Chapter 9, Problem 18P
a)
Summary Introduction
To draw: The precedence diagram.
b)
Summary Introduction
To calculate: The efficiency.
c)
Summary Introduction
To calculate: The theoretical minimum number of workstations.
d)
Summary Introduction
To calculate: The idle time per boat.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A dress-making operation is being designed as an assemblyline. Table 10-22 shows the tasks that need to be performed, theirtask times, and preceding tasks. If the goal is to produce 30 dressesper hour, answer the questions that follow the table.
(a) Compute the cycle time.(b) Which task is the bottleneck?(c) What is the maximum output for this line?(d) Compute the theoretical minimum number of stations.(e) Assign work elements to stations, using the longest tasktime rule.(f) Compute the effi ciency and balance delay of yourassignment.
Management wants to design an assembly line that will turn out 800 videotapes per day. There will be eight working hours in each day. The industrial engineering staff has assembled the information below: A) Determine the maximum and minimum cycle times.B) Determine the optimum cycle time.C) What is the minimum number of stations needed?D) Draw the precedence diagram.E) Assign tasks to stations in order of most following tasks first. Submit an Excel file based on Chapter 6 Excel Template to indicate your computation.
The Mach 10 is a one-person sailboat manufactured by Creative Leisure. The final assembly plant is in Cupertino, California. The assembly area is available for production of theMach 10 for 200 minutes per day. (The rest of the time it is busy making other products.) The daily demand is 60 boats. Given the information in the table on the next page,a) Draw the precedence diagram and assign tasks using five workstations .b) What is the efficiency of the assembly line, using your answer to (a)?c) What is the theoretical minimum number of workstations?d) What is the idle time per boat produced?
Chapter 9 Solutions
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Ch. 9 - Prob. 1DQCh. 9 - Prob. 2DQCh. 9 - Prob. 3DQCh. 9 - Prob. 4DQCh. 9 - Prob. 5DQCh. 9 - Prob. 6DQCh. 9 - Prob. 7DQCh. 9 - Prob. 8DQCh. 9 - What are the requirements for a focused work...Ch. 9 - Prob. 10DQ
Ch. 9 - Prob. 11DQCh. 9 - Prob. 12DQCh. 9 - Prob. 13DQCh. 9 - Prob. 14DQCh. 9 - Prob. 15DQCh. 9 - Prob. 16DQCh. 9 - Explain the concept of cross-docking.Ch. 9 - What is a heuristic? Name several that can be used...Ch. 9 - Prob. 1PCh. 9 - Prob. 2PCh. 9 - Three departmentsmilling (M), drilling (D), and...Ch. 9 - Roy Creasey Enterprises, a machine shop, is...Ch. 9 - Prob. 5PCh. 9 - Prob. 6PCh. 9 - Prob. 7PCh. 9 - Prob. 8PCh. 9 - Six processes are to be laid out in six areas...Ch. 9 - After an extensive product analysis using group...Ch. 9 - Stanford Rosenberg Computing wants to establish an...Ch. 9 - Illinois Furniture, Inc., produces all types of...Ch. 9 - Sue Helms Appliances wants to establish an...Ch. 9 - The Action Toy Company has decided to manufacture...Ch. 9 - The following table details the tasks required for...Ch. 9 - Tailwind, Inc., produces high-quality but...Ch. 9 - Prob. 18PCh. 9 - Because of the expected high demand for Mach 10,...Ch. 9 - Prob. 20PCh. 9 - Suppose production requirements in Solved Problem...Ch. 9 - The preinduction physical examination given by the...Ch. 9 - Samuel Smith's company wants to establish an...Ch. 9 - As the Cottrell Bicycle Co. of St. Louis completes...Ch. 9 - Prob. 1CSCh. 9 - Prob. 2CSCh. 9 - Prob. 3CSCh. 9 - Prob. 4CSCh. 9 - Prob. 1.1VCCh. 9 - Prob. 1.2VCCh. 9 - Prob. 1.3VCCh. 9 - Prob. 1.4VCCh. 9 - Prob. 1.5VCCh. 9 - Prob. 1.6VCCh. 9 - Prob. 2.1VCCh. 9 - Prob. 2.2VCCh. 9 - Prob. 2.3VC
Knowledge Booster
Similar questions
- The following is a list of activities that must be completed in order to assemble a car. Draw the precedence diagram. Calculate the cycle time if there5 are 8 hours in a workday and 800 units desired per day. Balance the line using the longest operation time as a selection rule. Calculate the efficiency rating. How much overtime would be needed for an additional 20 units? Is this possible? Task Time Feasible TASK TIME PRECEDING Station Task Time Remaining Tasks TASK (Seconds) TASK A 16 ----- B 14 ----- C 22 ----- D…arrow_forwardThe Mach 10 is a one-person sailboat manufactured by Creative Leisure. The final assembly plant is in Cupertino, California. The assembly area is available for production of the Mach 10 for 200 minutes per day. (The rest of the time it is busy making other products.) The daily demand is 60 boats. Given the information in the table, Draw the precedence diagram and assign tasks. a. Based on "longest operating time", what station should task E be assigned to? [Select] : b. What is the efficiency and idle time of the assembly line, based on the actual grouping and cycle time? [Select] c. What is the theoretical minimum number of workstations? 