Question
Chapter 10, Problem 9P
a)
Summary Introduction
To draw: An activity chart to change the right rear tire on an automobile with only one person working
Introduction: Activity chart is the type of chart that is used to observe the present method and propose improvement. The study helps to improve the utilization of machine, operator, and the combination of machine and operator.
b)
Summary Introduction
To draw: An activity chart to change the right rear tire on automobile with two people working
Introduction: Activity chart is the type of chart that is used to observe the present method and propose improvement. The study helps to improve the utilization of machine, operator, and the combination of machine and operator.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A Methods and Measurements Analyst needs to develop a time standard for a certain task. The task involves use of a ruler, square, and portable electric saw to mark and cut the "notch" in a rafter (a standard carpentry task of home construction). In a preliminary study, he observed one of his workers performing this task five times. The observations were made in an air-conditioned, well-lit training facility, at ground level, with all tools and equipment clean and readily available.
Observation:
1
2
3
4
5
Task time (seconds):
82
74
80
83
76
a. What is the actual average time for this task?
b. What is the normal time for this task if the employee worked at a 20% faster pace than is typical for adequately trained workers?
c. What is standard time for this task if allowances sum to 14%?
d. If the analyst then thought more carefully about his experiment and decided that the allowances needed to be increased to match the real (outside, not air-conditioned)…
What is the answer of this question ?
Claudine Soosay recorded the following times assembling a watch:
Observation No.
1
2
3
4
5
6
7
8
Performance rating is given as 95%.
a) The average time of Claudine for the operation =
Time (minutes)
0.11
0.09
0.11
0.09
0.15
0.10
0.09
0.10
Observation No.
9
10
11
12
13
14
15
16
minutes (round your response to three decimal places).
Time (minutes)
0.11
0.09
0.11
0.10
0.11
0.12
0.14
0.10
Chapter 10 Solutions
EP PRIN.OF OPERATIONS MGMT.-MYOMLAB
Ch. 10 - Prob. 1EDCh. 10 - Prob. 1DQCh. 10 - Prob. 2DQCh. 10 - Prob. 3DQCh. 10 - Prob. 4DQCh. 10 - Prob. 5DQCh. 10 - Prob. 6DQCh. 10 - Prob. 7DQCh. 10 - Prob. 8DQCh. 10 - Prob. 9DQ
Ch. 10 - Prob. 10DQCh. 10 - Prob. 11DQCh. 10 - Prob. 12DQCh. 10 - Prob. 13DQCh. 10 - Prob. 14DQCh. 10 - Prob. 1PCh. 10 - Prob. 2PCh. 10 - Prob. 3PCh. 10 - Prob. 4PCh. 10 - Prob. 5PCh. 10 - Prob. 6PCh. 10 - Prob. 7PCh. 10 - Prob. 8PCh. 10 - Prob. 9PCh. 10 - Prob. 10PCh. 10 - Prob. 11PCh. 10 - Prob. 12PCh. 10 - Prob. 13PCh. 10 - Prob. 14PCh. 10 - Prob. 15PCh. 10 - Prob. 16PCh. 10 - Prob. 17PCh. 10 - Prob. 18PCh. 10 - Prob. 19PCh. 10 - Prob. 20PCh. 10 - Prob. 21PCh. 10 - Prob. 22PCh. 10 - Virginia College promotes a wide variety of...Ch. 10 - Prob. 24PCh. 10 - Prob. 25PCh. 10 - Prob. 26PCh. 10 - Prob. 27PCh. 10 - Prob. 28PCh. 10 - Prob. 29PCh. 10 - Prob. 30PCh. 10 - Prob. 31PCh. 10 - Prob. 32PCh. 10 - Prob. 33PCh. 10 - Prob. 34PCh. 10 - Prob. 35PCh. 10 - Prob. 36PCh. 10 - Prob. 37PCh. 10 - Prob. 38PCh. 10 - Prob. 1CSCh. 10 - Prob. 2CSCh. 10 - Prob. 3CSCh. 10 - Prob. 4CSCh. 10 - Prob. 1.1VCCh. 10 - Prob. 1.2VCCh. 10 - Prob. 1.3VCCh. 10 - Prob. 2.1VCCh. 10 - Prob. 2.2VCCh. 10 - Prob. 2.3VCCh. 10 - Prob. 2.4VC
Knowledge Booster
Similar questions
- Are there any ethical and/or privacy concerns with worker-tracer wristbands?arrow_forwardAn analyst has been asked to prepare an estimate of the proportion of time that a turret lathe operator spends adjusting the machine, with 90% confidence level. Based on previous experience, the analyst believes the proportion will be approximately 30%. a. If the analyst uses sample size of 400 observations, what is the maximum error that will be associated with the estimate? b. What sample size would the analyst need in order to have the maximum error be no more than +/- 5%?arrow_forwardK Claudine Soosay recorded the following times assembling a watch: Observation No. 1234567co 8 Time (minutes) 0.12 0.10 0.11 0.11 0.15 0.10 0.10 0.10 Observation No. 9 10 11 12 13 14 15 16 Time (minutes) 0.11 0.08 0.11 0.10 0.10 0.11 0.14 0.08arrow_forward
