•• 3.8 The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is given. Draw the Gantt chart for the whole construction activity.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office
space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin.
Activity
A
B
C
D
E
F
G
Description
Survey building site
Develop initial design
Obtain board approval
Select architect
Establish budget
Finalize design
Obtain financing
Hire contractor
Immediate
Predecessor
A, B
C
C
D, E
E
F, G
Time
(weeks)
7
11
15
4
6
14
12
H
(a) Draw a project network. (Submit a file with a maximum size of 1 MB.)
Choose File no fie selected
9
Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new
gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilitíes. The following activities
would have to be undertaken before construction can begin.
Immediate
Time
Activity
Description
Predecessor
(weeks)
A
Survey building site
B
Develop initial design
9.
Obtain board approval
А, В
14
D
Select architect
Establish budget
5
F
Finalize design
D, E
16
G
Obtain financing
E
12
Hire contractor
F, G
6
(a) Draw a project network. (Submit a file with a maximum size of 1 MB.)
Choose File)
no file selected
This answer has not been graded yet.
(b) Identify the critical path. (Enter your answers as a comma-separated list.)
(c) Develop the activity schedule for the project.
Earliest
Latest
Finish
Latest
Earliest
Activity
Slack
Start
Start
Finish
A
В
D
E
F
(d) Does it appear reasonable that construction of the athletic complex could…
Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and
intramural facilities. The following activities would have to be undertaken before construction can begin.
Immediate
Predecessor
Time
Activity
Description
(weeks)
A
Survey building site
5
B
Develop initial design
Obtain board approval
A, B
14
D
Select architect
2
E
Establish budget
4
F
Finalize design
D, E
15
G
Obtain financing
E
12
H
Hire contractor
F, G
6
(a) Draw a project network. (Submit a file with a maximum size of 1 MB.)
Browse. No file selected.
This answer has not been graded yet.
(b) Identify the critical path. (Enter your answers as a comma-separated list.)
(c) Develop the activity schedule for the project.
Earliest
Earliest
Finish
Latest
Latest
Activity
Slack
Start
Start
Finish
A
B
D
F
G
(d) Does it appear reasonable that construction of the athletic complex could…
Chapter 3 Solutions
Operations Management
Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - What would a project manager have to do to crash...Ch. 3 - Describe how expected activity times and variances...
Ch. 3 - Define earliest start, earliest Finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - What are dummy activities? Why are they used in...Ch. 3 - What are the three time estimates used with PERT?Ch. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - 3.2 Robert Day has decided to run for a seat as...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - 3.5 Using AOA, diagram the network described below...Ch. 3 - Stephen Hall is developing a program in supply...Ch. 3 - Task time estimates for the modification of an...Ch. 3 - 3.8 The City Commission of Nashville has decided...Ch. 3 - Refer to the table in Problem 3.8. a. Draw the AON...Ch. 3 - The activities needed to build a prototype laser...Ch. 3 - Dave Fletcher (see Problem 3.10) was able to...Ch. 3 - The activities described by the following table...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The following is a table of activities associated...Ch. 3 - Assume that the activities in Problem 3.15 have...Ch. 3 - Bill Fennema, president of Fennema Hospitality,...Ch. 3 - What is the minimum cost of crashing the following...Ch. 3 - Three activities are candidates for crashing on a...Ch. 3 - Development of Version 2.0 of a particular...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Rich Cole Control Devices, Inc., produces...Ch. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Using PERT, Adam Munson was able to determine that...Ch. 3 - Clark Products makes pizza ovens for commercial...Ch. 3 - The Tesla 6 is a new custom-designed sports car....Ch. 3 - TABLE 3.6 Southwestern University Project 1....Ch. 3 - TABLE 3.6 Southwestern University Project 2 What...Ch. 3 - TABLE 3.6 Southwestern University Project 3. If it...Ch. 3 - Project Management at Arnold Palmer Hospital Video...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...
Additional Business Textbook Solutions
Find more solutions based on key concepts
E6-14 Using accounting vocabulary
Learning Objective 1, 2
Match the accounting terms with the corresponding d...
Horngren's Accounting (12th Edition)
Fundamental and Enhancing Characteristics. Identify whether the following items are fundamental characteristics...
Intermediate Accounting (2nd Edition)
Place the letter of the appropriate accounting cost in Column 2 in the blank next to each decision category in ...
Fundamentals of Cost Accounting
(Interest rate determination) You’re looking at some corporate bonds issued by Ford, and you are trying to det...
