Problem 2. (1 point) Market Fresh Foods is looking to develop a new strategic plan. Guillermo Santiago has been developing a project plan and has identified the following tasks, precedence relations, normal task durations, and resource requirements. Task Predecessors Task Duration Resource Required 0 2 start A start 0 38 BCDEF В A 37 с A 27 234 A 20 5 B, C, D 12 E 25 E 34 I E E 20 18 J F, G, H, I 43 end J 0 621662O Guillermo has studied project management at the University of Portland and knows that the makespan of the project may be determined from the information in the table using the critical path method. Guillermo also learned a simple heuristic for evaluating resource sufficiency. Help Guillermo by answering the following related assuming 3 workers per week and a due date of 302.8: Project Work Content: Total Resource Capacity: Minimum due date for which 3 resources is sufficient: Minimum resource level that could make due date of 302.8 feasible:
1 point) Market Fresh Foods is looking to develop a new strategic plan. Guillermo Santiago has been developing a project plan and has identified the following tasks, precedence relations, normal task durations, and resource requirements.
Guillermo has studied project management at the University of Portland and knows that the makespan of the project may be determined from the information in the table using the critical path method. Guillermo also learned a simple heuristic for evaluating resource sufficiency. Help Guillermo by answering the following related assuming 3 workers per week and a due date of 302.8:
Project Work Content:
Total Resource Capacity:
Minimum due date for which 3 resources is sufficient:
Minimum resource level that could make due date of 302.8 feasible:


Step by step
Solved in 2 steps