A furniture factory makes two types of wooden tables, large and small. See the flowchart below.
Setup Time, Minutes | Run Time per Piece, Minutes | Capacity, Pieces per Hour | |
Wood cutting | 30 | 5 | 15 |
Male four legs | 60 | 10 | 10 |
Male tops | 60 | 12 | 8 |
Finish the wood | 20 | 8 | 12 |
Assemble and ship | 20 | 17 | 14 |
Small tables are made in batches of 100, and large tables are made in batches of 50. A batch includes a fixed setup time for the entire batch at each process step and a run time for each piece in the batch. Both large and small tables have the same processing times. The capacities of each process step are given, and apply to production of either type of table, as shown in the flowchart.
- a. What is the capacity of the system, and what is the bottleneck?
- b. What are the throughput times for batches of large and small tables?
- c. When producing at a rate of six small tables per hour on average, how many tables will be in the system?
a)
To determine: The capacity of the process.
Introduction:
Flow rate is the number of flow units through a business procedure per unit time. Flow rate refers to the number of customers who will be served per hour or the parts produced per minute.
Explanation of Solution
Given information:
A furniture factory makes large and small wooden tables. The given information is tabulated below:
Setup time (Minutes) | Run time per piece (Minutes) | Capacity (Pieces per hour) | |
Wood cutting | 30 | 5 | 15 |
Make four legs | 60 | 10 | 10 |
Make tops | 60 | 12 | 8 |
Finish the wood | 20 | 8 | 12 |
Assemble and ship | 20 | 17 | 14 |
Small wooden tables are finished in batches of 100 and large wooden tables are finished in the batches of 50. A batch includes fixed setup time and run time. Both small tables and large tables have the same processing time.
Determine the capacity:
As both large wooden table and small wooden table have same capacities, the capacity of the system is minimum of the capacity of the resources. The minimum capacity resource is 8 tables per hour and the process is making tops.
Setup time (Minutes) | Run time per piece (Minutes) | Capacity (Pieces per hour) | |
Wood cutting | 30 | 5 | 15 |
Make four legs | 60 | 10 | 10 |
Make tops | 60 | 12 | 8 |
Finish the wood | 20 | 8 | 12 |
Assemble and ship | 20 | 17 | 14 |
b)
To determine: The average throughput time.
Introduction:
Flow rate is the number of flow units through a business procedure per unit time. Flow rate refers to the number of customers who will be served per hour or the parts produced per minute.
Explanation of Solution
Given information:
A furniture factory makes large and small wooden tables. The given information is tabulated below:
Setup time (Minutes) | Run time per piece (Minutes) | Capacity (Pieces per hour) | |
Wood cutting | 30 | 5 | 15 |
Make four legs | 60 | 10 | 10 |
Make tops | 60 | 12 | 8 |
Finish the wood | 20 | 8 | 12 |
Assemble and ship | 20 | 17 | 14 |
Small wooden tables are finished in the batches of 100 and large wooden tables are finished in the batches of 50. A batch includes fixed setup time and run time. Both small tables and large tables have the same processing time.
Determine the average throughput time:
Small tables | Large tables | |
Batch size | 100 | 50 |
Wood cutting | 530 | 280 |
Make four legs | 1,060 | 560 |
Make tops | 1,260 | 660 |
Finish the wood | 820 | 420 |
Assemble and ship | 1,720 | 870 |
Total time | 4,330 | 2,230 |
Hence, the average throughput time for small tables is 4,330 minutes and the average throughput time for large tables is 2,230 minutes.
Working note:
Wood cutting for small tables:
It is calculated by adding the setup time to the multiplied value of run time and batch size.
Wood cutting for large tables:
It is calculated by adding the setup time to the multiplied value of run time and batch size.
Note: The calculation is carried out for all the processes.
Compute the throughput time for small tables:
While adding the time taken, the maximum amount should be chosen from the process of making four legs and tops, as they can be done in parallel.
Compute the throughput time for large tables:
While adding the time taken, the maximum amount should be chosen from the process of making four legs and tops, as they can be done in parallel.
c)
To determine: The number of tables in the system.
Introduction:
Flow rate is the number of flow units through a business procedure per unit time. Flow rate refers to the number of customers who will be served per hour or the parts produced per minute.
Explanation of Solution
Given information:
A furniture factory makes large and small wooden tables. The given information is tabulated below:
Setup time (Minutes) | Run time per piece (Minutes) | Capacity (Pieces per hour) | |
Wood cutting | 30 | 5 | 15 |
Make four legs | 60 | 10 | 10 |
Make tops | 60 | 12 | 8 |
Finish the wood | 20 | 8 | 12 |
Assemble and ship | 20 | 17 | 14 |
Small wooden tables are finished in the batches of 100 and large wooden tables are finished in the batches of 50. A batch includes fixed setup time and run time. Both small tables and large tables have the same processing time. The factory is producing at the rate of six small tables per hour.
Formula to determine the average number of tables in the system:
Here
I refers to the number of orders in the systems.
T refers to the average throughout time.
R refers to the average flow rate in the process.
Determine the average number of tables in the system:
It calculated by multiplying the average throughput time with the average flow rate in the process.
Hence, the average number of tables in the system is 433 tables.
Want to see more full solutions like this?
Chapter 6 Solutions
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
- What are some good examples of bullet points on a resume for a Christian Elementary School?arrow_forwardWhat is an example of a cover letter for a Christian School Long-Term Substitute Teaching position?arrow_forwardThe supply chain is a conventional notion, but organizations are only really interested in making products that they can sell to customers. Provided they have reliable supplies of materials and reasonable transport for finished products, logistics is irrelevant. Do you think this is true? If yes, explain, and if no, clearly explain as well.arrow_forward
- working as a program operations managerarrow_forward12 X1, X230 1 x =0x2 write the Following linear Programming model by 1- general Form Canonical Forms Canonical formY 2- Standard Form Max Z=35X+ 4 X 2 +6 X3 ST. X+2X2-5x3 = 40 3X, + 6X2 + 7x 3 = 30 7x, +lox2 x3 = 50 X3 X 2 X 3 <0arrow_forwarda/ a Minimum cost assign each worker for one job at Jobs J1 12 33 WI 2 4 6 W2 5 W3 5 33 6 7arrow_forward
- وبة واضافة هذه القيمة الى القيم Ex: Assign each job for each worker at minimum total Cost عمل لكل عامل وبأقل كلفة ممكنة obs الأعمال Workors العمال J1 J2 J3 J4 W₁ 15 13 14 12 W2 11 12 15 13 W3 13 12 10 11 W4 15 17 14 16arrow_forwardThe average completion time (flow time) for the sequence developed using the FCFS rule = 11.75 days (round your response to two decimal places). The percentage utilization for the sequence developed using the FCFS rule = 42.55 % (enter your response as a percentage rounded to two decimal places). b) Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): An Alabama lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left: Job Due Date A 212 B 209 C 208 D 210 Duration (days) 6 3 3 8 Sequence 1 Job B 2 3 4 A D The average tardiness (job lateness) for the sequence developed using the SPT rule = 5.00 days (round your response to two decimal places). The average completion time (flow time) for the sequence developed using the SPT rule = 10.25 days…arrow_forwardWith the aid of examples, fully discuss any five (5) political tactics used in organisations.arrow_forward
- a. With the aid of examples, define discrimination. b. Fully discuss any four (4) types of discrimination in the workplacearrow_forwardRead the Following Extract and Answer the Questions that Follows:The word politics has a somewhat negative connotation. It suggests that someone is attempting touse means or to gain ends that are not sanctioned by the organisation. Political behaviour, as we’vedefined it is quite neutral. Similarly, power is not inherently negative. Whether a person viewspower and politics as unsavoury topics depends on several considerations, most important perhapsbeing where the individual stands on a specific issue in each situation. Nonetheless, most managersare reluctant to admit to political character of their own work settings.Discuss any Five (5) Political tactics you know.arrow_forwardDescribe current features of Cigna Accredo pharmacy own appraisal forms and compare the system used against the textbook’s description of desirable features of appraisal forms. What improvements would you recommend and why?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,