Textbook Question
Chapter 3, Problem 3CS
TABLE 3.6 Southwestern University Project
3. If it is necessary to crash to 250 or 240 days, how would Hill do so, and at what costs? As noted in the case, assume that optimistic time estimates can be used as crash times.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Activity
Predecessor
Activities
Normal
Crashed
Duration (Days)
Cost ($)
Duration
Cost ($)
KA
-
5
2000
3
5600
LB
-
7
3000
4
7800
MC
A
10
4000
7
6100
ND
AB
11
5000
8
8000
PE
B
6
2400
4
3600
RF
C
8
3000
6
5100
QG
C,D,E
4
4200
1
3000
SH
E,G
5
5500
3
2500
What is the ES for Activity G and and LS for activity F?
Consider the following activity description with associated cost data shown in Table 1. The cost data represents the total cost and should be considered linear with time.
Table 1: Crash Cost Table
Activity
Immediate Predecessor
Normal Duration (days)
Normal Cost ($)
Crash Duration (days)
Crash Cost ($)
A
---
5
50
3
150
B
---
4
40
2
200
C
B
7
70
5
250
D
A, C
2
20
1
50
E
A, C
5
125
1
525
F
B
10
80
7
290
G
D
7
50
3
250
H
E, F
6
60
3
180
Reduce the project duration to minimum duration and calculate the cost.
Note:-
Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism.
Answer completely.
You will get up vote for sure.
Please answer all parts..
Chapter 3 Solutions
Operations Management
Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - What would a project manager have to do to crash...Ch. 3 - Describe how expected activity times and variances...
Ch. 3 - Define earliest start, earliest Finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - What are dummy activities? Why are they used in...Ch. 3 - What are the three time estimates used with PERT?Ch. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - 3.2 Robert Day has decided to run for a seat as...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - 3.5 Using AOA, diagram the network described below...Ch. 3 - Stephen Hall is developing a program in supply...Ch. 3 - Task time estimates for the modification of an...Ch. 3 - 3.8 The City Commission of Nashville has decided...Ch. 3 - Refer to the table in Problem 3.8. a. Draw the AON...Ch. 3 - The activities needed to build a prototype laser...Ch. 3 - Dave Fletcher (see Problem 3.10) was able to...Ch. 3 - The activities described by the following table...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The following is a table of activities associated...Ch. 3 - Assume that the activities in Problem 3.15 have...Ch. 3 - Bill Fennema, president of Fennema Hospitality,...Ch. 3 - What is the minimum cost of crashing the following...Ch. 3 - Three activities are candidates for crashing on a...Ch. 3 - Development of Version 2.0 of a particular...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Rich Cole Control Devices, Inc., produces...Ch. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Using PERT, Adam Munson was able to determine that...Ch. 3 - Clark Products makes pizza ovens for commercial...Ch. 3 - The Tesla 6 is a new custom-designed sports car....Ch. 3 - TABLE 3.6 Southwestern University Project 1....Ch. 3 - TABLE 3.6 Southwestern University Project 2 What...Ch. 3 - TABLE 3.6 Southwestern University Project 3. If it...Ch. 3 - Project Management at Arnold Palmer Hospital Video...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- CASE - CAPACITY BUILDING PROJECT AIMS TO INCREASE YOUTH INVOLVEMENT IN SUSTAINABLE DEVELOPMENT Basseterre, St. Kitts, April 29, 2021 (SKNIS): St. Kitts and Nevis Youth Ambassador Corps officially launched a new project on Wednesday (April 28, 2021) designed to increase the contributions of young people to the sustainable development of the twin-island Federation. The initiative, dubbed the Youth Capacity Building Small Grants Project on Youth in Sustainable Development, will build the capacity and practical skills of young people to design, implement, and monitor interventions relevant to the social, economic, and sustainable development of youth and their communities. The project is geared towards members of youth groups specifically. It is spearheaded by the national youth ambassador corps in collaboration with the GEF Small Grants Programme (SGP), and the Departments of Youth in St. Kitts, and Nevis. The Small Grants Project is funding the initiative to the tune of US$49,970.00. SGP…arrow_forwardCASE - CAPACITY BUILDING PROJECT AIMS TO INCREASE YOUTH INVOLVEMENT IN SUSTAINABLE DEVELOPMENT Basseterre, St. Kitts, April 29, 2021 (SKNIS): St. Kitts and Nevis Youth Ambassador Corps officially launched a new project on Wednesday (April 28, 2021) designed to increase the contributions of young people to the sustainable development of the twin-island Federation. The initiative, dubbed the Youth Capacity Building Small Grants Project on Youth in Sustainable Development, will build the capacity and practical skills of young people to design, implement, and monitor