Textbook Question
Chapter 3, Problem 12P
The activities described by the following table are given for the Howard Corporation in Kansas:
ACTIVITY | IMMEDIATE PREDECESSOR(S) | TIME |
A | --- | 9 |
B | A | 7 |
C | A | 3 |
D | B | 6 |
E | B | 9 |
F | C | 4 |
G | E, F | 6 |
H | D | 5 |
I | G, H | 3 |
- a. Draw the appropriate AON PERT diagram for J.C. Howard’s management team.
- b. Find the critical path.
- c. What is the project completion time?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Consider a project having the following ten activities:
Immediate
Activity
A
Time (weeks)
Predecessors
none
7
B
none
3
A
5
А, В
С, D
6
E
4
F
D
4
G
C
9
E, G
E, F
H, I
H
8
I
J
5
a)Construct AON diagram for the following data.
b) Identify path, path duration and critical path
c) Conduct CPM analysis by identifying ES, EF, LS, LF
d) What is the slack for each activity and the critical path?
The activities described by the following table are given for the Howard Corporation in Kansas: a) Draw the appropriate AON PERT diagram for J.C. Howard's management team.b) Find the critical path.c) What is the project completion time?
Humber Web Design Co. is organizing a new project to increase efficiency and improve relations with their clients. The project manager for this initiative has broken the project up into several parts as follows:
Activity
Activity Description
Immediate Predecessor
Activity time (days)
A
Identify Client Base
―
33
B
Develop Client Prospectus
―
21
C
Perform Design Analysis
―
35
D
Program Back End
A, B, C
47
E
Program Front End
A
13
F
Project Consolidation
D, E
11
(a) For the given project, fill in the nodes of the network diagram below.
A
E
33
13
Start
B
D
F
Finish
Time
21
47
11
Time
C
35
(b) Using the network diagram, fill in the table. Make sure that you put the values in the appropriate columns.
Activity
Earliest Start (ES)
Latest…
Chapter 3 Solutions
Operations Management
Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - What would a project manager have to do to crash...Ch. 3 - Describe how expected activity times and variances...
Ch. 3 - Define earliest start, earliest Finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - What are dummy activities? Why are they used in...Ch. 3 - What are the three time estimates used with PERT?Ch. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - 3.2 Robert Day has decided to run for a seat as...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - 3.5 Using AOA, diagram the network described below...Ch. 3 - Stephen Hall is developing a program in supply...Ch. 3 - Task time estimates for the modification of an...Ch. 3 - 3.8 The City Commission of Nashville has decided...Ch. 3 - Refer to the table in Problem 3.8. a. Draw the AON...Ch. 3 - The activities needed to build a prototype laser...Ch. 3 - Dave Fletcher (see Problem 3.10) was able to...Ch. 3 - The activities described by the following table...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The following is a table of activities associated...Ch. 3 - Assume that the activities in Problem 3.15 have...Ch. 3 - Bill Fennema, president of Fennema Hospitality,...Ch. 3 - What is the minimum cost of crashing the following...Ch. 3 - Three activities are candidates for crashing on a...Ch. 3 - Development of Version 2.0 of a particular...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Rich Cole Control Devices, Inc., produces...Ch. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Using PERT, Adam Munson was able to determine that...Ch. 3 - Clark Products makes pizza ovens for commercial...Ch. 3 - The Tesla 6 is a new custom-designed sports car....Ch. 3 - TABLE 3.6 Southwestern University Project 1....Ch. 3 - TABLE 3.6 Southwestern University Project 2 What...Ch. 3 - TABLE 3.6 Southwestern University Project 3. If it...Ch. 3 - Project Management at Arnold Palmer Hospital Video...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Humber Web Design Co. is organizing a new project to increase efficiency and improve relations with their clients. The project manager for this initiative has broken the project up into several parts as follows: Activity Activity Description Immediate Predecessor Activity time (days) A Identify Client Base ― 44 B Develop Client Prospectus ― 35 C Perform Design Analysis ― 46 D Program Back End A, B, C 43 E Program Front End A 27 F Project Consolidation D, E 36 (a) For the given project, fill in the nodes of the network diagram below. A E 44 27 Start B D F Finish Time 35 43 36 Time C 46 (b) Using the network diagram, fill in the table. Make sure that you put the values in the appropriate columns. Activity Earliest Start (ES) Latest…arrow_forwardPart 