Summary Introduction
To determine: Thedifference between aggregate planning in service and aggregate planning in manufacturing
Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
QUESTION 1
A master production schedule shows the following information
MPS
Week
Week
Week
Week
Beginning inventory =
300
31
Forecast
1.000
1,200
1,300
1.200
800
700
Actual customer orders
Projected on-hand
inventory
Available to promise
800
1,000
MPS
Based on the information in the MPS, what is the amount that is available to promise in week 4?
O a. 1,200
Ob.700
Oc. 1.500
O d. 500
Question 4
b) Company ABC wishes to evaluate whether to produce a component
internally or purchase from a vendor. The firm has the following options:
Internal Production
Process 1
Process 2
Purchase from Vendor
Vendor 1
Vendor 2
Vendor 3
Variable cost of $17 per unit; annual
fixed cost of $200,000
Variable cost of $14 per unit; annual
fixed cost of $240,000
Offers a price of $20 per unit for any
volume up to 30,000 units
Offers a price of $22 per unit for 1,000
units or less, and $18 per unit for
large quantities
Offers a price of $21 per unit for the
first 1,000 units and $19 per unit for
additional units
If the annual demand is 10,000 units, which alternative would be best from
a cost standpoint? For 20,000 units, which alternative would be best?
Question 4) APP Linear Programming
Given the following information:
Quarter Demand
Regular Prod. Capacity = 3,000 units/gt
8,000 Overtime Prod. Capacity = 800 units/gtg
4,000 Subcontracting Capacity = 1,800 units/gt
Regular Prod. Cost = $20/unit
Overtime Prod. Cost = $25/unit
1
2
2,000 Inventory Capacity
= 6,000 untis/atr
Subcontracting Cost = $35/unit
Inventory Cost
3
Beginning Inventory
= 500 units
= $4/unit/gtr
Linear programming is to be used to determine a production plan strategy of Level Production,
Overtime, and Subcontracting.
a. Formulate the Objective Function (note that there are 3 quarters).
b. Formulate all Constraints (standardized).
c. How many decision variables are in the model?
d. How many constraints are in the model? (do not include non-negativity constraints)
Chapter 13 Solutions
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Ch. 13 - Prob. 1DQCh. 13 - Why are SOP teams typically cross-functional?Ch. 13 - Prob. 3DQCh. 13 - Prob. 4DQCh. 13 - Prob. 5DQCh. 13 - Prob. 6DQCh. 13 - Question: 7. What is level scheduling? What is the...Ch. 13 - Question: 8. Define mixed strategy. Why would a...Ch. 13 - Prob. 9DQCh. 13 - Prob. 10DQ
Ch. 13 - Question: 11. What is the relationship between the...Ch. 13 - Prob. 12DQCh. 13 - Question: 13. What are major limitations of using...Ch. 13 - Prob. 14DQCh. 13 - Question: 13.1 Prepare a graph of the monthly...Ch. 13 - Prob. 2PCh. 13 - The president of Hill Enterprises, Terri Hill,...Ch. 13 - Prob. 4PCh. 13 - Prob. 5PCh. 13 - Prob. 6PCh. 13 - Prob. 7PCh. 13 - Prob. 8PCh. 13 - Prob. 9PCh. 13 - Question: 13.10 The SOP team (see Problem 13.9)...Ch. 13 - Prob. 11PCh. 13 - Prob. 12PCh. 13 - Prob. 13PCh. 13 - Question: 13.14 Jerusalem Medical Ltd., an...Ch. 13 - Prob. 15PCh. 13 - Prob. 16PCh. 13 - Prob. 17PCh. 13 - Question: 13.18 Jose Martinez of El Paso has...Ch. 13 - Prob. 19PCh. 13 - Prob. 24PCh. 13 - Prob. 25PCh. 13 - Prob. 26PCh. 13 - Prob. 1CSCh. 13 - Prob. 2CSCh. 13 - Prob. 1VCCh. 13 - Prob. 2VCCh. 13 - Question: 3. What are some concerns the team needs...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Question 3 List any five (5) costs prevalent in aggregate planning in the motor car industry.arrow_forwardQuestion 4.4 Montreal Hardware Co. is making a make-or-buy decision. The market feedback shows that the optimal price for this item is $10 each. If the item is outsourced to Laval Hardware Co, there is virtually no cost other than the $6 per unit that they would pay Laval Hardware Co. Internally, they have two choices. Process A requires an investment of $120,000 for design and equipment, but it results in a $4 per unit cost. Process B requires only a $100,000 investment, but its per unit cost is $5. Regardless of whether the item is subcontracted or produced internally, there is a 50% chance that they will sell 50,000 units, and a 50% chance that they will sell 100,000 units. Draw the decision tree appropriate to the alternatives and outcomes stated. Using the decision tree and EMV, what is their best choice?arrow_forwardQuestion 4 An alternative will have fixed costs of $10,000 per month, variable costs of $50 per unit, and revenue of $70 per unit. The break-even point volume is:arrow_forward
