Concept explainers
a)
To determine: The results of the run test.
Introduction: Run chart refers to a line graph that displays the recorded data based on the time sequence.
a)
Answer to Problem 14P
Explanation of Solution
Given information:
Test | z-score |
Median | +1.37 |
Up/Down | +1.05 |
By observing the given data of median +1.37 (< ±2) and up/down +1.05 (< ±2), it can be concluded that they are within the statistical limits of ±2.
Hence, the result of the run test suggests that the output possess randomness.
b)
To determine: The results of the run test.
Introduction: Run chart refers to a line graph that displays the recorded data based on the time sequence.
b)
Answer to Problem 14P
Explanation of Solution
Given information:
Formula:
Calculation of expected number of runs:
Observed number of runs = 14
The expected number of runs is calculated by adding half of the total number of samples with 1 which gives 11.
Calculation of standard deviation:
Standard deviation is calculated by subtracting number of sample 20 from 1 and dividing the resultant by 4 and taking square for the value which yields 2.18.
The z factor for median is calculated by dividing the difference of 14 and 11 with 2.18 which yields +1.38 which is within the test statistics of ±2.00 and no non-randomness exist.
Up/Down Test:
The observed number of runs is 8.
Calculation of expected number of runs:
The expected number of runs is calculated by subtracting the double of the number of samples 20 and subtracting from1 and dividing the resultant with 3 which gives 13.
Calculation of standard deviation:
Standard deviation is calculated by multiplying the number of samples with 16 and subtracting the resultant from 29 and then dividing the resulting value with 90 and taking square root which yields 1.80.
The z factor for median is calculated by dividing the difference of 8 and 13 with 1.80 which yields -2.78 which is beyond the test statistics of ±2.00 which is non-random.
Hence, the result of the median run test is random and up/down test is no non randomness is detected.
c)
To determine: The results of the run test.
Introduction: Run chart refers to a line graph that displays the recorded data based on the time sequence.
c)
Answer to Problem 14P
Explanation of Solution
Given information:
Cable | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
Defects | 2 | 3 | 1 | 0 | 1 | 3 | 2 | 0 | 2 | 1 | 3 | 1 | 2 | 0 |
Formula:
Analysis of data:
To make analysis of data, the given data is compared with median (center line) to make A/B and U/D which is shown below,
Median run test:
From analysis, the observed number of runs is 10 and median is 1.5.
Calculation of expected number of runs:
The expected number of runs is calculated by adding half of the total number of samples with 1 which gives 8.
Calculation of standard deviation:
Standard deviation is calculated by subtracting number of sample 14 from 1 and dividing the resultant by 4 and taking square for the value which yields 1.80.
The z factor for median is calculated by dividing the difference of 10 and 8 with 1.80 which yields +1.11 which is within the test statistics of ±2.00 and no non-randomness exist.
Up/Down Test:
The observed number of runs from the analysis is 10.
Calculation of expected number of runs:
The expected number of runs is calculated by subtracting the double of the number of samples 14 and subtracting from1 and dividing the resultant with 3 which gives 9.0.
Calculation of standard deviation:
Standard deviation is calculated by multiplying the number of samples with 14 and subtracting the resultant from 29 and then dividing the resulting value with 90 and taking square root which yields 1.47.
The z factor for median is calculated by dividing the difference of 10 and 9 with 1.47 which yields +0.68which is within the test statistics of ±2.00.
Hence, the results of the median run test and up/down test is random and no non randomness is detected.
d)
To determine:The results of the run test.
Introduction: Run chart refers to a line graph that displays the recorded data based on the time sequence.
d)
Answer to Problem 14P
Explanation of Solution
Given information:
Day | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
Comp. | 4 | 10 | 14 | 8 | 9 | 6 | 5 | 12 | 13 | 7 | 6 | 4 | 2 | 10 |
Formula:
Analysis of data:
To make analysis of data, the given data is compared with median (center line) to make A/B and U/D which is shown below,
Median run test:
From analysis, the observed number of runs is 8.
Calculation of expected number of runs:
The expected number of runs is calculated by adding half of the total number of samples with 1 which gives 8.
Calculation of standard deviation:
Standard deviation is calculated by subtracting number of sample 14 from 1 and dividing the resultant by 4 and taking square for the value which yields 1.80.
The z factor for median is calculated by dividing the difference of 6 and 8 with 1.80 which yields -1.11 which is beyond the test statistics of ±2.00 and non-randomness exist.
Up/Down Test:
The observed number of runs from the analysis is 7.
Calculation of expected number of runs:
The expected number of runs is calculated by subtracting the double of the number of samples 26 and subtracting from1 and dividing the resultant with 3 which gives 9.0.
Calculation of standard deviation:
Standard deviation is calculated by multiplying the number of samples with 16 and subtracting the resultant from 29 and then dividing the resulting value with 90 and taking square root which yields 1.47.
The z factor for median is calculated by dividing the difference of 7 and 9 with 1.47 which yields -1.36 which is within the test statistics of ±2.00.
Hence, the results of the median run test and up/down test is random and no non randomness is detected.
Want to see more full solutions like this?
