Question
Book Icon
Chapter 9, Problem 2.3VC
Summary Introduction

Case summary:

WC company is the worlds largest manufactuer of ambulances had only a handful of employees while beginning. It is like many other companies did not build the manufacturing plant from scratch.

Since the plant is not built from scratch there are some issues where too many employees are running into each other in the assembly line. It has become increasingly difficult to finish an ambulance in seven days.

To measure: The efficiency of this layout.

Blurred answer
Students have asked these similar questions
QUESTION #3 Smith's Tourism company has recently expanded from four to six departments. Over the past month the six departments have the following trip matrix and current block plan of all departments: Closeness Factor Dept. Name A 7 C E 2 3 10 12 3 6. %3D A B C E a. What is the weighted distance score for the current layout? (Assume rectilinear distance and that the distance between departments A and B is one unit of distance.) b. What would be the weighted distance score for the following layout? CE A D B c. Which plan should Smith's company choose and why? Focus ABCD EF
(Layout Strategies) A steel workshop wants to improve its productivity by making small metal hooks by changing the layout of the workshop into a workstation. The workshop has made observations on the activities of its workers in the workshop and arranged these activities in the form of the table below. Activities Duration (in seconds) Predecessor A 17 None B 15 A C 18 B D 8 B E 12 B F 6 C,D,E G 14 F   The workshop aims to produce 225 small metal hooks for 2 hours. Based on this information, please answer the questions below. Sketch a precedence diagram of the above activity  Calculate cycle time and the minimum number of workstations to be made  Make a grouping of the workstations  Calculate the efficiency of the work with the workstation
need answer asap

Chapter 9 Solutions

Operations Management: Sustainability and Supply Chain Management (12th Edition)

Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.