1: Below matrix shows one of the important data used in project management, identify the name of the matrix and explain the roles of each person involved in this matrix. Total= 10 marks Facilities Plant Mgr HR Security Project Mgr Identify a minimum of three asphalt R contractors from Angie's List Arrange for contractor visits and quotes Review quotes and references, A R make contractor selection Review and finalize contract, lock in plant shutdown week R Communicate project to shutdown maintenance crew, make sure all R vehicles are removed from the lot Provide security gate access codes for asphalt crew by June 15 A Oversee the project during the plant shutdown week, ensure it is A R completed on time R = Responsible, A = Accountable, C = Consulted, I = Informedarrow_forwardJanice Eliassen must complete the activities in the following table to fin ish her consulting project. a) Draw the appropriate PERT diagram.b) Find the critical path and project completion time.c) Find the probability that the project will take more than49 time periods to complete.arrow_forward
- Consider the following data for a project to reorganize the office space at Platinum Financial Advisors:a. Draw the network diagram for this project. b. Identify the critical path and estimate the project’s duration. c. Calculate the slack for each activity.arrow_forwardConsider the following data for a project to reorganize the office space at Platinum Financial Advisors:a. Draw the network diagram for this project.b. Identify the critical path and estimate the project’s duration.c. Calculate the slack for each activity.arrow_forwardThe activities described by the following table aregiven for the Howard Corporation in Kansas: a) Draw the appropriate AON PERT diagram for J.C. Howard’smanagement team.b) Find the critical path.c) What is the project completion time?arrow_forward
- Consider the following information for a project to add a drive-thru window at Crestview Bank. a. Choose the correct network diagram below. O A. S Activity Activity Time (weeks) Immediate Predecessor(s) 7 3 4 ITT 3 A, B 6 5 9 12 A B C D E F G H Q B. S B D, C E, C F, Garrow_forwardSolve the following problem using PERT or CPM.arrow_forwardA Make a network diagram and find the project completion time and critical path Activity Activity Description Excavate (7) Estimated Duration (Weeks) Immediate Predecessors 2 B Lay the foundation A 4 C Put up the rough wall B 10 D Put up the roof C 6 E Install the exterior plumbing C 4 F Install the interior plumbing E 5 G Put up the exterior siding D 7 H Do the exterior painting E, G 9 1 Do the electrical work C 7 J Put up the wallboard F, I 8 K Install the flooring J 4 Do the interior painting J 5 M Install the exterior fixtures H N Install the interior fixtures K, L 26arrow_forward
- Problem 1 The following data represent the plan of a project in Magic Corporation: Times (weeks) Activity A B C D DEF Predecessor G H 1 J A A A B, C D a 4 2 2 1 3 4 1 1 3 1 m 5 4 4545300 E, F G G H, I a. Draw the network diagram and find the critical path. b. Estimate the expected completion time of the project. c. Calculate the probability that the job will take more than 30 weeks to complete. d. Calculate the probability that the job will take less than 26 weeks. 3 8 b 12 12 6 9 5 6 4 2 5 9 11 3 Слarrow_forwardRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: This exercise contains only part a a) The correct precedence diagram for the project is shown in Activity Immediate Predecessor(s) Time (days) A BCDEF G 1100 AD C E. F 3 5 1 10 5 8 SE Flaure 1 A В Figure 2 A 6 F Figure 3 A B Earrow_forwardPERT-CPM 1. Consider a project involving the following activities and precedence relationship. The cost of each activity is listed. The following activity time estimates have been provided for a preparation involving an MIS project. a. Draw the AON and AOA Diagram. b. Perform a Program Evaluation and Review Technique (PERT) to determine the expected total duration of the project. [Note: Use the diagramming convention agreed in class and tabulate the results for each activity's ES, EF, LS, LF, slack time and indication if it's in the critical path Note: Expected (Ave Time) = (0ptimistic Time + 4*Most Likely Time + PessimisticTime) / 6 = ( OT + 4MLT + PT ) / 6 c. If the project exceeds 11 weeks, there is an additional miscellaneous costs around Php 30,000. Will the company opt to speed up the project? Activity Predecessors Optimistic Most Pessimistic Crash Normal Crashed Likely Time Cost Cost A 2 4 6. 2 11,000 6,000 3,000 7,000 4,000 13,000 9,000 4,000 5,000 3,000 3 17.000 В 1 3 5 1…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY