a)
To determine: Whether plan 5 will be suitable to maintain a constant workforce in order to meet the demand.
Introduction:
The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
b)
To determine: Plan 6 to maintain the constant workforce and use the subcontract to meet the demand requirement.
Introduction:
The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
c)
To summarize: The results from Plan 1 to Plan 6
Want to see the full answer?
Check out a sample textbook solutionChapter 13 Solutions
Operations Management: Sustainability and Supply Chain Management (12th Edition)
- Wormwood, Ltd., produces a variety of furniture products. The planning committee wants to prepare an aggregate plan for the next six months using the following information.Month1 2 3 4 5 6Demand 160 150 160 180 170 140CapacityRegular 150 150 150 150 160 160Overtime 10 10 0 10 10 10Cost Per UnitRegular time $50Overtime 75Subcontract 80Inventory holding, per month 4Subcontracting can handle a maximum of 10 units per month. Beginning inventory is zero.Develop a plan that minimizes total cost. No back orders are allowed. Regular capacity = Regularproduction.arrow_forwardDeforrest Marine Motors manufactures engines for the speedboat racing circuit. As part of their annual planning cycle, they forecasted demand for the next four quarters. The number of available days of production and the anticipated demand are given below. Employees Production Rate Production Cost Backorder Cost Overtime Cost Overtime Limit Demand Q1 2,400 6,019,000 They also estimated many of the costs required to conduct operations planning. Some of these key figures are listed below. 30 70 units/employee/quarter Q2 2,200 $1,000/unit $200/unit/quarter $1,500/unit <= 25% of Reg. Production Q3 1,700 Q4 1,800 Hire Cost Fire Cost Subcontracting Cost Subcontracting Limit Inventory Cost Initial Inventory $1,200/employee $800/employee $1,800/unit 400 units maximum $100/unit/quarter 280 units Deforrest Marine Motors wishes to maintain the current number of employees for the entire year to follow a level strategy balanced with inventory and backorders as needed. What is the total cost of this…arrow_forwardThe planner at a company that makes garden tractors is about to prepare an aggregate production plan that will cover the next 6 months. She has collected the following information: Month Demand Forecast Above the available capacity through permanent workforce 1 1,000 2 1,000 3 2,000 4 3,000 5 4,000 6 1,000 Total: 12,000 Production per month = 20 units per worker Initial inventory = 500 units Desired ending inventory (at the end of month 6) = 0 units Cost: Hire cost = $500 per temporary worker Inventory = $10 per tractor per month Backorder = $150 per tractor per month The optimum aggregate plan is: Month 1 2 3 4 5 6 Total Forecast Demand above regular capacity 1,000 1,000 2,000 3,000 4,000 1,000 12,000 # of temporary workers required 50 50 100 150 200 50 Temp. Workers hired 25 25 50 75 0 0 Temp. workers laid off 0…arrow_forward
- answer only letters D, E and Farrow_forwardhelp:) thank you!! two partsarrow_forwardA. When aggregate planning seeks to influence demand and supply, both the marketing and operations functions are involved. In this case, the goal is generally to find: a. A lower total cost plan b. A higher profit plan c. A higher sales revenue plan d. A lower cost of goods manufactured plan B. In a market situation where demand is exceeding supply, which from the following list would you generally work on first? a. Distribution b. Work force level c. Promotion d. Pricearrow_forward
- Kindly helparrow_forwardplease answer both the questions within 30 minutes. make sure both the questions are answered else i will give negative ratings.arrow_forwardWhich of the following is not one of the graphical methodsteps?a) Determine the demand in each period.b) Determine capacity for regular time, overtime, andsubcontracting each period.c) Find labor costs, hiring and layoff costs, and inventoryholding costs.d) Construct the transportation table.e) Consider company policy that may apply to the workers or stock levels.f ) Develop alternative plans and examine their total costs.arrow_forward
- Aggregate planners attempt to balance: a. demand and inventories b. capacity and costs c. capacity and demand d. demand and costsarrow_forwarda. How much should be produced each period? b. What is ending inventory for each period? c. If inventory carrying cost is $3 per case per period based on ending inventory, what is the total cost of carrying inventory? d. What is the total plan cost and why? 4. The opening backlog is 1200 units. Forecast demand is shown below. a. Calculate the weekly production for level production if the backlog is to be reduced to 1000 units, b. Calculate the projected backlog for each week. Week 2 4 3 1200 1200 Forecast 1200 Demand Planned Production Projected Backlog 1200 1100 5 1100 25 20 6 1000 Total 5. A firm plans to make 400 wagons, 200 carts, and 100 sleds. The resource bill shown below displays the amount of critical resources needed to make one average unit of product family: Wood (Board Feet) Labor (Standard Hours) Product Wagon 0.75 0.50 1.00 Cart Sled 30 Calculate the total wood AND labor needed to make the total number of items in the product family.arrow_forwardSearch for Patterns: Problem No. 1: The first week of chess club had 3 students. The second week had five students. The third week had eight students and the fourth had twelve. If this pattern continues, how many students will show up for the eight week? Problem No. 2: From the given table find the value of n if m = 50. M 1 2 3 4 5 50 N 1 3 5 7 Problem No. 3: What is the unit’s digit in the power of 7 with an exponent of 1999?arrow_forward
- MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational PublishingPractical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,