Chapter 10 Solutions
Operations Management
- 4. Problem 8.29 The number of imperfections in bond paper produced by a paper mill is observed over a period of several days. Table 8-28 shows the area inspected and the number of imperfections for 25 samples. Construct a control chart for the number of imperfections per square meter. Revise the limits, if necessary, assuming special causes for the out-of-control points. TABLE 8-28 Area Area Sample Inspected (m?) Imperfections Sample Inspected (m²) Imperfections 1 150 6 14 300 8 2 100 8 15 300 12 3 200 5 16 200 6 4 150 4 17 150 4 250 10 18 200 7 6. 100 11 19 150 14 7 150 20 100 4 8 200 5 21 100 8 9 300 10 22 200 10 250 10 23 300 12 11 100 24 250 7 12 200 4 25 200 5 13 250 12arrow_forwardThe Healthy Chocolate Company makes a variety of chocolate candles, including a 12-ounce chocolate bar (340 grams) and a box of six 1-ounce chocolate bars (170 grams). a.Specifications for the 12-ounce bar are 322 grams to 358 grams. What is the largest standard deviation (In grams) that the machine that fills the bar molds can have and still be considered capable if the average fill is 340 grams? (Round your intermediate calculations to 2 decimal places and final answer to 3 decimal places.) Standard deviation b.The machine that filles the bar molds for the 6-ounce bars has a standard deviation of .84 grams. The filling machine is set to deliver an average of 1.04 ounces per bar. Specifications for the six-bar box are 150 to 190 grams per box. Is the process capable? Hint: The variance for the box is equal to six times the bar variance. Convert all calculations Into grams. O Yes O No grams c.What is the lowest setting in ounces for the filling machine that will provide capability in…arrow_forwardSolve in a normal method (no excel please ). (8)arrow_forward
- P-chart and c-chart. Using the appropriate control chart, determine two-sigma controllimits for each Problem case, a. An inspector found an average of 3.9 scratches in the exterior paint of each of theautomobiles being prepared for shipment to dealers. b. Before shipping lawnmowers to dealers, an inspector attempts to start each mowerand notes any that do not start on the first try. The lot size is 100 mowers, and anaverage of 4 did not start (4 percent).arrow_forwardProblem 10-4 (Static) Software upgrade times (in minutes) are being evaluated. Samples of five observations each have been taken, and the results are as listed. 1 79.2 78.8 80.0 78.4 81.0 Number of Observations in Subgroup, n 2 4 5 6 7 8 9 Click here for the Excel Data File Factors for three-sigma control limits for and Rcharts 10 11 13 12 13 14 SAMPLE 2 4 3 80.5 79.6 78.9 78.7 81.0 80.4 79.7 79.6 79.4 80.4 79.4 80.1 80.6 15 16 17 18 19 20 80.3 80.8 Factor for I Chart, A2 1.88 1.02 0.73 0.58 0.48 0.42 5 6 80.5 79.7 79.6 80.6 80.4 80.5 80.8 80.0 78.8 81.1 0.37 0.34 0.31 0.29 0.27 0.25 0.24 0.22 0.21 0.20 0.19 0.19 0.18 FACTORS FOR R CHARTS Lower Upper Control Limit, D3 Control Linit, D4 3.27 2.57 2.28 2.11 2.00 1.92 1.86 1.82 1.78 1.74 1.72 1.69 1.67 1.65 1.64 1.62 1.61 1.60 1.59 0 8 0 0 0 0.08 0.14 0.18 0.22 0.26 0.28 0.31 0.33 0.35 0.36 0.38 0.39 0.40 0.41arrow_forwardSam’s Long Life 60-watt light bulbs are designed to have a life of 1,350 hours with tolerance of ± 340 hours. A recent representative sample from the process that makes these light bulbs revealed a mean of 1,290 hours, with a standard deviation of 94 hours. Compute a. Compute the process capability ratio and the process capability index, and comment on the overall capability of the process b. Explain to what extent the process for producing Sam’s Long Life 60-watt light bulbs would have to be improved to achieve 4-sigma quality. c. show detail workarrow_forward
- A shirt manufacturer buys clothes by the 100-yard roll from a supplier. For setting a control chart to manage the irregularities (e.g., loose threads and tears), the following data were collected from a sample provided by the supplier. Sample 1 2 3 4 5 6 7 8 9 10 Irregularities 3 5 2 6 5 4 6 3 4 5 Which type of control chart should be used? Construct a control chart with two-sigma control limits. Suppose the next five rolls from the supplier had three, two, five, three, and seven irregularities. Is the supplier process under control? Explain and show workarrow_forwardAuto pistons at Wemming Chung's plant in Shanghai are produced in a forging process, and the diameter is a critical factor that must be controlled. From sample sizes of 10 pistons produced each day, the mean and the range of this diameter have been as follows: a) What is the value of x? x= 156.76 mm (round your response to two decimal places). b) What is the value of R? Day 1 2 3 4 5 Mean x (mm) 158.9 155.2 155.6 157.5 156.6 R = 4.40 mm (round your response to two decimal places). c) What are the UCL and LCL using 3-sigma? Upper Control Limit (UCL) = mm (round your response to two decimal places). Range R (mm) 4.2 4.4 4.3 4.8 4.3 Çarrow_forwardPlease do not give solution in image format thankuarrow_forward
- The operations manager of thebooking services departmentof Hometown Bank is concerned about the number ofwrong customer account numbers recorded by Hometownpersonnel. Each week a random sample of 2,500 depositsis taken, and the number of incorrect account numbers is recorded. The results for the past12 weeks are shown in thefollowing table. Is the bookingprocess out of statistical control? Use three-sigma controllimits, which will provide a typeI error of 0.26 percent.arrow_forwardWhy is it usually desirable to use both a median run test and an up/down run test on the same data in an production of organization ?arrow_forwardThe following is a control chart for the average number of minor errors in 22 service reports. UCL LCL a. Calculate the observed mean, expected mean, standard deviation and z value for the median and up/down test. Use z = +/-2 to compare your z test scores. (Negative amounts should be indicated by a minus sign. Round your answers to 2 decimal places.) Test Observed Expected Std. dev Median Up/Downarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.