Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows:
TASK | TIME (SEC) | IMMEDIATE PREDECESSORS |
A | 12 | − |
B | 15 | A |
C | 8 | A |
D | 5 | B, C |
E | 20 | D |
Rosenberg’s goal is to produce 180 PDAs per hour.
- a. What is the cycle time?
- b. What is the theoretical minimum for the number of workstations that Rosenberg can achieve in this assembly line?
- c. Can the theoretical minimum actually be reached when workstations are assigned?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Amelio Rodriguez Computing wants to establish an assembly line for producing a new product, the Personal Digital
Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows:
Task
Time
(sec)
Immediate
Predecessor
ABCDE
11
14
A
8
A
4
18
B, C
D
Amelio's goal is to produce 180 PDAs per hour.
a) The cycle time for the production of a PDA =
seconds (round your response to two decimal places).
(round your
b) The theoretical minimum number of workstations that Amelio can achieve in this assembly line =
response up to the next whole number).
c) For one to assign the tasks to the actual workstations and be able to use the "theoretical minimum" number, the
activity assignment should be:
Workstation #
Tasks Assigned to Workstation
1
A
B
2
3
Were you able to assign all the tasks to the theoretical minimum number of workstations?
Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows:
Task
Time
(sec)
Immediate Predecessor
A
11
−
B
15
A
C
7
A
D
4
B, C
E
20
D
Rosenberg's goal is to produce
175
PDAs per hour.
a) The cycle time for the production of a PDA =
nothing
seconds (round your response to two decimal places).
B) what's the minimum number of workstations in the assembly line?
C) Can the minimum actually be reached when workstations are assigned?
Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows:
Task
Time
(sec)
Immediate Predecessor
A
12
−
B
15
A
C
7
A
D
5
B, C
E
18
D
Rosenberg's goal is to produce
170
PDAs per hour.
Part 2
a) The cycle time for the production of a PDA =
enter your response here
seconds (round your response to two decimal places).
Chapter 9 Solutions
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Ch. 9 - Prob. 1DQCh. 9 - Prob. 2DQCh. 9 - Prob. 3DQCh. 9 - Prob. 4DQCh. 9 - Prob. 5DQCh. 9 - Prob. 6DQCh. 9 - Prob. 7DQCh. 9 - Prob. 8DQCh. 9 - What are the requirements for a focused work...Ch. 9 - Prob. 10DQ
Ch. 9 - Prob. 11DQCh. 9 - Prob. 12DQCh. 9 - Prob. 13DQCh. 9 - Prob. 14DQCh. 9 - Prob. 15DQCh. 9 - Prob. 16DQCh. 9 - Explain the concept of cross-docking.Ch. 9 - What is a heuristic? Name several that can be used...Ch. 9 - Prob. 1PCh. 9 - Prob. 2PCh. 9 - Three departmentsmilling (M), drilling (D), and...Ch. 9 - Roy Creasey Enterprises, a machine shop, is...Ch. 9 - Prob. 5PCh. 9 - Prob. 6PCh. 9 - Prob. 7PCh. 9 - Prob. 8PCh. 9 - Six processes are to be laid out in six areas...Ch. 9 - After an extensive product analysis using group...Ch. 9 - Stanford Rosenberg Computing wants to establish an...Ch. 9 - Illinois Furniture, Inc., produces all types of...Ch. 9 - Sue Helms Appliances wants to establish an...Ch. 9 - The Action Toy Company has decided to manufacture...Ch. 9 - The following table details the tasks required for...Ch. 9 - Tailwind, Inc., produces high-quality but...Ch. 9 - Prob. 18PCh. 9 - Because of the expected high demand for Mach 10,...Ch. 9 - Prob. 20PCh. 9 - Suppose production requirements in Solved Problem...Ch. 9 - The preinduction physical examination given by the...Ch. 9 - Samuel Smith's company wants to establish an...Ch. 9 - As the Cottrell Bicycle Co. of St. Louis completes...Ch. 9 - Prob. 1CSCh. 9 - Prob. 2CSCh. 9 - Prob. 3CSCh. 9 - Prob. 4CSCh. 9 - Prob. 1.1VCCh. 9 - Prob. 1.2VCCh. 9 - Prob. 1.3VCCh. 9 - Prob. 1.4VCCh. 9 - Prob. 1.5VCCh. 9 - Prob. 1.6VCCh. 9 - Prob. 2.1VCCh. 9 - Prob. 2.2VCCh. 9 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Please view the following and answerarrow_forward*see the attached problem and requiredarrow_forwardThe City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: Code A B с D E F G H I Description Find location; determine resource requirements Requisition of lumber and sand Dig and grade Saw lumber into appropriate sizes Position lumber in correct locations Time (hrs) 20 60 100 30 20 10 20 10 30 Nail lumber together Put sand in and under the equipment Put dirt around the equipment Put grass all over the garden, landscape, paint Refer to the legend for the activity that corresponds to each code. Using the line drawing tool, draw a Gantt chart for activites E through I of the project. Immediate Predecessor(s) None A A B D, C E F F G, H A B C- D- E F G H- H 0 20 40 60 80 100 120 140 160 180 200 Q ✔arrow_forward
