Question
Chapter 7, Problem 6P
a)
Summary Introduction
To determine: The number of Kanban containers required.
Introduction:
Lean systems in an organization would have greater impact on the customers and their values. The goal of lean thinking is to improve the productivity of the department, and the goal for any lean system is to maximize the customer’s value.
b)
Summary Introduction
To determine: The number of Kanban containers required.
Introduction:
Lean systems in an organization would have greater impact on the customers and their values. The goal of lean thinking is to improve the productivity of the department, and the goal for any lean system is to maximize the customer’s value.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A company is in the business of machining parts that go through various work centers. Suppose work center A feeds work center B with parts. The following times (in minutes) are given for each work center. A standard kanban container holds 50 parts that are transferred from work center A to work center B. The demand rate at work center B is four parts per minute. a. How many kanban containers are needed for this situation? b. If move time is cut in half, what does this do to the number of containers needed? How much will this change reduce inventory?
3
What is OEE and also calculate the OEE from the given data in below table
Items
Data
Shift Length
8 Hours
Breaks
(2) 15 minute and (1) 30 minute
Downtime
47 minutes
ideal Cycle Time
1.0 seconds
Total Count
19,271 widgets
Reject Count
423 widgets
Chapter 7 Solutions
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Lead Time Gourmet Helper Appliance Company manufactures home kitchen appliances. The manufacturing process includes stamping, final assembly, testing and shipping. In the stamping operation, a number of individuals are responsible for stamping the steel outer surface of the appliance. The stamping operation is set up prior to each run. A run of 75 stamping is completed after each setup. A setup requires 40 minutes the parts wait for the setup to be completed before stamping begins. Each stamping requires 5 minutes of operating time. After each batch is completed, the operator moves stamp the stamped covers to the final assembly area. This move takes 10 minutes to complete. The final assembly for each appliance unit requires 18 minutes and is also done in batches of 75 appliance units. The batch of 75 appliance units is moved into the test building, which is crossed street. The move takes 25 minutes. In the final test, the 75 unit batch is tested one at a time. Each test…arrow_forward4arrow_forwardAnswers letters f and garrow_forward
- Jason Carter works for a producer of soaps that come inpackages of 6 each. His job is to fi ll the packages with soap, andhe is expected to process 30 packages an hour. Th e facility whereJason works uses a kanban production system in which eachcontainer holds 5 packages of soap. It takes 20 minutes to receivethe packages he needs from the previous workstation. How manykanbans are needed for the fi lling process?arrow_forward. Kinga Doll Company manufactures eight versions of its popular girl doll, Shari. Thecompany operates on a 40-hour workweek. The eight versions differ in doll skin, hair,and eye color, enabling most children to have a doll with a similar appearance to them.It currently sells an average of 4000 dolls (spread equally among its eight versions) perweek to boutique toy retailers. In simplified terms, doll making at Kinga involves threebasic operations: molding the body and hair, painting the face, and dressing the doll.Changing over between versions requires setup time at the molding and painting stationsdue to the different colors of plastic pellets, hair, and eye color paint required. Table 7.5lists the setup times for a batch and the activity times for each unit at each step.a. What is the process capacity in dolls per hour with a batch size of 500 dolls? b. What is the utilization of molding in dolls per hour with a batch size of 800 dolls? c. Which batch size would minimize inventory…arrow_forwardtrue or false- Five different products on a pallet being moved, is equal to one unit load.arrow_forward
- New Mode Y Delay A Yost-Perry Industries (YPI) manufactures a mix of affordable guitars (A, B, C) that are fabricated and assembled at four different processing stations (W, X, Y, Z). The operation is a batch process with small setup times that can be considered negligible. The product information (price, weekly demand, and processing times) and process sequences are shown below. Purchased parts and raw materials (shown as a per-unit consumption rate) are represented by inverted triangles. YPI is able to make and sell up to the limit of its demand per week with no penalties incurred for not meeting the full demand. Each workstation is staffed by one highly skilled worker who is dedicated to work on that workstation alone and is paid $15 per hour. The plant operates one 8-hour shift per day and operates on a 5-day work week (i.e., 40 hours of production per person per week). Overhead costs are $9,000/week. Q Q Product A $11 Q Step 1 Station W (12 min) Step 2 Station Z (13 min) Purchased…arrow_forward(Setup Everywhere) Consider the following batch-flow process consisting of three process steps performed by three machines. Process Step Step 1 Step 2 Step 3 Processing Time 0.25min./unit 0.20 min./unit 0.15 min./unit Setup time 30 min 20 min 45 min Work is processed in batches at each step. Before a batch is processed at a step, the machine at that step must be set up. (During a setup, the machine is unable to process any product.) Assume that there is a dedicated setup operator for each machine (i.e., there is always someone available to perform a setup at each machine.) a. What is the capacity of step 1 if the batch size is 35 parts? b. For what batch sizes is step 1 (2, 3) the bottleneck?arrow_forwardSawing 20 min/unit Sanding 20 min/unit Drilling 32 min/unit Welding 30 min/unit Assembly 93 min/unit Assembly 93 min/unit Assembly 93 min/unit A production process is shown in the figure above. The drilling operation occurs separately from, and simultaneously with the sawing and sanding operations. Welding starts when both drilling and sanding operations have been completed. After welding, a product needs to go through only one of the three assembly operations (the operations are in parallel, where parallel lines perform the exact same operation). Considering the process times at stations, what is the process time of the system (in min/unit)?arrow_forward
- An assembly line has 10 stations with times of 1, 2, 3, 4, 10, respectively. What is the bottleneck time? OA. 1.82% of the throughput time OB. 18.18% of the throughput time OC. 100% of the throughput time OD. 550% of the throughput time OE. 50% of the throughput time چارarrow_forwardA production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). 7 units/hr 5 units/hr Assembly 0.8 units/hr Sawing Sanding Welding Assembly 2.1 units/hr 0.8 units/hr Drilling 2.5 units/hr Assembly 0.8 units/hr a) is the bottleneck. b) The bottleneck time is minutes per unit (round your response to two decimal places). c) The throughput time of the overall system is minutes (round your response to two decimal places).arrow_forwardAmy Xia's p lant was designed to produce 7,000 hammers per day but is limited to making 6,000 hammers per day because of the time needed to change equipment betweenstyles of hammers. What is the utilization?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.