The following table lists the components needed to assemble an end item, lead times, and quantities on hand. Item LT (week) End 1 B C D E G H 3 1 1 1 1 1 Amount on hand 7 12 22 8 26 3 Click here for the Excel Data File B(2) End Item D (3) AIA E (2) F (3) G (2) E (2) H (4) E (2) a. If 17 units of the end item are to be assembled, how many additional units of E are needed? (Hint. You don't need to develop an MRP plan to determine this.) Additional units b. An order for the end item is scheduled to be shipped at the start of week 12. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don't need to develop an MRP plan for this part either.)

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
Question
not use ai please
The following table lists the components needed to assemble an end item, lead times, and quantities on hand.
Item
LT (week)
End
1
B
C
D
E
G
H
3
1
1
1
1
1
Amount on hand
7
12
22
8
26
3
Click here for the Excel Data File
B(2)
End Item
D (3)
AIA
E (2) F (3) G (2) E (2) H (4)
E (2)
a. If 17 units of the end item are to be assembled, how many additional units of E are needed? (Hint. You don't need to develop an MRP
plan to determine this.)
Additional units
b. An order for the end item is scheduled to be shipped at the start of week 12. What is the latest week that the order can be started
and still be ready to ship on time? (Hint: You don't need to develop an MRP plan for this part either.)
Transcribed Image Text:The following table lists the components needed to assemble an end item, lead times, and quantities on hand. Item LT (week) End 1 B C D E G H 3 1 1 1 1 1 Amount on hand 7 12 22 8 26 3 Click here for the Excel Data File B(2) End Item D (3) AIA E (2) F (3) G (2) E (2) H (4) E (2) a. If 17 units of the end item are to be assembled, how many additional units of E are needed? (Hint. You don't need to develop an MRP plan to determine this.) Additional units b. An order for the end item is scheduled to be shipped at the start of week 12. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don't need to develop an MRP plan for this part either.)
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Marketing
Marketing
Marketing
ISBN:
9780357033791
Author:
Pride, William M
Publisher:
South Western Educational Publishing
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Contemporary Marketing
Contemporary Marketing
Marketing
ISBN:
9780357033777
Author:
Louis E. Boone, David L. Kurtz
Publisher:
Cengage Learning
MARKETING 2018
MARKETING 2018
Marketing
ISBN:
9780357033753
Author:
Pride
Publisher:
CENGAGE L