- Sue Helms Appliances wants to establish an assem-bly line to manufacture its new product, the Micro Popcorn Popper. The goal is to produce five poppers per hour. The tasks,task times, and immediate predecessors for producing one MicroPopcorn Popper are as follows:TASK TIME (min) IMMEDIATEPREDECESSORSA 10 —B 12 AC 8 A, BD 6 B, CE 6 CF 6 D, Ea) What is the theoretical minimum for the smallest number ofworkstations that Helms can achieve in this assembly line?b) Graph the assembly line, and assign workers to workstations.Can you assign them with the theoretical minimum?c) What is the efficiency of your assignment?arrow_forwardA company is setting up an assembly line to produce 90 units per hour. The table below identifies the work elements, times, and immediate predecessors. Work Element Time (Sec.) Immediate Predecessor(s) A 25 - B 18 A C 20 A D 5 B, C E 12 C F 8 E G 16 D, F H 12 G What cycle time is required to satisfy the required output? What is the theoretical minimum number of stations?arrow_forwardKiko Teddy Bear is a manufacturer of stuffed teddy bears. Kiko would like to be able to produce 40teddy bears per hour on its assembly line. The following information will assist in answering thequestions that follow: Task Information for Kiko Teddy Bear Work Element Task Description ImmediatePredecessor Task Time (inseconds)A Cut teddy bear pattern None 90B Sew teddy bear cloth A 75C Stuff teddy bear B 50D Glue on eyes C 20E Glue on nose C…arrow_forward
- Kiko Teddy Bear is a manufacturer of stuffed teddy bears. Kiko would like to be able to produce 40teddy bears per hour on its assembly line. The following information will assist in answering thequestions that follow: Task Information for Kiko Teddy Bear Work Element Task Description ImmediatePredecessor Task Time (inseconds)A Cut teddy bear pattern None 90B Sew teddy bear cloth A 75C Stuff teddy bear B 50D Glue on eyes C 20E Glue on nose C…arrow_forward7.14. The Henry Street Mission uses volunteers to assemble care packages for needy families during the holiday season. The mis- slon would like to organize the work as efficiently as possible. A list of tasks, task times, and precedence requirements follows: Task Precedence Time (Mins) A B A B. 7. D. C, D 4 a. If the mission wants to complete a care package every 10 min- utes, how many volunteers should be called in? Balance the line and calculate the efficiency. How many packages can be assem- bled in a four-hour period? b. Suppose that volunteers are plentiful. Balance the line to max- imize output. What is the efficiency of the line? How many care packages can be assembled in a four-hour period?arrow_forwardThe Henry Street Mission uses volunteers to assemble carepackages for needy families during the holiday season. Themission would like to organize the work as efficiently as possible. A list of tasks, task times, and precedence re-quirements follows: a. If the mission wants to complete a care package every10 minutes, how many volunteers should be called in?Balance the line and calculate the efficiency. How manypackages can be assembled in a four-hour period?b. Suppose that volunteers are plentiful. Balance the lineto maximize output. What is the efficiency of the line? How many care packages can be assembled in a four-hour period?arrow_forward
- Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows: Task Time (sec) ABCDE 24842 12 14 20 Immediate Predecessor A A B, C D Rosenberg's goal is to produce 170 PDAs per hour. a) The cycle time for the production of a PDA = seconds (round your response to two decimal places).arrow_forwardManagement wants to design an assembly line that will turn out 800videotapes per day. There will be eight working hours in each day. The industrial engineeringstaff has assembled the information below: Task Time (min.) Immediate Follower a .2 b,d b .2 f c .4 b,e d .1 e e .3 f f .2 h g .1 h h .2 i i .6 none A) Determine the optimum cycle time (i.e., actual operating time/desired output).B) What is the minimum number of stations needed?C) Assign tasks to work stations.D) What is the efficiency of this assembly line?arrow_forwardThe City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: A- Time B- Code Description (hrs) Immediate Predecessor(s) C- A Find location; determine resource requirements 25 None Requisition of lumber and sand Dig and grade Saw lumber into appropriate sizes 55 A D- C 100 A E- 30 В E Position lumber in correct locations 20 D, C F- F Nail lumber together 10 E G- Put sand in and under the equipment Put dirt around the equipment G 25 F H F H- Put grass all over the garden, landscape, paint 35 G, H Refer to the legend for the activity that corresponds to each code. Using the line drawing tool, draw a Gantt chart for activities E through I of the project. 20 40 60 80 100 120 140 160 180 200 220arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY