OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
7th Edition
ISBN: 9780077835439
Author: Roger G Schroeder, M. Johnny Rungtusanatham, Susan Meyer Goldstein
Publisher: McGraw-Hill Education
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 7, Problem 5P
Suppose a work center has a setup plus run time of 30 minutes to make 50 parts. Also assume it takes 10 minutes to move a standard container of 50 parts to the next work center and the demand rate is one part per minute throughout the day.
- a.
Schedule this situation by drawing a picture of when work center A should be producing and idle and when movements of containers take place from A to B, the using work center. - b. How many standard containers are needed for this part to circulate from the picture in part a?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Suppose a work center has a setup plus run time of 30 minutes to make 50 parts. Also assume it takes 10 minutes to move a standard container of 50 parts to the next work center and the demand rate is one part per minute throughout the day.a. Schedule this situation by drawing a picture of when work center A should be producing and idle and when movements of containers take place from A to B, the using work center.b. How many standard containers are needed for this part to circulate from the picture in part a?c. Use the formula n = DT ÷ C to calculate the number of containers.
XYZ is famous for homemade pizzas which are crisp with thin crust and varied toppings giving the pizzas fabulous tastes. XYZ· is revamping its order processing and pizza-making process. In order to deliver fresh pizza fast, six work elements must be completed as shown in the table below :Element Description Precedence Time (in min)A Receive order - 2·0B Shape dough A 1·0C Prepare toppings A 2·0D Assemble pizza B, C 3·0E Bake pizza D 3·0F Deliver pizza E 3·0Construct a precedence diagram for the process.If the demand is 120 pizzas per night (5:00pm to 1:00am), compute the cycle time for the process. Compute the lead time for the process.What is the theoretical minimum number of workstations needed to achieve the required production?How will you balance the production line to produce and deliver 120 pizzas per night? What is the actual minimum number of workstations needed?
Judy’s Cake Shop makes fresh cakes to customer orders. After receiving the order by Judy’s assistant, which takes 2 minutes, Judy then takes 8 minutes tomix the ingredients for the cake and loads a cake pan for baking. Then the cake is put into the oven for 30 minutes. The oven can hold three cakes at one time. When the cake is taken out of the oven, it is cooled for 1 hour. The assistant then takes 2 minutes to pack the cake for pickup and bills the customer, which takes 3 minutes.a. What is the capacity of the process, and what is the bottleneck?b. What is the throughput time for a typical cake?c. If on average five orders are taken per hour, how many cakes are there in the process (on average)?
Chapter 7 Solutions
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- 1arrow_forwardNew Mode Y Delay A Yost-Perry Industries (YPI) manufactures a mix of affordable guitars (A, B, C) that are fabricated and assembled at four different processing stations (W, X, Y, Z). The operation is a batch process with small setup times that can be considered negligible. The product information (price, weekly demand, and processing times) and process sequences are shown below. Purchased parts and raw materials (shown as a per-unit consumption rate) are represented by inverted triangles. YPI is able to make and sell up to the limit of its demand per week with no penalties incurred for not meeting the full demand. Each workstation is staffed by one highly skilled worker who is dedicated to work on that workstation alone and is paid $15 per hour. The plant operates one 8-hour shift per day and operates on a 5-day work week (i.e., 40 hours of production per person per week). Overhead costs are $9,000/week. Q Q Product A $11 Q Step 1 Station W (12 min) Step 2 Station Z (13 min) Purchased…arrow_forwardThe Assembly Department started the month with 37,000 units in its beginning work in process inventory. An additional units 482,000 were transferred in from the prior department during the month to begin processing in the Assembly Department. There were 34,000 units in the ending work in process inventory of the Assembly Department. How many units were transferred to the next processing department during the month? A. none of the options B. 485,000 C. 473,000 D. 479,000arrow_forward
