Control Limit (LCLx)=enter your response here units (round your response to two decimal places). Part 6 How do the control limits change? A. The control limits are tighter for the 3-sigma x-chart than for the 2-sigma x-chart. B. The control limits for the 2-sigma x-chart and for the 3-sigma x-chart are the same. C. The control limits…arrow_forward
- Can someone please explain how to find upper and lower limits using Excel? I am trying to answer this question: The overall average on a process you are attempting to monitor is 50.0 units. The process population standard deviation is 1.84 Sample size is given to be 4.a) Determine the 3-sigma x-chart control limits. Upper Control Limit (UCL) = ____units (round your response to two decimal places).arrow_forwardAt Gleditsia Triacanthos Company, a certain manufactured part is deemed acceptable if its lengthis between 12.45 to 12.55 inches. The process is normally distributed with an average of 12.49inches and a standard deviation of 0.014 inches. A) Is the process capable of meeting specifications? B) Does the process meet specifications?arrow_forwardWe want to determine the AOQ for an acceptance samplingplan when the quality of the incoming lots in percent defectiveis 1.5%, and then again when the incoming percent defective is 5%.T he sample size is 80 units for a lot size of 550 units. Furthermore,Pa at 1.5% defective levels is 0.95. At 5% incoming defective levels,the Pa is found to be 0.5. Determine the average outgoing qualityfor both incoming percent defective levels.arrow_forward
- An e-commerce website has received some complaints on Billing errors. Managers ask the accounting department to monitor the shipping process and make sure of the quality in their process. To monitor the process, for 10 consecutive weeks, they look into the first 100 shipments and count the number of Billing errors as shown in table below: 45 52 6 3 63 7 8 9 10 1 6 1 2 Construct a two-sigma limit control chart to show whether the shipping process in this e-commerce firm needs any improvement or performs at an acceptable level. (Round your answer to three decimal places.) Week 1 2 3 Number of Billing errors. 5 1 3 Upper Control Limit Lower Control Limitarrow_forwardAt Gleditsia Triacanthos Company, a certain manufactured part is deemed acceptable if its length is between 12.45 to 12.55 inches. The process is normally distributed with an average of 12.49 inches and a standard deviation of 0.014 inches. a) is the process capable of meeting specifications? b) Does the process meet specifications?arrow_forwardAn operator wants to determine the standard deviation for a machine she operates. To do this, she wants to create a p-chart. Over a month's time, she collects 30 samples of 75 observations each and records the number of errors. The average proportion defective is found to be 0.024. Which of the following is the standard deviation () of the machine? a. More than 0.5 but less than or equal to 1.0 b. More than 1.0 c. Less than or equal to 0.1 d. More than 0.1 but less than or equal to 0.5arrow_forward
- A process considered to be in control measures an ingredient in ounces. A quality inspector took 10 samples, each with 5 observations as follows: Using this information, obtain three-sigma (i.e., z=3) control limits for a mean control chart and control limits for a range chart, respectively. It is known from previous experience that the standard deviation of the process is 1.36. Discuss whether the process is in control or not.arrow_forwardUsing samples of 200 credit card statements, an auditor found the following: Sample 1 2 3 4 Number with errors 4 2 5 9 a. Determine the fraction defective in each sample. b. If the true fraction defective for this process is unknown, what is your estimate of it? c. What is your estimate of the mean and standard deviation of the sampling distribution of fractions defective for samples of this size? d. What control limits would give an alpha risk of .03 for this process? Page 457 e. What alpha risk would control limits of .047 and .003 provide? f. Using control limits of .047 and .003, is the process in control? g. Suppose that the long-term fraction defective of the process is known to be 2 percent. What are the values of the mean and standard deviation of the sampling distribution? h. Construct a control chart for the process, assuming a fraction defective of 2 percent, using two-sigma control limits. Is the process in control? Can you show me the steps and formulas using excelarrow_forward1. The data shown in Table 1 are x and R values for 20 samples of size n= 5 taken from a process producing bearings. The measurements are made on the inside diameter of the bearing, with only the last three decimals recorded (i.e., 31.6 should be 0.50316). Please show all your work for full credit. (a) Set up x and R charts on this process. Does the process seem to be in statistical control? If necessary, revise the trial control limits. (b) Assume that diameter is normally distributed. Estimate the process standard deviation. Sample R Sample R 1 31.6 4 11 29.8 4 33.0 3 12 34.0 4 35.0 4 13 33.0 10 4 32.2 4 14 34.8 4 5 33.8 38.4 31.6 15 35.6 7 3 16 30.8 7 4 17 33.0 5 8 36.8 10 18 31.6 3 9. 35.0 15 19 28.2 9 10 34.0 6 20 33.8 Table 1: Bearing Diameter Dataarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.