To define: Advantages and disadvantages of varying the workforce according to the demand requirement
Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
QUESTION 2
NAK Consult Ltd is a construction company with many contracts being executed concurrently. A large
number of workers are on various construction sites. NAK Consult Ltd has an internal audit department
and the team is currently reviewing cash wages systems within the company. The following information is
available concerning the wages systems:
• Workers on each site are controlled by a foreman. The foreman has a record of all employee numbers and
can issue temporary numbers for new employees.
• Any overtime is calculated by the computerized wages system and added to the standard pay.
• The two staff in the wages department make amendments to the computerized wages system in respect of
employee leave, illness, as well as setting up and maintaining all employee records.
• The computerized wages system calculates deductions from gross pay, such as employee taxes (PAYE),
and other statutory deductions.
• Finally, a list of net cash payments for each employee is produced. Cash is…
QUESTION 1
Kofi Kwakye is a 17-year old final year Senior High student from a wealthy home. His academic life had been
quite eventful, as he had been part of the top 10 students in his class and had dropped to be part of the last 10
students during the past school term. On 28th May 2022, in the heat of the preparation towards the final
examination, Kofi Kwakye took exeat from school to acquire some "provisions" to enable him cope during the
final exam period, which was three months ahead. He entered a shop in Accra and, instead of focusing on the
"provisions", he purchasee the following items: Microsoft Xbox, the latest iPhone, and a three-piece suit by
Pierre Cardin.
Kofi Kwakye did not have enough money to pay for all the items at once. He, therefore, agreed with the shop
owner, Mr. Ametepe, to pay the outstanding amount owed in five instalments. However, after paying the first
instalment, Kofi Kwakye fell into arrears. The two parties then entered into another arrangement under…
QUESTION TWO
*
Blue Inc. produces a product that has a 6 month demand cycle, as shown below.
Each unit requires 10 worker hours to produce, at a labour cost of K6, 000 per hour
regular rate or K9, 000 per hour overtime rate. The total cost per unit is estimated at
K200, 000 but units can be subcontracted at a cost of K208, 000 per unit. There are
currently 20 workers employed in the subject department, and hiring and training
costs for additional workers are K300,000 per person; whereas layoff costs are
K400,000 per person. Company policy is to retain a safety stock equal to 20% of the
monthly forecast, and month's safety stock becomes the beginning inventory for the
next month. There are currently 50 units in stock carried at a cost of K2, 000 per unit
month. Unit shortage, or stockpots, has been assigned a cost of K20, 000 per unit
month.
February March April
400
100
21
21
168
May
200
22
176
June
300
20
January
300
Forecast demand
500
Work days
22
19
176
152
168
160
Work hour at 8…
Chapter 13 Solutions
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Ch. 13 - Prob. 1DQCh. 13 - Why are SOP teams typically cross-functional?Ch. 13 - Prob. 3DQCh. 13 - Prob. 4DQCh. 13 - Prob. 5DQCh. 13 - Prob. 6DQCh. 13 - Question: 7. What is level scheduling? What is the...Ch. 13 - Question: 8. Define mixed strategy. Why would a...Ch. 13 - Prob. 9DQCh. 13 - Prob. 10DQ
Ch. 13 - Question: 11. What is the relationship between the...Ch. 13 - Prob. 12DQCh. 13 - Question: 13. What are major limitations of using...Ch. 13 - Prob. 14DQCh. 13 - Question: 13.1 Prepare a graph of the monthly...Ch. 13 - Prob. 2PCh. 13 - The president of Hill Enterprises, Terri Hill,...Ch. 13 - Prob. 4PCh. 13 - Prob. 5PCh. 13 - Prob. 6PCh. 13 - Prob. 7PCh. 13 - Prob. 8PCh. 13 - Prob. 9PCh. 13 - Question: 13.10 The SOP team (see Problem 13.9)...Ch. 13 - Prob. 11PCh. 13 - Prob. 12PCh. 13 - Prob. 13PCh. 13 - Question: 13.14 Jerusalem Medical Ltd., an...Ch. 13 - Prob. 15PCh. 13 - Prob. 16PCh. 13 - Prob. 17PCh. 13 - Question: 13.18 Jose Martinez of El Paso has...Ch. 13 - Prob. 19PCh. 13 - Prob. 24PCh. 13 - Prob. 25PCh. 13 - Prob. 26PCh. 13 - Prob. 1CSCh. 13 - Prob. 2CSCh. 13 - Prob. 1VCCh. 13 - Prob. 2VCCh. 13 - Question: 3. What are some concerns the team needs...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- QUESTION 1 The enrollment of the new students at ABC University has increased steadily over the past few years. The university would like to plan the workforce for academicians for year six to year eight. The reyulalury buuy, Malaysian Acuredilaliun Ayency (MQA) has set the standard of the ratio between academicians and student to be 1:50. The data below show the number of students enrolled for the past five years. Year Demand 4500 5000 5200 1 2 3 4 5600 5800 The university's administration considers using simple regression analysis to forecast the number of students enrolled in the next three years. a) Use simple linear regression to forecast the annual number of students enroll for the next three years. b) Determine the correlation coefficient for the data and interpret its meaning. c) Determine the coefficient of determination for the data and interprot its moaning. d) Determine the number of academicians that can fulfill the MQA standard for year six.arrow_forwardQUESTION 1 According to the time-based strategy, check out this scenario. if the processing time is reduced from 2 hours per a product, to only 1 hour per product, the time to market will be longer and customer service is not enhanced O True O False QUESTION 2 Quantity Year 1 Year 2 J F M A M J JASOND Months O True O False O Not enough information Based on theabove figure, the demand pattern is seasonal in which you can notice that April month in year 2 has the highest possible demand value.arrow_forwardQuestion 4.4 Montreal Hardware Co. is making a make-or-buy decision. The market feedback shows that the optimal price for this item is $10 each. If the item is outsourced to Laval Hardware Co, there is virtually no cost other than the $6 per unit that they would pay Laval Hardware Co. Internally, they have two choices. Process A requires an investment of $120,000 for design and equipment, but it results in a $4 per unit cost. Process B requires only a $100,000 investment, but its per unit cost is $5. Regardless of whether the item is subcontracted or produced internally, there is a 50% chance that they will sell 50,000 units, and a 50% chance that they will sell 100,000 units. Draw the decision tree appropriate to the alternatives and outcomes stated. Using the decision tree and EMV, what is their best choice?arrow_forward
