Suppose you are using a push-loaded scraper with a heaped capacity of 31 cy. Assuming an average load of 96% of heaped capacity results in an average load of 29.76 cy. If the material to be hauled is a sandy clay with a swell factor of 0.80, what is the volume carried in bank cubic yards?
Suppose you are using a push-loaded scraper with a heaped capacity of 31 cy. Assuming an average load of 96% of heaped capacity results in an average load of 29.76 cy. If the material to be hauled is a sandy clay with a swell factor of 0.80, what is the volume carried in bank cubic yards?
Principles of Foundation Engineering (MindTap Course List)
9th Edition
ISBN:9781337705028
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Braja M. Das, Nagaratnam Sivakugan
Chapter12: Pile Foundations
Section: Chapter Questions
Problem 12.36P: Figure P12.36 shows a 3 5 pile group consisting of 15 concrete piles of 400 mm diameter and 12 m in...
Related questions
Question
Suppose you are using a push-loaded scraper with a heaped capacity of 31 cy. Assuming an average load of 96% of heaped capacity results in an average load of 29.76 cy. If the material to be hauled is a sandy clay with a swell factor of 0.80, what is the volume carried in bank cubic yards?
AI-Generated Solution
AI-generated content may present inaccurate or offensive content that does not represent bartleby’s views.
Unlock instant AI solutions
Tap the button
to generate a solution
Recommended textbooks for you
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning