A furniture factory makes two types of wooden tables, large and small. See the flowchart below.
Setup Time, Minutes | Run Time per Piece, Minutes | Capacity, Pieces per Hour | |
Wood cutting | 30 | 5 | 15 |
Male four legs | 60 | 10 | 10 |
Male tops | 60 | 12 | 8 |
Finish the wood | 20 | 8 | 12 |
Assemble and ship | 20 | 17 | 14 |
Small tables are made in batches of 100, and large tables are made in batches of 50. A batch includes a fixed setup time for the entire batch at each process step and a run time for each piece in the batch. Both large and small tables have the same processing times. The capacities of each process step are given, and apply to production of either type of table, as shown in the flowchart.
- a. What is the capacity of the system, and what is the bottleneck?
- b. What are the throughput times for batches of large and small tables?
- c. When producing at a rate of six small tables per hour on average, how many tables will be in the system?
a)

To determine: The capacity of the process.
Introduction:
Flow rate is the number of flow units through a business procedure per unit time. Flow rate refers to the number of customers who will be served per hour or the parts produced per minute.
Explanation of Solution
Given information:
A furniture factory makes large and small wooden tables. The given information is tabulated below:
Setup time (Minutes) | Run time per piece (Minutes) | Capacity (Pieces per hour) | |
Wood cutting | 30 | 5 | 15 |
Make four legs | 60 | 10 | 10 |
Make tops | 60 | 12 | 8 |
Finish the wood | 20 | 8 | 12 |
Assemble and ship | 20 | 17 | 14 |
Small wooden tables are finished in batches of 100 and large wooden tables are finished in the batches of 50. A batch includes fixed setup time and run time. Both small tables and large tables have the same processing time.
Determine the capacity:
As both large wooden table and small wooden table have same capacities, the capacity of the system is minimum of the capacity of the resources. The minimum capacity resource is 8 tables per hour and the process is making tops.
Setup time (Minutes) | Run time per piece (Minutes) | Capacity (Pieces per hour) | |
Wood cutting | 30 | 5 | 15 |
Make four legs | 60 | 10 | 10 |
Make tops | 60 | 12 | 8 |
Finish the wood | 20 | 8 | 12 |
Assemble and ship | 20 | 17 | 14 |
b)

To determine: The average throughput time.
Introduction:
Flow rate is the number of flow units through a business procedure per unit time. Flow rate refers to the number of customers who will be served per hour or the parts produced per minute.
Explanation of Solution
Given information:
A furniture factory makes large and small wooden tables. The given information is tabulated below:
Setup time (Minutes) | Run time per piece (Minutes) | Capacity (Pieces per hour) | |
Wood cutting | 30 | 5 | 15 |
Make four legs | 60 | 10 | 10 |
Make tops | 60 | 12 | 8 |
Finish the wood | 20 | 8 | 12 |
Assemble and ship | 20 | 17 | 14 |
Small wooden tables are finished in the batches of 100 and large wooden tables are finished in the batches of 50. A batch includes fixed setup time and run time. Both small tables and large tables have the same processing time.
Determine the average throughput time:
Small tables | Large tables | |
Batch size | 100 | 50 |
Wood cutting | 530 | 280 |
Make four legs | 1,060 | 560 |
Make tops | 1,260 | 660 |
Finish the wood | 820 | 420 |
Assemble and ship | 1,720 | 870 |
Total time | 4,330 | 2,230 |
Hence, the average throughput time for small tables is 4,330 minutes and the average throughput time for large tables is 2,230 minutes.
Working note:
Wood cutting for small tables:
It is calculated by adding the setup time to the multiplied value of run time and batch size.
Wood cutting for large tables:
It is calculated by adding the setup time to the multiplied value of run time and batch size.
Note: The calculation is carried out for all the processes.
Compute the throughput time for small tables:
While adding the time taken, the maximum amount should be chosen from the process of making four legs and tops, as they can be done in parallel.
Compute the throughput time for large tables:
While adding the time taken, the maximum amount should be chosen from the process of making four legs and tops, as they can be done in parallel.
c)

To determine: The number of tables in the system.
Introduction:
Flow rate is the number of flow units through a business procedure per unit time. Flow rate refers to the number of customers who will be served per hour or the parts produced per minute.
Explanation of Solution
Given information:
A furniture factory makes large and small wooden tables. The given information is tabulated below:
Setup time (Minutes) | Run time per piece (Minutes) | Capacity (Pieces per hour) | |
Wood cutting | 30 | 5 | 15 |
Make four legs | 60 | 10 | 10 |
Make tops | 60 | 12 | 8 |
Finish the wood | 20 | 8 | 12 |
Assemble and ship | 20 | 17 | 14 |
Small wooden tables are finished in the batches of 100 and large wooden tables are finished in the batches of 50. A batch includes fixed setup time and run time. Both small tables and large tables have the same processing time. The factory is producing at the rate of six small tables per hour.
Formula to determine the average number of tables in the system:
Here
I refers to the number of orders in the systems.
T refers to the average throughout time.
R refers to the average flow rate in the process.
Determine the average number of tables in the system:
It calculated by multiplying the average throughput time with the average flow rate in the process.
Hence, the average number of tables in the system is 433 tables.
Want to see more full solutions like this?
Chapter 6 Solutions
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
- qusestion 6. An electrical engineering company is designing two types of solar panel systems: Standard Panels (S) and High-Efficiency Panels (H). The company has certain constraints regarding the hours of labor and material available for production each week. Each Standard Panel requires 4 hours of labor and 2 units of material and each High-Efficiency Panel requires 3 hours of labor and 5 units of material. The company has a maximum of 60 hours of labor and 40 units of material available per week. The profit from each Standard Panel is GH¢80, and the profit from each High-Efficiency Panel is GH¢100. The company wants to determine how many of each type of panel to produce in order to maximize profit. i. Formulate a linear programming model of the problem for the company. ii Convert the linear programming model formulated in (a) to a standard form.arrow_forwardG ווח >>> Mind Tap Cengage Learning 1- CENGAGE MINDTAP Chapter 09 Excel Activity: Exponential Smoothing Question 1 3.33/10 e Submit 自 A ng.cengage.com C Excel Online Student Work G A retail store records customer demand during each sales period. 1. What is the f... Q Search this course ? ✓ Co Excel Online Tutorial Excel Online Activity: Exponential Smoothing A-Z A retail store records customer demand during each sales period. The data has been collected in the Microsoft Excel Online file below. Use the Microsoft Excel Online file below to develop the single exponential smoothing forecast and answer the following questions. Office Video X Open spreadsheet Questions 1. What is the forecast for the 13th period based on the single exponential smoothing? Round your answer to two decimal places. 25.10 2. What is the MSE for the single exponential smoothing forecast? Round your answer to two decimal places. 21.88 Activity Frame ? 3. Choose the correct graph for the single exponential…arrow_forwardNot use ai pleasearrow_forward
- Items removed from the work area (5S) were taken to a storage area called ___________. Choose from: SORT, STORD, KNUJ, STUFF, FUDG SORT STORD KNUJ STUFF FUDGarrow_forwardCould you please help explain How was the poor strategic decisions lead to economic downturns of Circuit City Company? What are the sequences of key events and problems that contribute to its collapse. Could you please explain each one them and give the examples If Circuit City would apply Lean Six Sigma. would it helped prevent businesses from collapsed?? How Qualitative and quantitative Research Methodology in Case Study Research would affect Circuit City?arrow_forwardApple is a global technology company renowned for its innovation and design. To create its products, Apple has established a world class global supply chain to bring their products to market. What strategies is Apple using to source and manufacture its products? How does Apple view its responsibility to its suppliers and those who build its products?arrow_forward
- Critical Path Method (CPM) is an important Project Management Tool that has wide industry application in modern day Project Management. By using an example of the project of your choice, critically examine the practical application of CPM as a Project Management Tool.arrow_forwardwhat is an other difination for principle?arrow_forwardNeed help or ideas to design out two slides as my script and writing quite long to squeese into two slides. But can just point form in slides with correct title and a good script for me to present two slides in only 2.5 mins. Following is my draft, pls guide me step by step on powerpoint creation and good script to present findings. My draft: Slide 1: Foreign Labor Exploitation in Dyson's Supply Chain Introduction Dyson's former Malaysian supplier, ATA IMS Bhd, became embroiled in serious labor exploitation allegations in 2021. These concerns surfaced when whistleblowers exposed unethical labor practices affecting migrant workers, primarily from Nepal and Bangladesh. Key Forms of Exploitation Debt Bondage Due to Recruitment Fees Workers were forced to pay exorbitant recruitment fees before securing employment, often taking loans at high interest rates. This financial burden trapped them in debt bondage, leaving them with little choice but to accept exploitative working…arrow_forward
- Not use ai pleasearrow_forwardThe Business Development Bank of Canada. (2023). Canadian economic outlook for 2024: Shifting into neutral. https://www.bdc.ca/en/articles-tools/blog/canadian-economic-outlook-for-2024-shifting-into-neutral “Despite persistently high inflation and rising interest rates, the news was generally better than expected for the Canadian economy in 2023” (BDC Blog 2024). Discussion Question: In your view, what are the most pressing problems for Canadian companies or consumers in 2024? Explain your answer using current examples of companies or consumer concerns.arrow_forwardhow have idividual objectives led to the current situation at TeraCog? what should Emaa do?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,