interventions relevant to the social, economic, and sustainable development of youth and their communities. The project is geared towards members of youth groups specifically. It is spearheaded by the national youth ambassador corps in collaboration with the GEF Small Grants Programme (SGP), and the Departments of Youth in St. Kitts, and Nevis. The Small Grants Project is funding the initiative to the tune of US$49,970.00. SGP…arrow_forwardPM.66 Real estate developer Russell Call was working with a few contractors to make a number of improvements to one of his rental properties. After gathering information from these contractors he determined the following durations, predecessors, and costs of all the required activities: Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s) А 3 $1,000 $3,300 В 1 $2,160 $2,460 3 2 $1,300 $3,000 D 7 3 $2,000 $2,500 A E 3 $1,650 $2,100 B F 4 3 $4,100 $5,260 G 4 2 $1,650 $2,100 D, E What is the overall duration of the project? Number Which of the following activities has the lowest crash cost per week? O A O Earrow_forward
- QUESTION 16 Refer to the project addressed in questions 21-30 of your Quiz 1 and associated worked solutions used in our review session. The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for the project. Activity A B D E Table 1 Reference: Ref 1 optimistic most likely time time 3 4 2 6 5 5 8 3 9 9 pessimistic time 7 10 5 12 15 Activity Predecessor A A B, C D Using Table 1, which of the following statements are correct? O A. The latest finish time of activity B is the same as its earliest finish time O B. Activity A is critical because it is the starting activity in the project O C. Activity D must be critical because it is the only predecessor of activity E O D. Answers A and B are correct O E. Answers A and C are correctarrow_forward2.arrow_forwardPreceding Activity Crashed Cost per week $600 $700 $400 Activity Normal Completion Time (week) Crashed Completion time (week) A 7 5 B 12 10 A 8 2 $800 $300 $500 E C, D 5 4 F E 9 8 D. F 10 10 i. Draw the network diagram linking all the activities in a way that it shows if there exist any preceding activity/activities before starting each of the mentioned activities in the above table, ii. Showing the earliest start time, the earliest finish time, the latest start time and the latest finish time of each of the activities in the project determine the completion time of the project and the critical path. ii. Find the slack time (delay time) of each of the activities, the critical and the non-critical activities. Find the minimum possible completion time of the project by considering the crashed completion times and the minimal total cost of that crashing the project. iv. Need proper handwritten answers. Thank you!arrow_forward
- 2. Given the data, answer the questions below. Activity Normal Time Normal Cost Crashed Time Crashed Cost (weeks) (Pesos) (weeks) (Pesos) 1-2 12 30,000 7 50,000 2-3 8 20,000 35,000 2-4 4 40,000 3 70,000 3-4 4-5 4 5,000 1 11,000 4-6 12 500,000 9. 710,000 5-6 4 5,000 1 11,000 6-7 4 150,000 220,000 750,000 1,107,000 a. Suppose the project needs to be completed within 30 weeks, how much extra cost will be incurred to finish the project by this time? Which activity/ies must be crushed? b. If the project duration is reduced down to the minimum time possible, what is the total number of crashed weeks? How much extra cost will this require?arrow_forward7arrow_forwardTable 7.5 contains information about an environmental clean-up project in the township of Hiles. Shorten the project threeweeks by finding the minimum-cost schedule. Assume thatproject indirect costs and penalty costs are negligible. Identifyactivities to crash while minimizing the additional crash costs.arrow_forward
- P11-1 Drawing simple CPM diagram and determining critical path From the following information draw a network showing the critical path and calculate the minimum time required to complete the work. Activity Duration (days) A B C D E F G H I 1 2 3 1 8 3 2 1 2 A must be completed before starting the other activities, B, C and E can commence concurrently after completion of A. D can commence after completion of B and C. F can commence after completion of C and E. G follows F, and H follows D. I can commence after completion of G and H. Number your nodes.arrow_forwardConnect HW Q1arrow_forward21. The following table provides the information necessary to construct a project network and project crash data: Activity (i, j) Activity Predecessor Activity Time (weeks) Normal Crash Activity Cost Normal Crash a (1,2) --- 16 8 $2000 $4400 b (1,3) --- 14 9 1000 1800 c (2,4) a 8 6 500 700 d (2,5) a 5 4 600 1300 e (3,5) b 4 2 1500 3000 f (3,6) b 6 4 800 1600 g (4,6) c 10 7 3000 4500 h (5,6) d, e 15 10 5000 8000 a. Construct the project network b. Manually crash the network to 28 weeks Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY