Problem 1. (2 points) Jimbo's Java & Jerk is looking to implement a new labor scheduling system. Colin Alexander has been developing a project plan and has identified the following tasks, precedence relations, and normal task durations. Task Predecessors με σε start 0 0 A start 19 20.14 B start 31 36.27 C B 6 6.24 Ꭰ A 39 45.24 E A 31 18.91 F E 12 8.16 G C, D, F 13 14.69 H E 40 18.4 end G, H 0 0 Because Colin has studied project management at the University of Portland, he knows that the he should incorporate a time buffer into any estimates for the project's makespan. If Colin wants to quote a 90% makespan: Quoted Makespan = Time Buffer = Note: state all answers to two decimal places. Note: You can earn partial credit on this problem. preview answers

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
icon
Related questions
Question

Problem 1.

(2 points) Jimbo's Java & Jerk is looking to implement a new labor scheduling system. Colin Alexander has been developing a project plan and has identified the following tasks, precedence relations, and normal task durations.

 

Because Colin has studied project management at the University of Portland, he knows that the he should incorporate a time buffer into any estimates for the project's makespan. If Colin wants to quote a 90% makespan:

Quoted Makespan = 
Time Buffer = 

Note: state all answers to two decimal places.

Problem 1.
(2 points) Jimbo's Java & Jerk is looking to implement a new labor scheduling system. Colin Alexander has been developing a project plan and has identified the following tasks, precedence relations,
and normal task durations.
Task Predecessors
με
σε
start
0
0
A
start
19
20.14
B
start
31
36.27
C
B
6
6.24
Ꭰ
A
39
45.24
E
A
31
18.91
F
E
12
8.16
G
C, D, F
13
14.69
H
E
40
18.4
end
G, H
0
0
Because Colin has studied project management at the University of Portland, he knows that the he should incorporate a time buffer into any estimates for the project's makespan. If Colin wants to
quote a 90% makespan:
Quoted Makespan
=
Time Buffer =
Note: state all answers to two decimal places.
Note: You can earn partial credit on this problem.
preview answers
Transcribed Image Text:Problem 1. (2 points) Jimbo's Java & Jerk is looking to implement a new labor scheduling system. Colin Alexander has been developing a project plan and has identified the following tasks, precedence relations, and normal task durations. Task Predecessors με σε start 0 0 A start 19 20.14 B start 31 36.27 C B 6 6.24 Ꭰ A 39 45.24 E A 31 18.91 F E 12 8.16 G C, D, F 13 14.69 H E 40 18.4 end G, H 0 0 Because Colin has studied project management at the University of Portland, he knows that the he should incorporate a time buffer into any estimates for the project's makespan. If Colin wants to quote a 90% makespan: Quoted Makespan = Time Buffer = Note: state all answers to two decimal places. Note: You can earn partial credit on this problem. preview answers
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Principles of Management
Principles of Management
Management
ISBN:
9780998625768
Author:
OpenStax
Publisher:
OpenStax College
Management, Loose-Leaf Version
Management, Loose-Leaf Version
Management
ISBN:
9781305969308
Author:
Richard L. Daft
Publisher:
South-Western College Pub