- QUESTION 2 ID11 What is an information system for identifying and planning the enterprise-wide resources needed to take, make, ship, and account for customer orders? BOM MRP CIM ⒸERParrow_forwardQUESTION #1 Mrs. Johnson, the owner of a small manufacturing business has patented a new device for kitchen appliance. Before trying to commercialize the device and add it to her existing product line, the she wants reasonable assurance of success. Variable costs are estimated at $8 per unit produced and sold. Fixed costs are about $60,000 per year. a. Forecasted sales for the first year are 15,000 units if the price is reduced to $20. With this pricing strategy, what would be the product's total contribution to profits in the first year? b. If the selling price is set at $30, how many units must be produced and sold to break even? Use both algebraic and graphic approachesarrow_forwardQUESTION 9 Consider a SKU with 276 picks forecasted during the planning horizon and an annual flow of 2000 ft. Suppose that: • the cost of picking from the forward fast-pick area is 1 minute per pick • the cost of picking from the reserve area is 4 minutes per pick • the cost of restocking the fast-pick area from reserve is 5 minutes per restock What is the labor efficiency of this SKU? Provide your answer to the nearest single decimal point.arrow_forward
- QUESTION 2 NAK Consult Ltd is a construction company with many contracts being executed concurrently. A large number of workers are on various construction sites. NAK Consult Ltd has an internal audit department and the team is currently reviewing cash wages systems within the company. The following information is available concerning the wages systems: • Workers on each site are controlled by a foreman. The foreman has a record of all employee numbers and can issue temporary numbers for new employees. • Any overtime is calculated by the computerized wages system and added to the standard pay. • The two staff in the wages department make amendments to the computerized wages system in respect of employee leave, illness, as well as setting up and maintaining all employee records. • The computerized wages system calculates deductions from gross pay, such as employee taxes (PAYE), and other statutory deductions. • Finally, a list of net cash payments for each employee is produced. Cash is…arrow_forwardQuestion 6 only questions in redarrow_forwardQuestion 3 Gajah Sdn Bhd makes two products (Alpha and Beta) that require direct materials, direct labour and overhead. The operations for next month are: Alpha RM Beta Revenue Direct material Direct labour Overhead: Direct material related Direct labour related RM 300,000 60,000 95,000 Total RM 400,000 90,000 135,000 100,000 30,000 40,000 13,500 40,500 Required : a) Gajah uses a two-stage cost allocation system. It uses direct material costs to allocate direct materials related overhead and direct labour costs to allocate direct labour related overhead costs: i. Calculate the direct material related overhead rate for next month. ii. Calculate the direct labour related overhead rate for next month iii. What is the total overhead allocated to product Alpha next month? iv. What is the total overhead allocated to product Beta next month?arrow_forward
- Question 6 Table below is a time-phased net requirements for Widgets over the next six weeks. Week 1 Requirements 335 The setup cost is $200 and the holding cost is $0.30 per unit per week. Using the Silver-Meal heuristics, indicate the number of units to produce for each of the following period. Enter your answer as integer. Week 1 2 3 4 5 6 2 200 Production Quantity 3 140 4 440 5 300 The total holding and setup cost for the Silver-Meal lot sizing method is $ Note: Enter your value with exactly 2 decimal places, as in 12345.67 6 200arrow_forwardQuestion 3 Heman Company has three production plants in P1, P2, and P3 and two warehouses W1 and W2. The capacities of the three production plants during the next year are 450, 600, and 380. The demands at the two warehouses are 650 and 780 cars. The cost chart between the production plants and the warehouses is given: COST Chart W1 W2 P1 $6 $4 P2 $3 $6 P3 S7 $8 Formulate an initial feasible solution to Heman Company's problem using the Northwest- Corner Rule. Then evaluate each unused shipping route by computing all improvement indices using Stepping-Stone Method. Is the solution optimal?arrow_forwardQUESTION 3 (Using the same problem) A vendor for the local ballpark food stand is questioning whether to stock his concession with a large or small inventory. He believes that it will depend upon the size of the crowd. He has developed a payoff matrix for the various alternatives (stocking decision) and states of nature (size of crowd). What is the Expected Value of Perfect Information (EVPI)? PROFIT ($) Average Crowd $50,000 $70,000 .50 Alternatives Large Inventory Small Inventory Probability * A) $68,400 B) $78,400 C) $10,000 D) -$20,000 O E) $51,500 Large Crowd $220,000 $90,000 .20 Small Crowd -$2,000 -$5,000 30arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.