Foundations Of Finance
How is activity-based costing useful for pricing decisions?
Horngren's Cost Accounting: A Managerial Emphasis (16th Edition)
Mary Williams, owner of Williams Products, is evaluating whether to introduce a new product line. After thinkin...
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- 2. Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin. Immediate Time Activity Predecessor (Weeks) Description Survey Building Site Develop Initial Design Obtain Board Approval Selct Architect Establish Budget Finaliza Design Obtain Financing Hire Contractor A 6. C А, В 12 D 4 E 6 F D, E 15 E 12 H F, G 8 a. Draw the project network. b. Identify the critical path. c. In your assessment, is it reasonable that construction of the athletic complex could begin one year after the decision to begin the project with the site survey and initial design plans? Explain your answer.arrow_forwardimagearrow_forwardColonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin. Activity A B 9 с D E F G H Description Survey building site Develop initial design Obtain board approval Select architect 9 Establish budget Finalize design Obtain financing Hire contractor This answer has not been graded yet. Immediate Predecessor A, B с с D, E E F, G Time (weeks) 5 9 12 2 LO 5 15 (a) Draw a project network. (Submit a file with a maximum size of 1 MB.) Choose File No file chosen 13 8 (b) Identify the critical path. (Enter your answers as a comma-separated list.) B. C.E.F.H 9 9arrow_forward
- 1) Recommend a suitable structure and process for the monitoring and control of a project. Monitoring and controlling strategy( Mile stone , Base line etc.) changes Applied in scgedule/ Costarrow_forwardProject scope statement for sidewalk improvement project?arrow_forwardCONSTRUCTION METHOD AND PROJECT MANAGEMENT.arrow_forward
- project developmental approach used in elliott bay sea wall rebuilding project and 3 reasons why it was usedarrow_forward3) Use the earned value table for Project Terrace to calculate their estimated cost to completion (all dollar amounts are in hundreds). Activity Landscape design Retaining wall Dirt work Move utilities Sprinkler system Planting Plan Cumulative Actual Duration in days 3 6 12 12 12 12 15 18 10 18 9 13 |4 6 14 24 12 2 13 14 9 33 15 13 12 15 48 % Comp 100 50 5 10 10 10arrow_forwardColonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin. Activity Description ImmediatePredecessor Time(weeks) A Survey building site 5 B Develop initial design 8 C Obtain board approval A, B 11 D Select architect C 4 E Establish budget C 6 F Finalize design D, E 15 G Obtain financing E 11 H Hire contractor F, G 6 (a) Draw a project network. (Submit a file with a maximum size of 1 MB.) (b) Identify the critical path. (Enter your answers as a comma-separated list.) (c) Develop the activity schedule for the project. Activity EarliestStart LatestStart EarliestFinish LatestFinish Slack A B C D E F G H…arrow_forward
- Q3) The network is drawn below showing the main activities of the construction project: The following things are required to be illustrated on given network: A) Complete all required data? B) Clarify all final findings on final table? C) Determine in details all steps of calculations until reach to final findings on networkarrow_forwardTopic 4 - PROCESS&TECHNOLOGY AND CAPACITY&FACILITY DESIGNa.Discuss a few objectives of facility layout, and why capacity needed to be understood?b. Elaborate the meaning of process innovation, and how did/can you apply it in your group project given during the academic semesterc.Define in brief about; i. Process Designii. Process Strategyiii. Process Planningiv.Capital Intensityv. Process Flexibilityd. The design committee has collected a data on patient movement in General Hospital, Kuala Lumpur. The design committee would like to relocate the current layout of six rooms in such that the rooms become more efficient and customer-friendly. Number of patient movement from all rooms are given as in Table Q4d. No. 1 to 6 stands for:1 = Intake Dept., 2 = Examination room, 3 = Radiology,4 = Laboratory, 5 = Orthopedics, 6 = Waiting roomFrom the above data; i. Analyze the non-adjacent loads for the CURRENT LAYOUT of the six rooms as shown in Figure Q4d.ii. If the current layout is…arrow_forwardImagine that you are a project manager for a construction company. You must create a WBS for the Site Preparation phase of this project. Here is a list of tasks. Task Title Predecessors Duration A Contract Approval -- 5 B Site Survey A 5 C Permit Application A 4 D Grading B,C 5 E Sewer Lines B 7 F Base Paving D 3 G City Approval C,F 6 H Final Paving E,G 8arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY