•• 3.2 Robert Day has decided to run for a seat as Congressman from the House of Representatives, District 34, in Connecticut. He views his 8-month campaign for office as a major project and wishes to create a work breakdown structure (WBS) to help control the detailed
LEVEL | LEVEL ID NO. | ACTIVITY | |||
1 | 1.0 | Develop political campaign | |||
2 | 1.1 | Fund-raising plan | |||
3 | 1.11 | ----- | |||
3 | 1.12 | ----- | |||
3 | 1.13 | ----- | |||
2 | 1.2 | Develop a position on major issues | |||
3 | 1.21 | ----- | |||
3 | 1.22 | ----- | |||
3 | 1.23 | ----- | |||
2 | 1.3 | Staffing for campaign | |||
3 | 1.31 | ----- | |||
3 | 1.32 | ----- | |||
3 | 1.33 | ----- | |||
3 | 1.34 | ----- | |||
2 | 1.4 | Paperwork compliance for candidacy | |||
3 | 1.41 | ----- | |||
3 | 1.42 | ----- | |||
2 | 1.5 | Ethical plan/issues | |||
3 | 1.51 | ----- |
Help Mr. Day by providing details where the blank lines appear. Are there any other major (level-2) activities to create? If so, add an ID no. 1.6 and insert them.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
create a network for planning and construction of the new hospital at Arnold Palmer
Plz sir solve this for me
V
what is feasibility Report ?Define when and why we need it And also define who prepare this document.
Chapter 3 Solutions
Operations Management
Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - What would a project manager have to do to crash...Ch. 3 - Describe how expected activity times and variances...
Ch. 3 - Define earliest start, earliest Finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - What are dummy activities? Why are they used in...Ch. 3 - What are the three time estimates used with PERT?Ch. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - 3.2 Robert Day has decided to run for a seat as...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - 3.5 Using AOA, diagram the network described below...Ch. 3 - Stephen Hall is developing a program in supply...Ch. 3 - Task time estimates for the modification of an...Ch. 3 - 3.8 The City Commission of Nashville has decided...Ch. 3 - Refer to the table in Problem 3.8. a. Draw the AON...Ch. 3 - The activities needed to build a prototype laser...Ch. 3 - Dave Fletcher (see Problem 3.10) was able to...Ch. 3 - The activities described by the following table...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The following is a table of activities associated...Ch. 3 - Assume that the activities in Problem 3.15 have...Ch. 3 - Bill Fennema, president of Fennema Hospitality,...Ch. 3 - What is the minimum cost of crashing the following...Ch. 3 - Three activities are candidates for crashing on a...Ch. 3 - Development of Version 2.0 of a particular...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Rich Cole Control Devices, Inc., produces...Ch. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Using PERT, Adam Munson was able to determine that...Ch. 3 - Clark Products makes pizza ovens for commercial...Ch. 3 - The Tesla 6 is a new custom-designed sports car....Ch. 3 - TABLE 3.6 Southwestern University Project 1....Ch. 3 - TABLE 3.6 Southwestern University Project 2 What...Ch. 3 - TABLE 3.6 Southwestern University Project 3. If it...Ch. 3 - Project Management at Arnold Palmer Hospital Video...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Compute the BCWS AND BCWP 58 weeks time framework completion= not yet startedarrow_forwardPart 1: The 5 project management groups have wide industry application in modern day project management. By using practical examples of your choice, demonstrate the practical application of the project management processes in bringing a project to a successful end (Detailed response required, also acknowledge information sources). Part 2: A gantt chart is widely applied in project management as a project scheduling tool,whose format is in bar chart form. Critically examine a gantt chart as a project scheduling tool and practically demonstrate how it can also be used as a project planning and control technique (Detailed response required, also acknowledge information sources).arrow_forwardanswer the following: Develop the network for planning and construction of the new hospital at Arnold Palmer.arrow_forward
- Describe the primary concerns of scope control.arrow_forward1. Using Microsoft Excel TM prepare a Gantt Chart for the following project. Activity Predecessor(s) Duration (Days) 1. Forming the problem statement 2. Identifying functional requirements 3. Identifying constraints and limitations 4. Defining a schedule 5. Defining the design parameters 6. Identifying alternatives 7. Evaluating and analyzing alternatives 8. Select a solution 9. Gather supplies 10. Construct prototype 11. Test performance 12. 1 1 1 1 1 2,3 1 2 1 2 7 1 8 4 10 1 Redesign 13. 11 2 Demonstrate solution to 12 1 class 5 COarrow_forwardRequired: Develop a schedule for hiring new employees. What is thetotal cost of this schedule?arrow_forward
- Please do not give solution in image format thankuarrow_forwardTable 7.5 contains information about an environmental clean-up project in the township of Hiles. Shorten the project threeweeks by finding the minimum-cost schedule. Assume thatproject indirect costs and penalty costs are negligible. Identifyactivities to crash while minimizing the additional crash costs.arrow_forwardWaht is the implication of nutrition and hygiene programs as part of occupational health. Create a program proposal for this which includes objectives, procedures, persons involved with job description, diagram, referral system with criteria, and possible budget proposal for these programsarrow_forward
- Problem 4 Draw the network diagram from the following information. Create a data sheet for ES, EF, LS, LF, TF, FF, INTF and Independent Float. Find the critical path and critical activities. CIV 417/CPM THE NETWORK DIAGRAM Activity Duration (days) Activity Description 1-2 Relocation of Boundaries-Cleaning 1 2-3 2 Construction of Field Office 2-4 5 Delivery of Materials 2-5 2 Staking and batter boards 3-5 Digging/excavation 4-5 10 Cutting and assembling of steel reinforcement 4-7 Dummy 3-6 12 Making of forms and door jambs 5-6 Positioning Steel Reinforcement 5-7 Forms and Scaffoldings 5-8 8 Electrical, plumbing and water pipe connections 6-8 Dummy 6-9 Pouring of footings and columns 2 7-8 1 Removal of forms CIV 417/CPM 95arrow_forwardActivity-4 Dear Students, Search in the internet and submit a written report (minimum three (3) pages) of an effective sales training program conducted by any company.arrow_forwardOpp l +O 90% 10:31 33,19 K/s UNIVERSITY OF GHANA 35 Part 1 of 1- Question 1 of 100 . refers to how the project is expected to work and solve the stated problem in project or proposal writing. A. Project Portfolio B. Portfolio of Activities C. Plan of Activities D. Project Activities Reset Selection [1] Question Progressarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY