The Dubuque Cement Company packs 80-pound bags of concrete mix. Time-study data for the filling activity are shown in the following table. Because of the high physical demands of the job, the company's policy is a 23% allowance for workers. (Round all intermediate calculations to two decimal places before proceeding with further calculations.) Element Performance Rating Observation (seconds) 1 2 3 4 5 Grasp and place bag 105% 7 9 9 12 8 Fill bag 80% 36 40 39 Seal bag 105% 16 17 12 Place bag on conveyor 85% 8 5 10 88 35 114 19 18 30^ 34^ Bag breaks open; included as delay in the allowance factor ^ Conveyor jams; included as delay in the allowance factor a) The standard time for this process = seconds (round your response to two decimal places).

MARKETING 2018
19th Edition
ISBN:9780357033753
Author:Pride
Publisher:Pride
Chapter1: An Overview Of Strategic Marketing
Section1.2: Dollar Shave Club: The Company For Men
Problem 1C
icon
Related questions
Question

Answer in step by step with explanation.

Don't use Ai and chatgpt.

Answer in all options.

 

The Dubuque Cement Company packs 80-pound bags of concrete mix. Time-study data for the filling activity are shown in the following table. Because of the high physical demands of the job,
the company's policy is a 23% allowance for workers. (Round all intermediate calculations to two decimal places before proceeding with further calculations.)
Element
Performance
Rating
Observation (seconds)
1
2 3
4
5
Grasp and place bag
105%
7
9
9
12
8
Fill bag
80%
36
40
39
Seal bag
105%
16
17
12
Place bag on conveyor
85%
8
5
10
88
35
114
19
18
30^
34^
Bag breaks open; included as delay in the allowance factor
^ Conveyor jams; included as delay in the allowance factor
a) The standard time for this process =
seconds (round your response to two decimal places).
Transcribed Image Text:The Dubuque Cement Company packs 80-pound bags of concrete mix. Time-study data for the filling activity are shown in the following table. Because of the high physical demands of the job, the company's policy is a 23% allowance for workers. (Round all intermediate calculations to two decimal places before proceeding with further calculations.) Element Performance Rating Observation (seconds) 1 2 3 4 5 Grasp and place bag 105% 7 9 9 12 8 Fill bag 80% 36 40 39 Seal bag 105% 16 17 12 Place bag on conveyor 85% 8 5 10 88 35 114 19 18 30^ 34^ Bag breaks open; included as delay in the allowance factor ^ Conveyor jams; included as delay in the allowance factor a) The standard time for this process = seconds (round your response to two decimal places).