- PRODUCTION AND OPERATIONS MANAGEMENT Q5LAB 1arrow_forwardQuestion no 1: Nuts & Legumes is one of the major suppliers of pulses and dry fruits in Pakistan. Overhead is applied to jobs on the direct labor cost basis as they are using a job-order costing system. An estimated $330,000 of manufacturing overhead for an estimated activity level of $200,000 direct labor dollars and this data is used to calculate the predetermined overhead rate. Opening inventory balances were as follows: Finished goods . . . . . . . . . . . . . . . . . . . . $40,000 Work in process . . . . . . . . . . . . . . . . . . . . $10,000 Raw materials . . . . . . . . . . . . . . . . . . . . . $25,000 During the year, the following transactions were completed: Raw materials requisitioned for use in production, $280,000 (21.43% of this material were indirect). They purchased Raw materials of $275,000. From A&H foods. Human resource department provides the following data: Total Labor Cost was $252,000 out of which $72,000 was indirect labor Sales…arrow_forwardQuestion 2: A manufacturing company produces 2 products, air conditioners and fan heaters: Each air-conditioner requires 3 hrs of wiring and 2 hrs drilling. Each heater needs 2 hrs wiring and 1 hr drilling. During the next production period, there are 240 hrs of wiring time available and 140 hours of drilling time. Each air-conditioner sold yields a profit of 25€. Each heater can be sold for 15€. Formulate this production-mix Linear Programming problem and find the combination of air-conditioners and heaters which gives the most profit.arrow_forward
- Question 4 b) Company ABC wishes to evaluate whether to produce a component internally or purchase from a vendor. The firm has the following options: Internal Production Process 1 Process 2 Purchase from Vendor Vendor 1 Vendor 2 Vendor 3 Variable cost of $17 per unit; annual fixed cost of $200,000 Variable cost of $14 per unit; annual fixed cost of $240,000 Offers a price of $20 per unit for any volume up to 30,000 units Offers a price of $22 per unit for 1,000 units or less, and $18 per unit for large quantities Offers a price of $21 per unit for the first 1,000 units and $19 per unit for additional units If the annual demand is 10,000 units, which alternative would be best from a cost standpoint? For 20,000 units, which alternative would be best?arrow_forward3. Your independent oil and gas company is considering the purchase at time zero of a 100 % working interest in a property. If you elect to develop the lease for an 87.5% revenue interest, the following costs will be incurred: in time zero, the lease bonus cost is $100,00o, intangible drilling costs are estimated at $550,000 while tangible completion costs are estimated at $300,000. Operating costs are estimated to remain constant at $8.00 per barrel (includes production costs, severance taxes and ad-valorem taxes) in each of years 1, 2, 3 and 4. Oil prices are forecasted to be $50.00 per barrel in each of years 1, 2, 3, and 4. Production is summarized in the following table. The escalated dollar minimum rate of return is 12.0%. Use net present value analysis to determine if the acquisition and development of this lease is economically viable: (a) Before considering income taxes, (b) Assuming income tax rate of 30%. (Expense 100% of intangible drilling costs at the end of first year,…arrow_forwardQUESTION 1 A master production schedule shows the following information MPS Week Week Week Week Beginning inventory = 300 31 Forecast 1.000 1,200 1,300 1.200 800 700 Actual customer orders Projected on-hand inventory Available to promise 800 1,000 MPS Based on the information in the MPS, what is the amount that is available to promise in week 4? O a. 1,200 Ob.700 Oc. 1.500 O d. 500arrow_forward
- Question 3 Best Technology (BT) is a leading manufacturer of adhesives used in a variety of industrial applications. BT produces two types of industrial adhesives in its Texas plant for the US market. The two types of adhesives are produced using the same production technology and equipment. They have identical characteristics except their adhesive strengths which are determined by the last production step of mixing with different chemicals. The demands for the two types of adhesives are independent and their weekly demands in the US distribution centre (DC) are approximately normally distributed with their means and standard deviations given below. Adhesives Type I Adhesive Type II Adhesive Mean (kg) Standard Deviation (kg) 9,000 10,000 4,000 3,000 The replenishment lead time of the adhesives from BT's manufacturing plant to the US DC is 4 weeks. The current adhesive production cost is $100/kg, the cost of shipping the adhesive from the plant to the DC is $20,000, and the annual…arrow_forwardQ/Choose a suitable question for each of the following answers. 1-Harry works for an international company in Dallas. * Where Harry is working and in which place? For what company Harry does work and where? For what and where does Harry work ? Does Harry work in an international company in Dallas?arrow_forwardQuestion 6 only questions in redarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.