- The concept of quality of work life (QWL) includes a. reducing stress b. reducing monotony c. improving balance between work and family life d. all of the options are correctarrow_forwardDescribe the steps involved in conducting a work sampling study.arrow_forwardsubject: quality control What evidence is there that Six Sigma has been implemented in how many organizations in the world?arrow_forward
- II. Exercise You have been asked to develop a work sample for a receptionist position in a three-person law firm. The lawyers believe this might be the best way to evaluate applicants, especially because they are seeking someone with a disability and they do not believe in the practical credibility of standardized measures. 1. What information do you need to design the work sample? 2. What materials do you need? 3. What are the criteria for your observation schedule as the consumer performs the work sample?arrow_forwardPrepare a run diagram for this emergency call data. Use five-minute intervals (i.e., count the calls received in each five- minute interval. Use intervals of 0-4, 5-9, etc.). Note: Two or more calls may occur in the same minute; there were three operators on duty this night. What can you conclude from the run chart? Call Time Call Time Call Time 1 2 3 4 5 6 7 8 9 10 11 1:03 1:06 1:09 1:11 1:12 1:17 1:21 1:27 1:28 1:29 1:31 12 13 14 15 16 17 18 19 20 21 22 1:36 1:39 1:42 1:43 1:44 1:47 1:48 1:50 1:52 1:53 1:56 23 24 25 26 27 28 29 30 31 32 33 1:56 2:00 2:00 2:01 2:02 2:03 2:03 2:04 2:06 2:07 2:08 Call 34 35 36 37 38 39 40 41 42 Time 2:08 2:11 2:12 2:12 2:13 2:14 2:14 2:16 2:19 a. re-organize the above data for your analysis (using five-minute intervals; 0-4, 5-9, etc) b. Provide your diagram that shows the number of emergency calls by eacn five-minute intervals from 1am to 2:20am c. what can you conclude from the chart?arrow_forward. Given the following information, determine the sample sizeneeded if the standard time estimate is to be within 5 percent ofthe true mean 97 percent of the time. Work Element Standard Deviation (minutes) Mean Observed Time (minutes)l 0.20 1.102 0.10 0.803 0.15 0.904 0.10 1.00arrow_forward
- What situations call for the use of work sampling instead of time study?arrow_forwardTime left 1:06:0- In a fabric manufacturing factory, the quality control process using control charts from SPC. In an hour there are a total of 5 samples are taken each having 4 observations regarding the thickness of fabric in measured in millimeters. In a particular hour, the sample means (X-bar) are noted to be: 156.46, 199.62, 189.31, 102.22, and112.09 respectively. In the same sample, the corresponding ranges are: 11.97, 12.17, 13.94, 11.86, and 11.83 respectively. What are the lower and upper control limits for the R chart? O a. 0,28.17 O b. 0,31.17 OC None is correct O d. 0,24.71 O e. 0,30.47 Of. 0,29.17 US PAGE NEXT PAGE O # C a pe here to search Prt F10 F12 %23 & 2 . 3 5 6 V. 8. R T. Y U P 41 S F J G y H K L / C V } BYN i 10 Alt Alt Ctrlarrow_forwardEach year, Lord & Taylor, Ltd., sets up a giftwrapping station to assist its customers with holiday shopping. Preliminary observations of one worker at the stationproduced the following sample time (in minutes per package):3.5, 3.2, 4.1, 3.6, 3.9. Based on this small sample, what number of observations would be necessary to determine the truecycle time with a 95% confidence level and an accuracy of{5%?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.