5 If so, what is d. Is there an ability to improve the cycle time? [Select] the cycle time, efficiency, and idle time? [Select]arrow_forwardIn order of most following tasks. Tiebreaker: greatest positional weight. (Use your rounded cycle time. Enter your tasks in the order they were assigned at each station as a letter between a and h in lowercase with no other text or symbols. Round your numerical answers to 1 decimal place.) X Answer is complete but not entirely correct. Work Time Task Task Time Station Remaining A 1.7 0.0 X II В 0.8 1.2 E 0.8 0.4 II 0.7 1.3 0.5 0.8 F 0.8 0.0 IV 0.9 1.1 H 0.5 0.6 What is Efficiency? (Use your rounded cycle time in the denominator of your efficiency calculation. Round your answer to 1 decimal place.) X Answer is not complete. Efficiencyarrow_forward
- ANSWER ONLY 9.19arrow_forwardPlease provide answers in sentences for this question. Thanks!arrow_forwardPositively Rivet Inc. is a small machine shop that produces sheet metal products. It had one line dedicated to the manufacture of light-duty vent hood shells, but because of strong demand it recently added a second line. The new line makes use of higher-capacity automated equipment but consists of the same basic four processes as the old line. In addition, the new line makes use of one machine per workstation, while the old line has parallel machines at the workstations. The processes, along with their machine rates, number of machines per station, and average times for a lone job to go through a station (i.e., not including queue time), are given for each line in the following table: Process Old Line New Line Rate per Machine (parts/hour) # Machines per Station Time (minute) Rate per Machine (parts/hour) # Machines per Station Time (minute) Punching 15 4 4.0 120 1 0.50 Braking 12 4 5.0 120 1 0.50 Assembly 20 2 3.0 125…arrow_forward
- Using the information below answer the following questionsa) What is the bottleneck in the process – show your work by demonstrating the workloadby product and station.b) Using the traditional (margin) based model what is the order of priority of the 4 products,and how many of each can they produce BY MONTH. Show your math for determiningthe order of priority and for determining the number of unitsc) Using the bottle keck based model what is the order of priority of the 4 products, andhow many of each can they produce BY MONTH. Show your math for determining theorder of priority and for determining the number of unitsd) What is the profit using the traditional method – show your mathe) What is the profit using the bottleneck method – show your mathThe factory runs one 8-hour shift per day per station, operates five days a week. The skilledemployees get paid $25 / hour. In addition, the factory has a weekly overhead of $2000. Due touncertainty in the demand planning, management has…arrow_forwardGiven the following task, times, and sequence, develop a balanced line capable of operating with a I 0-minute cycle time at Dave Visser's company. a) Draw the precedence diagram.b) Assign tasks to the minimum feasible number of workstations according to the greatest time remaining (ranked positional weight) decision rule.c) What is the efficiency of the process?arrow_forwardHi! I need a little help with D. I can't figure out how to calculate the efficiency. Can you explain it to me?arrow_forward
- Please provide answers in sentences. Thanks in advance!arrow_forwardcan answer thisarrow_forwardgiven information: which step is in bottleneck=30 min for tan leather 60/30=2 briefcases per hr are processed at the bottleneck workstation per hour throughput time of the overall process Throughput = 75 minutes PLEASE answer the following 3 questions: If the manufacturing facility operates 8 hours per day, 250 days a year, what is the annual capacity of this manufacturing process. Assume the company decides to hire additional workers in order to duplicate the bottleneck step identified in part a so that there are 3 of these workstations instead of 1. Redraw the diagram showing the flow of the revised process. Answer parts a through d again based on the new process created in part e?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.