Detail Instructions Consider the following activities, activity times and precedence relations for a hypothetical Athletic Club Building project. Activity Activity Description Normal Time (weeks) Immediate Predecessors A Form project team 9 B Prepare renovation plans 12 A C Demolish interior space 10 B D Upgrade utility systems 20 A E Select equipment, furniture & 10 B fixtures F Hire Staff 10 A G Renovate building 30 B,C H Purchase equipment, furniture & 26 E fixtures Install equipment, furniture & 4 D.G.H fixtures 3 FI J Train staff a) Draw a project network. b) List all paths and path length (duration) of each path c) Based on step b, what is the critical path and projection. In one sentence, explain how you know. d) Make a forward pass through the network to compute and annotate the project network with earliest start and finish time for each activity e) Make a backward pass through the network to compute and annotate the project network with latest start and finish time for each activity e) Compute to compute and annotate the project network with the slack time for each activity. f) Highlight the critical path on the network by using different arrow colors or arrow thickness. g) Using new information from step e that was not available from step b, explain in one sentence how you know what the critical path is. h) Indicate which activities can be delayed without delaying the whole project and also how long each of these activities can be delayed. i) If you shortened the time of activity H, would it shorten the project duration? Explain why or why not. j) If you shortened the time of activity G, would it shorten the project duration? Explain why or why not.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter5: Network Models
Section5.3: Assignment Models
Problem 11P
icon
Related questions
Question
Detail Instructions
Consider the following activities, activity times and precedence relations for a hypothetical Athletic
Club Building project.
Activity Activity Description
Normal Time (weeks)
Immediate
Predecessors
A
Form project team
9
B
Prepare renovation plans
12
A
C
Demolish interior space
10
B
D
Upgrade utility systems
20
A
E
Select equipment, furniture &
10
B
fixtures
F
Hire Staff
10
A
G
Renovate building
30
B,C
H
Purchase equipment, furniture &
26
E
fixtures
Install equipment, furniture &
4
D.G.H
fixtures
3
FI
J
Train staff
Transcribed Image Text:Detail Instructions Consider the following activities, activity times and precedence relations for a hypothetical Athletic Club Building project. Activity Activity Description Normal Time (weeks) Immediate Predecessors A Form project team 9 B Prepare renovation plans 12 A C Demolish interior space 10 B D Upgrade utility systems 20 A E Select equipment, furniture & 10 B fixtures F Hire Staff 10 A G Renovate building 30 B,C H Purchase equipment, furniture & 26 E fixtures Install equipment, furniture & 4 D.G.H fixtures 3 FI J Train staff
a) Draw a project network.
b) List all paths and path length (duration) of each path
c) Based on step b, what is the critical path and projection. In one sentence, explain how you know.
d) Make a forward pass through the network to compute and annotate the project network with
earliest start and finish time for each activity
e) Make a backward pass through the network to compute and annotate the project network with
latest start and finish time for each activity
e) Compute to compute and annotate the project network with the slack time for each activity.
f) Highlight the critical path on the network by using different arrow colors or arrow thickness.
g) Using new information from step e that was not available from step b, explain in one sentence
how you know what the critical path is.
h) Indicate which activities can be delayed without delaying the whole project and also how long
each of these activities can be delayed.
i) If you shortened the time of activity H, would it shorten the project duration? Explain why or why
not.
j) If you shortened the time of activity G, would it shorten the project duration? Explain why or why
not.
Transcribed Image Text:a) Draw a project network. b) List all paths and path length (duration) of each path c) Based on step b, what is the critical path and projection. In one sentence, explain how you know. d) Make a forward pass through the network to compute and annotate the project network with earliest start and finish time for each activity e) Make a backward pass through the network to compute and annotate the project network with latest start and finish time for each activity e) Compute to compute and annotate the project network with the slack time for each activity. f) Highlight the critical path on the network by using different arrow colors or arrow thickness. g) Using new information from step e that was not available from step b, explain in one sentence how you know what the critical path is. h) Indicate which activities can be delayed without delaying the whole project and also how long each of these activities can be delayed. i) If you shortened the time of activity H, would it shorten the project duration? Explain why or why not. j) If you shortened the time of activity G, would it shorten the project duration? Explain why or why not.
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Foundations of Business (MindTap Course List)
Foundations of Business (MindTap Course List)
Marketing
ISBN:
9781337386920
Author:
William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:
Cengage Learning
Foundations of Business - Standalone book (MindTa…
Foundations of Business - Standalone book (MindTa…
Marketing
ISBN:
9781285193946
Author:
William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:
Cengage Learning
Management, Loose-Leaf Version
Management, Loose-Leaf Version
Management
ISBN:
9781305969308
Author:
Richard L. Daft
Publisher:
South-Western College Pub