- Up, Up, and Away is a producer of kites and wind socks.Relevant data on a bottleneck operation in the shop for theupcoming fiscal year are given in the following table:Item Kites Wind SocksDemand forecast 30,000 units/year 12,000 units/yearLot size 20 units 70 unitsStandard processing time 0.3 hour/unit 1.0 hour/unitStandard setup time 3.0 hours/lot 4.0 hours/lotThe shop works two shifts per day, 8 hours per shift, 200 daysper year. Currently, the company operates four machines,and desires a 25 percent capacity cushion. How many ma-chines should be purchased to meet the upcoming year’s de-mand without resorting to any short-term capacity solutions?arrow_forwardA metal fabrication shop has a single punch press. There are currently three partsthat the shop has agreed to produce that require the press, and it appears that theywill be supplying these parts well into the future. You may assume that the press isthe critical resource for these parts, so that we need not worry about the interactionof the press with the other machines in the shop. The relevant information here is: Part Number Demand/year Set up Cost ($) Cost per Unit ($) Production rate/year 1 2,500 80 16 45,000 2 5,500 120 18 40,000 3 1,450 60 22 26,000 Holding costs are based on an 18 percent annual interest rate, and the products are to be produced in sequence on a rotation cycle. Setup times can be considered negligible. What is the optimal lot size of part 2?arrow_forwardTrue or False: "Bottleneck refers to a stage in a process that limits the capacity of the entire system to produce more."arrow_forward
- What is OEE and also calculate the OEE from the given data in below table. Item Data Shift Length 8 hours Breaks (2) 15 minute and (1) 30 minute Downtime 47 minutes Ideal Cycle Time 1.0 seconds Total Count 19,271 widgets Reject Count 423 widgetsarrow_forwardC&A Furniture uses a four-step process to make its famous wood table: Processing Time Process Milling Table top Milling Table stand Assembly Finishing The milling machine requires a setup time of 30 minutes to make table tops and a changeover time of 30 minutes to make table stands. If the batch size is 10, what is the capacity of the process in tables per minute? A) 0.077 B) 0.05 C) 0.067 10 5 15 20 D) 0.048arrow_forward3. At Golf Co. product is automated to load golf balls into packaging. On an average day, the equipmentcan load 25 cases per hour, where each case contains 20 boxes and each box contains 12 balls.After maintenance, the machine is loading a little faster so that it takes 0.2 seconds less time to load onegolf ball into a box compared with the normal speed.How many cases per hour can the machine load at this new rate?arrow_forward
- Up, Up, and Away is a producer of kites and wind socks. Relevant data on the bottleneck operation in the shop for the upcoming fiscal year are given in the following table Wind Socks 10,000 units/year Item Demand forecast Lot size Standard processing time Standard setup time Kites 32,000 units/year 25 units 0.4 hourlunit 3.0 hours/lot 70 units 0.8 hour/unit 40 hours/fol The shop works two shifts per day, 8 hours per shift, 210 days per year. Currently, the company operates four machines, and desires a 25 percent capacity cushion. How many machines should be purchased to meet the upcoming year's demand without resorting to any short-term capacity solutions? The number of additional machines required is (Enter your response rounded up to the next whole number)arrow_forwardA production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). Q a) is the bottleneck. 6 units/hr Sawing 2.4 units/hr Sanding Drilling 2 units/hr Welding 5 units/hr Assembly 0.7 units/hr Assembly 0.7 units/hr Assembly 0.7 units/hr OUarrow_forwardYost-Perry Industries (YPI) manufactures a mix of affordable guitars (A, B, C) that are fabricated and assembled at four different processing stations (W, X, Y, Z). The operation is a batch process with small setup times that can be considered negligible. The product information (price, weekly demand, and processing times) and process sequences are shown in Figure. Raw materials and purchased parts (shown as a per-unit consumption rate) are represented by inverted triangles. YPI is able to make and sell up to the limit of its demand per week with no penalties incurred for not meeting the full demand. Each workstation is staffed by one highly skilled worker who is dedicated to work on that workstation alone and is paid $15 per hour. The plant operates one 8-hour shift per day and operates on a 5-day work week (i.e., 40 hours of production per person per week). Overhead costs are $9,000/week. Which of the four workstations, W, X, Y, or Z, has the highest aggregate workload, and thus…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY